Key Takeaways
- Under section 70 of the Street, Drainage and Building Act 1974 (Act 133), no one may erect a building without the council's prior written permission. The Act treats an addition with new foundations, a new or bigger roof or superstructure, an extra storey, or any departure from the approved plans as erecting a building.
- The penalties are heavy: up to RM50,000 or three years' jail (or both) under s.70(13), plus RM1,000 a day after conviction. Altering a building without permission carries up to RM25,000 and a court order to alter or demolish. Where the extension also needed planning permission, the Town and Country Planning Act 1976 (Act 172) allows a fine of up to RM500,000.
- Councils do act on factories. In February 2025 the Klang Royal City Council (MBDK) checked 533 industrial premises in and around Sungai Kapar Indah, issued 527 compounds and 59 notices, and told owners with illegal extensions to submit building plans or demolish.
- An unapproved extension sits outside the CCC, should be flagged by the bank's valuer and must be disclosed to your fire insurer. Standard fire policy wording can end cover on property whose fire risk was increased without the insurer's endorsement.
- To regularise, a principal submitting person (architect, professional engineer or registered building draughtsman) submits plans for the work as built and the council decides. Where no court case has started, Act 133 sets the penalty fee at five to 20 times the prescribed plan fee. Work the planning authority would have refused has to come down.
What counts as an illegal or unapproved extension in a factory?
Section 70(1) of Act 133 is short: "No person shall erect any building without the prior written permission of the local authority." What makes it bite for factory owners is the definition in s.70(16). A person is deemed to erect a building when they:
- add to or alter an existing building in a way that involves new foundations, or a new, partly new or bigger superstructure or roof on existing walls or foundations;
- depart, before or after completion, from any plan the council approved;
- build an additional storey, or rebuild an outer or party wall to the height of one storey;
- demolish and rebuild, or add to, more than half the wall and partition area, or more than half the floor area (excluding the ground floor) or roof.
Works done on the same building on two or more occasions within ten years may be added together. So a canopy one year and a mezzanine three years later can be treated as one reconstruction.
Seremban City Council (MBS) puts it plainly in its public FAQ: any construction, addition or renovation without council approval, or construction that does not follow the approved plan, is treated as a breach of section 70.
There is a second layer. Act 172 defines "development" as any building operation or any material change in the use of land or a building, and s.19 bans development without planning permission. Interior works escape that rule only if they do not change the use, the external appearance, the height or floor area, or the drainage, sanitation or soundness of the building (s.19(2)(a)). A mezzanine adds floor area, so it is outside that exemption.
Common factory additions and the rule they touch
| Addition | Why it needs approval |
|---|---|
| Steel roof or canopy over the front or side yard | New roof and superstructure (Act 133 s.70(16)). Some councils allow open awnings on a temporary permit (see the Selayang example below) |
| Mezzanine office or storage floor inside the bay | New superstructure, and more floor area, which takes it outside the planning exemption in Act 172 s.19(2)(a) |
| Extra floor on the office block | Additional storey (s.70(16)), more height and floor area |
| Side lane or back yard enclosed with walls and a roof | New foundations and roof; it can also break setback rules |
| Part of the factory turned into workers' quarters | Change of use (s.70(12)). Workers' accommodation also needs a certificate from the Labour Department under section 24D of Act 446 before anyone moves in (KPKT) |
| Internal partitions, new floor finishes | Interior works that change nothing on the list above need no planning permission; ask the council whether it wants a permit |
If the whole factory sits on agricultural land or was built without planning permission, that is a different problem: an unauthorised factory (KTK). See our guide to Selangor's KTK programme.
How do you spot unapproved works before you buy, rent or refinance?
- Ask for the approved building plans, any approved amendment plans, and the CCC (Form F) or the older CF. The CCC only covers what was built under approved plans. Our guide to what a CCC is explains the documents.
- Walk the site with the plans in hand. Compare the roof line, the number of bays, the floor levels and the yard. Look for a roof sheet of a different colour or age, steel columns standing in the yard, a roof edge running close to the boundary, a mezzanine with no staircase on the plans, and lanes that have been walled in.
- Ask whether the council has ever served a notice or compound. A council that wants an extension removed serves the notice on the owner of the land (s.72), so the owner should know about it.
- Check the use. Offices, canteens, showrooms or hostels inside a building approved as a factory may be a change of use.
- Read the valuation report. The Board of Valuers' standard on inspections says that where the valuer is aware of any breach of statutory requirements, it should be disclosed in the report.
What can the council do? Notices, compounds, fines and demolition
The MBDK operation in early 2025 shows how it usually starts. Its J-Force enforcement team inspected industrial premises around Sungai Kapar Indah from 3 February and, by 14 February, had issued 527 compounds and 59 notices under Act 133 and council by-laws for offences that included illegal extensions, storage areas without a licence and illegal signboards. Owners were told to submit building plans so the council could check them, or demolish the structures and restore the property to its original state (The Star, 26 February 2025).
If a notice or compound is ignored, the council can take the case to court. MBS explains that s.70(13) then applies.
The penalties in the law
| Law | What it covers | Maximum penalty |
|---|---|---|
| Act 133 s.70(11) | Altering a building without the council's written permission | Fine up to RM25,000, and a Magistrate's Court order to alter or demolish |
| Act 133 s.70(12) | Using a building or part of it for another purpose without permission | Fine up to RM25,000, plus up to RM500 a day after a notice to stop |
| Act 133 s.70(13) | Building in breach of the Act or by-laws, deviating from approved plans, ignoring a council order | Fine up to RM50,000 or jail up to 3 years or both, plus RM1,000 a day after conviction |
| Act 133 s.70(27)(f) | Occupying, or letting others occupy, a building or any part of it without a CCC | Fine up to RM250,000 or jail up to 10 years or both |
| Act 133 s.72(4) | Not complying with a council notice to stop or demolish | Up to RM250 for every day after the notice period |
| Act 133 s.73(2) | Erecting an unauthorised building that is later sold | Jail up to 2 years and a fine up to RM10,000; the court may order a refund to the buyer |
| Act 133 s.73(3) | Letting out an unauthorised building | Fine up to RM1,000 |
| Act 172 s.26 | Development without planning permission | Fine up to RM500,000 or jail up to 2 years or both, plus up to RM5,000 a day after the first conviction |
| Act 172 s.27(9) | Not complying with a notice to restore the land | Fine up to RM100,000 or jail up to 6 months or both, plus up to RM5,000 a day |
How demolition works
Under s.72 the council can serve a notice on the owner of the land to stop work, demolish within a set time, or take other steps. If the owner does not comply, the council may demolish the structure itself and recover the cost. Before it does, it must give the occupants at least 30 days' notice to vacate. Anything it removes is stored at the owner's risk and can be claimed within one month.
On the planning side, Act 172 s.27 gives the council two routes. If it would have refused planning permission anyway, it serves a notice requiring the land to be restored to its condition before the works. If not, it serves a notice inviting an application for planning permission, with extra fees on top of the normal ones.
The owner of the land carries the risk. Act 133 presumes that building work was carried out by the owner of the land (s.70(17)), and Act 172 deems the owner to have permitted the offence unless proved otherwise (s.26(2)).
How does an unapproved extension affect the CCC and the bank loan?
The CCC. Only the principal submitting person can issue a CCC, after supervising the work and making sure it matches the approved plans (s.70(20) and (21)). The KPKT CCC FAQ adds that the council can inspect and withhold the CCC where there is non-compliance. An extension built without plans was never supervised, so no CCC covers it. Occupying a building or part of it without a CCC is itself an offence under s.70(27)(f).
The loan. Banks lend against a panel valuer's report. Valuers are expected to disclose any breach of statutory requirements they are aware of. For valuations submitted to the Securities Commission, the asset valuation guidelines go further and require non-approved structures to be clearly marked on the layout plan. Once a report flags an extension, the bank can lend on the approved building only, ask for regularisation first, or decline. A refinance or top-up normally comes with a fresh valuation, so the same question comes back. Ask the bank before you pay a deposit.
Will your fire insurance still pay?
A factory policy taken by a company is a non-consumer insurance contract. Under paragraph 4 of Schedule 9 of the Financial Services Act 2013, before the policy is entered into, varied or renewed, the proposer must disclose any matter it knows to be relevant to whether the insurer accepts the risk and on what rates and terms, or that a reasonable person would know to be relevant. An extension built mid-term therefore has to be raised at renewal at the latest.
Policy wording adds two more traps. Using one insurer's standard fire policy as an example:
- Change in risk (Condition 9). If the circumstances affecting the insured building change in a way that increases the risk of fire, the insurance ceases to attach to the property affected unless the insurer has endorsed the change before the loss.
- Rebuilding rules (Condition 16). If the insurer cannot reinstate the property because of municipal or building regulations, it pays only what it would cost to reinstate the property if that could lawfully be done. Its public authorities extension also excludes costs where a council notice was served before the damage.
Tell your insurer about the extension in writing and get the endorsement. Our factory fire insurance guide covers sums insured and the average clause.
How do you regularise an unapproved extension, step by step?
- Collect what is on record: title, approved plans, CCC or CF, and any council notice or compound.
- Appoint a principal submitting person. KPKT lists architects, professional engineers and registered building draughtsmen.
- Check whether the extension can be approved at all. The PSP measures it and checks setbacks, plot ratio and use. If it adds floor area or changes the use, planning permission under Act 172 may be needed as well.
- Submit plans for the work as built, with the penalty fee. Where no court case has started, s.70(14) of Act 133 requires a payment of not less than five and not more than 20 times the prescribed fee, as the State sets it. The council must refuse plans submitted without it. In the model Uniform Building By-Laws 1984 (First Schedule, paragraph 17), the fee is ten times the normal fee where work started before approval, and paying it does not stop the council from prosecuting.
- Wait for the decision. The council should approve, refuse or ask for changes within three calendar months of submission. If it does not, the PSP may apply to the State Authority (s.70(18)).
- Rectify and certify. Carry out any changes the council requires. For works built under approved plans, the PSP supervises and issues the CCC, supported by Form G confirmations, including Bomba's (KPKT).
- If it is refused, remove the structure and restore the building, then update your insurer and bank.
A real example: Selayang's permit for factory awnings
Majlis Perbandaran Selayang's form JB-B04(A), updated on 5 March 2026, covers annual temporary permits for additions to factories, both new and "as built" (already on site):
- The addition must be an open awning, temporary rather than permanent, built of metal deck and steel tension. Grilles need their own permit.
- Minimum clearance from the gutter to the boundary: 10 ft at the front and 3 ft at the side and rear for detached and semi-detached factories; 3 ft at the front for intermediate terrace factories.
- Fee: RM10 for every 9 square metres, minimum RM300, plus a deposit of RM750 to RM1,500. The form's own example, a 10 m by 20 m addition, works out to RM222, so the RM300 minimum and a RM750 deposit apply.
- An as-built application must include the council's notice or compound, PSP-certified photos and plans, and a no-objection letter from the neighbouring lot. A tenant applying needs the owner's consent letter.
Other councils use their own forms and fees, so ask yours first.
Buyers, sellers, landlords and tenants: who carries the risk?
- Buyers: make the approval of every extension, or its removal, a condition in the SPA. See the clauses to check in a factory SPA.
- Sellers: a person who erected an unauthorised building that is later sold commits an offence under s.73(2), and the court can order a refund to the buyer. Regularise before you list.
- Landlords: letting out an unauthorised building is an offence under s.73(3), and notices are served on the owner of the land even when the tenant built the extension.
- Tenants: get the owner's written consent before any addition. Act 172 lets the council serve notices on the occupier too, although an occupier who is not the owner is not liable if they prove they did not carry out or permit the work.
Frequently Asked Questions
Is it illegal to extend a factory without council approval in Malaysia?
Yes. Section 70(1) of the Street, Drainage and Building Act 1974 says no one may erect a building without the council's prior written permission, and s.70(16) counts additions with new foundations, a new or bigger roof, extra storeys and departures from the approved plans as erecting a building. Additions that increase floor area or change the use may also need planning permission under Act 172.
What is the fine for an illegal extension in Malaysia?
Under Act 133 s.70(13), up to RM50,000 or up to three years' jail or both, plus RM1,000 for every day the offence continues after conviction. An alteration without permission carries up to RM25,000 under s.70(11), and development without planning permission can draw a fine of up to RM500,000 under Act 172. In practice the first step is usually a notice or compound.
Is the extension legal once I pay the council compound?
No. A compound settles the offence, but the structure still has no approval. MBDK told factory owners to submit building plans or demolish, and Selayang's as-built application asks for a copy of the compound alongside the plans. The model by-laws also say that paying the enhanced fee does not stop the council from prosecuting.
Is a CCC required for a renovation or extension?
A CCC is issued for building work carried out under approved building plans, by the principal submitting person who supervised it (Act 133 s.70(20) and (21)). Works the council allows under a permit, such as Selayang's annual permit for open awnings, are covered by that permit instead. An extension built without plans has neither.
Can the council demolish an illegal factory extension?
Yes. Under s.72 the council can order the owner of the land to demolish within a set time and, if the owner does not, demolish it and recover the cost. It must give the occupants at least 30 days' notice to vacate first. A Magistrate's Court can also make a mandatory order to alter or demolish.
Can I get a bank loan on a factory with an unapproved extension?
It is harder. The valuer should disclose the breach, and the bank may lend only on the approved building, ask for regularisation before release, or decline. Ask the bank and the valuer before you pay a deposit, and make regularisation a condition in the SPA.
Will my fire insurance pay if the extension was never approved?
It may not, in full. A business proposer must disclose relevant matters when the policy is taken, varied or renewed, and standard fire policy wording stops cover on property whose fire risk was increased without the insurer's endorsement. If building rules stop the insurer from reinstating, the payout is limited, and extra costs of meeting council rules are excluded where a notice was served before the damage.
What are the setback requirements for a factory canopy?
They depend on the council and the planning approval. As one example, Selayang's guideline for temporary factory awnings requires at least 10 ft from the gutter to the front boundary and 3 ft to the side and rear boundaries for detached and semi-detached factories. Your PSP checks the figures that apply to your lot.
This guide explains the law in general terms and is not legal advice. Ask a lawyer and a principal submitting person about your own factory.