Key Takeaways

  • A business premise license (lesen premis perniagaan) is the local council's permission to run a trade, business or industry from one address. For a factory or warehouse it is issued as an industrial or storage licence, and councils such as MBSA and DBKL combine it with the signboard licence into one composite licence (Lesen Komposit).
  • Councils ask for your SSM documents, the applicant's IC, the building's CCC or CF, a stamped tenancy agreement or SPA, photos, a location plan and a floor plan in square metres. Risky activities also need letters from agencies such as the DOE, Bomba or the police.
  • A factory licence is never instant. MBSA's charter allows 30 working days for a business or industrial licence, MBDK allows 14 days for a temporary industrial licence and 30 days for the full one, and MBSJ tables factory applications at a technical meeting within 14 working days. The clock starts only when the file is complete.
  • The signboard must use Malay wording checked by Dewan Bahasa dan Pustaka (RM30 per council on DBP Sah Bahasa), and MBSJ and MBPJ require the Malay words to be 30% larger than any other language.
  • The rejection reasons councils publish are about the building, not the forms: no CCC, partitions or extensions without approval, fire safety gaps, the wrong building status for the activity, or noise and nuisance.

This guide explains what the council asks for when you license a factory or warehouse in Selangor or Kuala Lumpur, using the published checklists of MBSA (Shah Alam), MBSJ (Subang Jaya), MBPJ (Petaling Jaya), MBDK (Klang) and DBKL. For the wider picture of SSM registration, WRT approval and the manufacturing licence, read our trade license guide for factories and warehouses. This is general information, not legal advice; confirm your own case with the council's licensing department.

What is a business premise licence and who issues it?

The licence comes from the local council (PBT), not from SSM or a federal ministry. Section 102 of the Local Government Act 1976 lets every council make by-laws to "control and supervise, by registration, licensing or otherwise" a trade, business or industry that could be a source of nuisance, and to "regulate, license, restrict, prevent or remove the exhibition of advertisements". Section 107 then sets the ground rules every council works under:

  • The council may set the licence fee and inspection charges.
  • Every licence carries whatever conditions the council thinks fit, and the council may revoke it at any time.
  • The council may refuse to grant or renew a licence without giving a reason.
  • A licence is valid for no more than three years.
  • The licence must be displayed in a prominent place on the premises. Failing to display or produce it is an offence with a fine of up to RM500, up to six months in jail, or both.

Each council then applies its own by-laws. MBSJ, for example, licenses factories under the Undang-Undang Kecil Pelesenan Tred, Perniagaan dan Perindustrian (MPSJ) 2007 and the Undang-Undang Kecil Iklan (MPSJ) 2007.

What each council calls it

Council Name of the licence How you apply
MBSA (Shah Alam) Lesen Komposit (Perniagaan / Perindustrian), premises plus signboard Form at the Gerbang Perkhidmatan Shah Alam counter, ground floor, Wisma MBSA, with four copies of every document; status on eLesen
MBDK (Klang) Lesen Sementara Industri, then Lesen Industri Berisiko See our MBDK licence guide
MBSJ (Subang Jaya) Lesen Perniagaan dan Iklan; industrial premises and factories are Category B Online
MBPJ (Petaling Jaya) Composite premises and signboard licence eLesen online
DBKL (Kuala Lumpur) Lesen premis; Lesen komposit for premises plus signboard elesen.dbkl.gov.my

Not sure which council covers your unit? DBKL's own advice is to check the assessment tax (cukai pintu) bill, which names the council.

The licence belongs to the business and the address

DBKL states that a licence is issued for the premises address and cannot be moved to another location, and MBSJ's industrial licence conditions say it cannot be transferred without the council's written consent. So a new tenant or a buyer applies afresh, even if the previous occupier was licensed.

What documents does the council ask for?

The standard list

MBSA's general checklist for business, industrial and signboard licences, amended 29 August 2025, is the most detailed published list in Selangor:

  1. The completed application form, signed and stamped with the company chop.
  2. One passport-size photo.
  3. A copy of the IC, front and back. Non-citizens give a passport and a work visa endorsed by the Immigration Department. Copies are crossed and marked "Urusan MBSA Sahaja".
  4. The full set of SSM documents (or ROS, SKM or other registration).
  5. The latest MBSA assessment tax bill for the premises.
  6. The current tenancy agreement, or the SPA for the building, stamped by LHDN.
  7. The Certificate of Fitness (CF) or the Certificate of Completion and Compliance (Form F).
  8. Current photos of the premises: front, back, inside and side.
  9. A location plan (a Google Maps print is accepted if the premises is marked).
  10. An up to date floor plan with measurements in square metres.
  11. Approval letters for partitions or other additions and alterations, or "TB" (not applicable) if there are none.
  12. For a signboard: the design with measurements, a photo of where it will go, and the Dewan Bahasa dan Pustaka verification letter.
  13. An authorisation letter on company letterhead if someone else handles the application.

MBSJ's factory licence guideline asks for almost the same set, and its application form has a separate "Lesen Stor / Gudang" section where you declare the building type, floor area and the type of goods stored. DBKL asks for SSM documents, the IC or passport, the DBP verified signboard design if any, and two exterior and two interior colour photos in 4R size. For activities on a vacant lot, in a detached building or after a change of use, DBKL also asks for the Development Order (DO).

Use a tenancy agreement that has been stamped: our tenancy stamp duty calculator shows what the stamping costs before you submit.

Letters from other agencies

When the activity carries risk, the council will not decide until the relevant agency has commented. MBSA's checklist lists, among others:

Activity Letter needed from
Processing, storing or producing hazardous or flammable material DOE (effluent discharge), Bomba (flammables, petroleum, solvent, LPG), Atomic Energy Licensing Board (radioactive material)
Storing firearms or explosives Ministry of Home Affairs and the Royal Malaysia Police
Used goods, used cars and used parts Royal Malaysia Police
Waste collection MBSA's public cleansing and waste department

MBSJ adds printing works (DOE), solid waste processing (its urban services department), industrial spray painting (DOE support), and any non-industrial business in an industrial area (its planning department, for material change of use).

How much does a business premise licence cost?

Fees come from each council's by-laws, so there is no national rate. The published figures we found:

Item Fee Source
MBSA processing fee, business licence RM50 MBSA
MBSA processing fee, industrial licence RM100 MBSA
MBSA licence plate and sticker RM7 and RM5 MBSA
DBKL annual fee, manufacturing RM5.00 per m² DBKL
DBKL annual fee, workshops and engineering work RM5.00 per m² DBKL
DBKL annual fee, warehouse, store or storage of goods RM3.00 per m² DBKL
DBKL annual fee, office RM200 per unit DBKL
DBP language check for a premises signboard RM30 per council DBP Sah Bahasa

On DBKL's rates, a 1,000 m² warehouse works out to RM3,000 a year and the same floor licensed for manufacturing to RM5,000, which is why the floor area you declare matters. MBSJ charges by floor area (up to 500 m² or above 500 m²) and by activity (making or processing, wholesale or storage, selling or services) under the Second Schedule of its 2007 by-laws.

Workers measure a warehouse floor with a tape while a manager notes the area for the licence fee
IllustrationWorkers measure a warehouse floor with a tape while a manager notes the area for the licence fee

How long does approval take?

Council or route Published time Source
MBSA business or industrial licence Decision within 30 working days MBSA client charter, in force from 1 January 2024
MBSA non-risk (tidak berisiko) business licence Within 1 hour Same charter
MBDK temporary industrial licence 14 days MBDK licensing department
MBDK risk category industrial licence 30 days MBDK licensing department
MBSJ Category B (industrial premises and factories) Tabled at the Licensing Technical Meeting within 14 working days MBSJ factory guideline
Speed Selangor projects Full licence within 24 hours of the CCC being deposited Speed Selangor guideline, in force from 1 October 2025

Why it often takes longer

Every charter counts from a complete file. MBSA's application flow chart shows the path: the counter checks the file and returns it if incomplete; a complete file goes to the technical departments, which inspect the site; the case then goes to a meeting that approves or rejects it, and the decision letter follows. MPHS (Hulu Selangor) prints the same rule on its form: only complete applications are accepted for processing. Agency letters and renovation permits run on their own timetables, so collect them first.

Temporary licences

MBSJ can grant a six-month temporary licence while you wait for other technical approvals, such as permits for renovation, a ramp or partitions, building alteration approval and the internal sanitary system. The full licence follows once every condition is met. MBDK runs a similar two-stage route, explained in our MBDK guide.

Speed Selangor is different: it covers new industrial buildings in planned industrial areas that the state accepts as strategic, high impact projects. There, a temporary licence can be sought once construction reaches 80%, it lasts six months with up to six more, and machines may be installed for commissioning but not for full commercial production.

What are the rules for the signboard licence?

Applied together with the premises licence

MBSA's composite licence combines the premises licence and the signboard licence. MBPJ says the signboard licence must be applied for as a composite with the premises licence and cannot be applied for on its own. At DBKL, a separate premises signboard application needs a copy of a valid premises licence.

Language and layout

  • Malay first. MBSJ's advertisement by-laws require the national language on every advertisement, written 30% larger, placed first and shown more clearly than other languages, with correct spelling and grammar. MBPJ applies the same 30% rule. DBKL asks that Malay be given priority in size, colour and position.
  • Activity in Malay. A registered company name that is not in Malay need not be translated, but the activity must be stated in Malay. MBSA asks for the activity to be in Malay, 5% larger than the company name and placed above it.
  • Reference numbers. MBPJ wants the company name and SSM number at the bottom right and "MBPJ / account number / year approved" at the bottom left. DBKL asks for the licence reference at the bottom left and the company name and number at the bottom right.
  • DBP check before fabrication. MBSA, MBSJ, MBPJ and DBKL all ask for a design verified by Dewan Bahasa dan Pustaka. MBPJ rejects hand sketches and black and white prints.

Size, position and structure

  • MBSA: the sign must not block windows or glazing or rise above the roof, the structure needs a registered engineer's approval, Bomba's comment is needed for a large sign or one covering windows, and a two-sided sign on the side wall needs a signed consent letter from the neighbour.
  • MBPJ: signs go on walls and beams only, flashing lights are not allowed, and a structural permit is needed if the structure reaches the roof.
  • MBSJ: pylons, sky signs, facade signs and other external signs need a temporary advertisement permit and a structure permit from the building department.
  • DBKL: a sign standing on the ground must be at least 5 feet from the drain or road reserve, and a horizontal sign larger than 40 feet by 4 feet needs public liability insurance.

What the signboard licence costs

MBPJ's published annual rates: a non-illuminated sign up to 8 m² costs RM100, plus RM10 for each extra m² or part of one; an illuminated sign up to 8 m² costs RM150, plus RM15 for each extra m². A one-time deposit equal to the approved fee is paid with the first approval, and it can be claimed back when the business moves out, provided the sign has been taken down.

What stops a council from approving a factory licence?

Reasons the councils publish

DBKL lists the reasons its Licensing Committee rejects premises licences:

  1. A single staircase that does not comply with the Uniform Building By-Laws 1984.
  2. Additions and alterations without planning approval and building plan approval.
  3. Fire prevention and safety measures that do not meet Bomba's requirements.
  4. Noise and nuisance with no acoustic control.
  5. Not following the department's licensing guidelines.

And under section 107 of the Act, a council may refuse without giving any reason. MBSA publishes an appeal form (Borang Rayuan Permohonan Lesen Komposit) for applicants who want a decision reconsidered.

Factory specific traps

  • Wrong building status. The MPHS form states that any making or processing may only be done in premises with industrial or factory status. DBKL requires the premises to be outside a residential zone; if it is not, a change of use application goes to the City Planning Department first.
  • No CCC or CF. MBSA, MBSJ and MPHS all ask for it. In Shah Alam, a factory without one can only apply under the unauthorised factory (KTK) regularisation route, which needs a KTK confirmation form from the planning department. Our CCC guide explains how to check it.
  • Partitions, sheds and added space. MBSA requires a temporary building permit for partitions and awnings, and for terrace, semi-detached and detached factories, amended plans through the OSC for partitions, sheds or added space at the front, side or back. MBSJ requires a partition permit for any room of 6.5 m² or more, a permit for wall openings over 3 m, and does not allow drains to be covered completely.
  • Agency letters missing. A process that discharges effluent, stores solvents or LPG, or sprays paint will wait for DOE or Bomba.
  • Arrears on the unit. MBSA asks for the latest assessment tax bill, so ask the landlord to clear it before you apply.

The approvals behind these points (planning permission, building plans, Bomba and DOE) are covered step by step in our factory approvals guide. For the fire certificate side, see this Bomba fire certificate guide on klangindustrial.my.

A council inspector points at a shed extension built over a drain beside a terrace factory
IllustrationA council inspector points at a shed extension built over a drain beside a terrace factory

What changes for a factory or warehouse compared with a shop?

  • No instant approval. MBSJ issues instant licences (Category C, 453 activities) as six-month temporary licences, with an inspection after 7 days or within 21 days. Factories sit in Category B, which needs a site inspection and technical review before any decision.
  • Fees follow the floor area and the activity, so a large warehouse pays more than a shop, and manufacturing pays a higher rate than storage at DBKL.
  • Stricter running conditions. MBSJ's industrial conditions require all work to stay inside the premises, no living quarters, fire extinguishers to Bomba's specification sent for testing every year and hung 1 metre above the floor, flammables in approved self-closing containers, all wash water and liquid waste into the sewer, and no dust, fumes, odour or vibration that becomes a nuisance. Premises on a material change of use must renew their planning permission three months before it expires, and temporary building permits must be renewed before the licence can be.
  • Workers. Foreign workers must hold valid passes, the licensee must submit their number and names, and the licence may not be sublet to a foreigner.
  • Penalties. Breaking MBSJ's by-laws can bring a fine of up to RM2,000, jail of up to one year, or both, plus up to RM200 for each day the offence continues. DBKL's sequence is a compound notice, then a show cause letter, then cancellation of the licence.

How to prepare before you rent or buy

  1. Read the assessment tax bill to confirm which council you are dealing with.
  2. Ask the owner for the CCC or CF and the approved building plans, and compare them with what is on site, including partitions, mezzanines and sheds.
  3. Check that the building status suits your activity: making and processing need industrial or factory status.
  4. List the agency letters your process needs and start them early.
  5. Have the signboard design verified by DBP before you order the sign.
  6. Stamp the tenancy agreement or SPA, then submit a complete file.
  7. Plan for the charter period plus the time the agency letters take, and keep the deposit receipts.

Costs, tax and financing: more questions

Does the previous tenant's licence carry over when I rent or buy the factory?

No. The licence is issued to a business for one address and cannot be transferred without the council's written consent, so you apply in your own name. The previous licence is still useful evidence that the building has been licensed for a similar activity.

Frequently Asked Questions

Can an industrial property agent help me apply for a factory licence?

Partly. The council licence is issued to your business for that address, so your company applies, and no agent can promise approval, because the council may refuse without giving a reason. What an industrial agent can do is check before you sign that the unit can be licensed for your trade: the industrial land use, the CCC or CF, no unapproved extensions, and whether DOE or Bomba letters will be needed. The agent can also get the landlord's documents the council asks for. A previous tenant's licence does not carry over.

How do I apply for an MBSA business licence for a factory in Shah Alam?

Apply for MBSA's Lesen Komposit, which covers the industrial premises and the signboard together. Submit the form at the Gerbang Perkhidmatan Shah Alam counter, ground floor of Wisma MBSA, with four copies of each document: SSM papers, IC, latest MBSA assessment bill, stamped tenancy or SPA, CCC or CF, photos, location and floor plans, and the DBP-verified signboard design. The industrial processing fee is RM100 and MBSA's charter allows 30 working days from a complete file. Track it on eLesen.

How much does it cost to get a business license in Malaysia?

It depends on the council and the size of the premises. DBKL charges RM5.00 per m² a year for manufacturing and RM3.00 per m² for a warehouse or store, while MBSA charges a processing fee of RM100 for an industrial licence on top of the licence fee under its by-laws. Add the signboard licence and the RM30 DBP language check for the sign.

Is SSM registration a business licence?

No. SSM registers the business or company, but it does not permit you to operate from a particular building. You still need the local council's premises licence for the address, and SSM documents are one of the items the council asks for.

How long does it take to get a business premise licence for a factory?

Published timelines range from 14 days for MBDK's temporary industrial licence to 30 working days for MBSA's business or industrial licence, while MBSJ tables factory applications at a technical meeting within 14 working days. These count from a complete file, so agency letters and renovation permits add to the total.

How much is a signboard license in Malaysia?

At MBPJ, a non-illuminated sign up to 8 m² costs RM100 a year and an illuminated one RM150 a year, plus RM10 or RM15 for each extra m², with a one-time deposit equal to the fee. Other councils set their own rates under their advertisement by-laws, and the DBP language check costs RM30 per council.

Can a foreigner apply for a business premise licence?

DBKL says a foreign national with valid identity documents can apply, except for activities and locations on its restricted lists, and an application with non-citizen ownership must add a support letter from an agency such as MITI, MIDA, KPDN, InvestKL or Bank Negara, or a franchise registration. MBSA accepts a passport with a work visa endorsed by the Immigration Department in place of an IC.

Can I run my factory on a temporary licence?

Yes, for a limited time. MBSJ grants six-month temporary licences while technical approvals such as renovation or partition permits are pending, and MBDK issues a temporary industrial licence before the full one. The conditions must be completed within that period or the licence will not be converted.