Key Takeaways
- The Works Ministry is studying several private-sector proposals for new tolled highways that would form part of, or extend, the Federal Highway alignment. Works Minister Datuk Seri Alexander Nanta Linggi said they will go to the Cabinet soon.
- Based on 2025 traffic figures, the Federal Highway has an "F" grade for level of service. The minister linked this to rapid housing, industrial and commercial development along the road.
- There are no plans to widen the Federal Highway or to build elevated routes or stacked interchanges on it, because of land acquisition costs, the takeover of existing assets and the impact on residents and businesses.
- A RM332 million project will upgrade three intersections along Jalan Subang to Persiaran Jubli Perak (FT3214) in Petaling and add an elevated road in an area with heavy vehicle movements.
- No new route has been approved yet. Factories in Shah Alam Sections 15 and 16, HICOM-Glenmarie and Batu Tiga should plan lorry runs and check access carefully when they rent or buy.
What the Works Ministry said
In a written parliamentary reply dated Monday, 23 November 2026, Works Minister Datuk Seri Alexander Nanta Linggi answered Shah Alam MP Azli Yusof (PH). Azli had asked how the ministry plans to ease congestion on the Federal Highway as housing and commercial projects keep growing along it, and whether elevated routes or stacked interchanges could be built. The Edge Malaysia reported the reply on 24 November, and so did Free Malaysia Today.
The main points of the reply:
- New tolled highways. The ministry has received several proposals from private-sector parties for new highways involving sections of, or extensions to, the existing Federal Highway alignment.
- Cabinet next. The proposals will be refined and studied in detail before they are submitted to the Cabinet "in the near future".
- Grade F. Based on 2025 traffic figures, the Federal Highway received an "F" grade for level of service because of severe congestion. The minister pointed to the rapid development of housing, industrial and commercial areas along the highway.
- No widening. The government has no plans to widen the Federal Highway or to build elevated routes or multi-level interchanges along it. The minister cited the high cost of acquiring land in built-up areas, the acquisition of existing assets and the social impact on residents and business premises.
- Rail instead of more lanes. The ministry is focusing on optimising the existing road network and on other modes of transport, including the LRT Shah Alam Line (LRT3). The line began operating on 29 June 2026 between Johan Setia and Bandar Utama, with an interchange to the Kelana Jaya Line at Glenmarie.
- RM332 million Jalan Subang upgrade. A project will upgrade three intersections along Jalan Subang to Persiaran Jubli Perak (FT3214) in Petaling and build an elevated road to give alternative routes in an area with high traffic volumes and heavy vehicle movements. The minister said the new routes are expected to divert some traffic from roads including the Federal Highway and reduce pressure on the wider Shah Alam road network.
The reply did not name the companies behind the highway proposals, and it gave no alignments, toll rates or timelines. It also gave no completion date for the RM332 million project.
Why this matters for factories along the corridor
The Federal Highway runs from Klang through Shah Alam and Petaling Jaya to Kuala Lumpur, and several of Shah Alam's established industrial areas sit right beside it.
- Shah Alam Section 16 and its neighbour Section 15 are reached from the Padang Jawa interchange and the Klang-bound Section 15-16 exit. MBSA has named both sections for redevelopment.
- HICOM-Glenmarie Industrial Park in Section U1 joins the Federal Highway at the Batu Tiga interchange through Persiaran Kerjaya, and the LRT3 Kerjaya and Glenmarie 2 stations opened there on 29 June 2026.
- Subang Hi-Tech Industrial Park sits in Batu Tiga, beside the highway on the Subang Jaya and Shah Alam border.
For these estates, an "F" grade is not an abstract rating. It shows up in daily operations:
- Lorry trips to Northport and Westports in Port Klang, and to customers in Kuala Lumpur, take longer and are harder to schedule.
- Drivers spend more paid hours on the road for each delivery, and each lorry completes fewer drops a day.
- Shift workers who drive or ride to work arrive late more often, which matters for factories running two or three shifts.
The minister's answer also tells landlords and occupiers what not to expect. There will be no extra lanes on the existing road and no new flyovers above it. Relief, if it comes, will come from new tolled routes that are still proposals, from the RM332 million Jalan Subang upgrade, and from more people switching to LRT3.
What new tolled highways could mean
Because the proposals involve sections of, or extensions to, the Federal Highway alignment, any project that is approved will run through the same industrial belt. Three points are worth watching.
- Toll costs. A tolled route may save time, but haulage operators will weigh each toll against the time saved. If your business moves goods every day, budget for it once rates are announced.
- Land along the route. New highways usually need land, and the minister named land acquisition costs as a reason not to widen the current road. The alignments of the proposals have not been published. If you are buying a factory or industrial land close to the corridor, ask your lawyer to run a title search and check for any acquisition notice or road reserve that affects the lot before you sign.
- Construction years. Even after Cabinet approval, highway works bring lane closures and diversions. A factory with a lease renewal or an expansion planned should allow for temporary disruption.
Prices and rents in the corridor today
JPPH-registered transactions show what occupiers have been paying in the two areas closest to the busiest stretch. The figures come from the registered records available so far (latest month August 2026), not every deal, and every sale psf is per sq ft of land.
| Measure (24 months to Aug 2026) | Shah Alam | Subang & Glenmarie |
|---|---|---|
| Terrace factory median price | RM1.13 million (RM484 psf of land) | RM1.42 million (RM594 psf of land) |
| Semi-detached factory median price | RM5.92 million (RM514 psf of land) | RM7.41 million (RM706 psf of land) |
| Median factory rent | RM1.71 psf/month | RM2.00 psf/month |
| Registered factory tenancies | 119 | 115 |
The full breakdowns are on the pages for Shah Alam transaction prices and rents and Subang & Glenmarie transaction prices and rents. The data does not show how much of any price gap comes from road access, so treat traffic as one factor alongside location, size, power supply and title.
Practical steps for owners, tenants and buyers
- Time the trip before you sign. Before renting a factory beside the Federal Highway, drive the route to your port terminal or main customer at the hours your lorries will run. Note which interchange the unit uses and whether lorries must make a U-turn to head the right way.
- Look for a second way out. Some sections also reach KESAS, which gives you another route when the Federal Highway jams. Section 15, for example, reaches KESAS through the Hicom interchange.
- Use LRT3 when hiring. If your factory is near the Kerjaya, Glenmarie 2 or another LRT3 station, mention rail access in job adverts. The minister expects the line to reduce reliance on private cars.
- Check the title. When buying near the corridor, include a land search and a check for acquisition notices in your due diligence, and ask the seller in writing whether they have received any notice.
- Follow the Cabinet decision. The proposals are due to go to the Cabinet soon. Routes and tolls will matter more to your site choice than the headline that new highways are coming.
- Owners: list your access clearly. If you are letting or selling a unit near an interchange or an LRT3 station, state the exit used, the distance to the station and the lorry turning space in your listing. Tenants comparing units along a congested road look for exactly these details.
Frequently Asked Questions
Will the Federal Highway be widened?
No. In a written parliamentary reply on 23 November 2026, Works Minister Datuk Seri Alexander Nanta Linggi said there are no plans to widen the Federal Highway or to build elevated routes or multi-level interchanges along it. He cited the cost of acquiring land and existing assets in built-up areas and the social impact on residents and business premises.
What new highways are being proposed for the Federal Highway corridor?
The Works Ministry has received several private-sector proposals for new tolled highways that would form part of, or extend, the existing Federal Highway alignment. The proposals will be refined and studied in detail before they go to the Cabinet. Their routes, toll rates and timelines have not been made public.
What is the RM332 million Jalan Subang project?
It is a project to upgrade three intersections along Jalan Subang to Persiaran Jubli Perak (FT3214) in Petaling, Selangor, including an elevated road. The area carries high traffic volumes and heavy vehicle movements, and the alternative routes are expected to divert some traffic away from roads such as the Federal Highway. The minister did not give a completion date.
Does the Federal Highway congestion affect factory rents in Shah Alam?
The registered data does not separate the effect of traffic from other factors. JPPH-registered tenancies show a median factory rent of RM1.71 psf/month in Shah Alam and RM2.00 psf/month in Subang & Glenmarie over the 24 months to August 2026. Road access is one factor among several, alongside size, power supply and title.
Why does the Federal Highway have an F grade?
The minister said the "F" grade for level of service is based on 2025 traffic figures and reflects severe congestion. He linked it to the rapid development of housing, industrial and commercial areas along the highway. LRT3 and the Jalan Subang upgrade are the measures he named to ease the pressure.
FactoryHub is dedicated to helping every client find the right factory or warehouse. If you are weighing a factory along the Federal Highway in Shah Alam, Glenmarie or Batu Tiga, contact Peter Tan (REN 12771) at 016-666 6872.