Key Takeaways

  • Design and build means one contractor takes on both the design and the construction under a single contract, so the contractor answers for the design. In the traditional route your own architect and engineers design the factory first, then contractors tender to build it.
  • Built-to-suit means a developer or landlord builds a factory on its land to your specification, then leases or sells it to you. Published Malaysian deals show first lease terms of 5 to 20 years, often with renewal options.
  • A developer can build to your production needs if you put them in writing before the price is agreed: power, floor loading, clear height, cranes, loading bays, utilities and expansion. In a standard contract that brief becomes the Employer's Requirements, and changing it later is a variation you pay for.
  • Cost control lives in the contract: a fixed scope, a set method for valuing variations, retention (the CIDB 2022 form defaults to 5%), liquidated damages for late completion (capped at 10% of the contract sum by default) and a defects liability period (12 months by default).
  • Land filling has no official rate. The bill depends on the fill volume, the material and how far it travels, the ground underneath (soft clay sinks under new fill) and the approvals, so get a survey and an engineer's estimate before you agree a price for the land.

When no ready-built factory fits your process, there are two ways to get one built without managing every trade yourself: hire a design and build contractor to build on your own land, or ask a developer to build to suit and then lease or sell the factory to you. This guide explains both, what Malaysian built-to-suit deals show about lease length, what to put in your brief, how the standard contracts control cost and what drives the cost of filling industrial land.

It does not repeat the build or buy decision: construction cost per square foot, approvals, taxes and financing are in our guide on building versus buying a factory, and title, access, soil and flood checks are in our industrial land due diligence guide. This guide is general information, not legal advice. Ask your lawyer and quantity surveyor to review any building contract or lease before you sign.

What Is a Design and Build Factory?

A design and build factory is one where a single contractor is hired to both design and construct the building under one contract. You state what the factory must do; the contractor's team plans, designs and builds it, and the contractor stays responsible if the design falls short of what the contract requires.

JKR Putrajaya describes the two routes plainly. Under the conventional method, planning and design are done first by the owner's side, and the construction phase goes to a contractor appointed by tender. Under design and build (reka dan bina), the owner sets a needs statement, and the planning, design, construction and monitoring are then carried out by the contractor, with the owner acting as quality auditor during construction.

Design and build vs the traditional route (design-bid-build)

Traditional (design-bid-build) Design and build
Who designs Your own architect and engineers, hired separately The contractor, through its own or appointed designers
What contractors price A finished design, usually with drawings and quantities Your written requirements
Who answers for design faults Your designers The contractor
How you control the details You approve the design before tender Through the written requirements and design approvals
Standard forms available PAM Contract 2018 (with or without quantities), CIDB 2022 form AIAC Standard Form of Design and Build Contract (2018), PWD Form DB in government work, or a bespoke contract

Who carries the design risk?

The CIDB Standard Form of Contract for Building Works 2022 Edition shows how contractor design is handled in a Malaysian standard form. Its Option Module D, for works designed by the contractor, says:

  • The contractor is fully responsible for the suitability, adequacy, integrity, durability and practicability of its design, and carries the same liability as an independent architect or other professional designer would.
  • The contractor must obtain direct warranties from its design consultants in favour of the employer (the owner).
  • The employer must clearly set out the requirements the design is meant to meet, and the contractor may not build until its design documents have been accepted.
  • Acceptance of the design by the owner's representative does not relieve the contractor of its design responsibility.

Which standard contracts are used in Malaysia?

The ICLG Malaysia chapter on construction law (2026) lists the main forms: the PAM Contract 2018 (with and without quantities), which it says is among the most commonly used forms and is widely adopted in private building projects; the PWD forms, including PWD Form DB (Rev. 2007) for government design and build work; the AIAC Standard Form of Design and Build Contract (Main Contract) (2018 Edition); the CIDB Standard Form of Contract for Building Works (2022 Edition); IEM forms for engineering works; and FIDIC for international projects. It notes that the IEM, CIDB and AIAC forms are rarely used because the industry is more familiar with PAM, PWD and FIDIC. Most of these forms send disputes to arbitration.

What Is a Built-to-Suit Factory?

A built-to-suit factory is built by a developer or landlord on its own land to the specification of a known occupier, who then leases it (build-and-lease) or buys it (build-to-sell). The developer funds and manages the design and construction, and the occupier commits to the lease or purchase before the building goes up.

Selangor developers use the model. Sime Darby Property says its Bandar Bukit Raja industrial park in Klang included a 39-acre joint venture with Mitsui & Co consisting of built-to-suit lots, and that all 57 built-to-suit lots in one phase sold out within a day. In Negeri Sembilan, Tan & Tan told The Edge in February 2026 that future phases of its EKA Industrial Park in Labu will have sell-then-build and built-to-suit factories.

Route Who owns the land Who funds the building What you commit to Your control over design
Ready-built factory Seller or landlord Already built Purchase or lease of what exists Fit-out only
Built-to-suit lease Developer or landlord Developer A long lease signed before construction Through the agreed specification
Built-to-suit purchase Developer until transfer Developer, paid by you on agreed terms Purchase of a building not yet built Through the agreed specification
Design and build on your land You You A construction contract Through your requirements and design approvals

A built-to-suit lease lets a manufacturer get a custom building without paying for the land and construction itself. The developer recovers its cost through rent over the lease, so it asks for a firm commitment before it builds.

How Long Is a Built-to-Suit Factory Lease Usually Signed For?

There is no standard term in Malaysian law. In published Malaysian deals, built-to-suit leases have run from 5 to 20 years for the first term, often with options to renew: 20 years plus two five-year options for a Selangor data centre, 10 plus 5 years for a FedEx warehouse, and 5 years for a Johor factory.

Deal (when announced) Location What was built First term Renewal
Sime Darby Property and Pearl Computing Malaysia (December 2024) Elmina Business Park, Selangor, 77 acres Data centre 20 years Two further 5-year terms
Axis REIT and Upeca Aerotech (November 2017) Subang, Selangor, 7.02 acres Aerospace manufacturing facility with office, 178,978.6 sq ft 20 years Two terms of 6 years each
Axis REIT and FedEx (July 2019) Batu Kawan, Penang, 2.5 acres 44,000 sq ft warehouse built to FedEx's specifications 10 years plus 5 ("10 + 5") Included in the 10 + 5
Axis REIT, Banyan Estate Malaysia and FCI Connectors (December 2025) Senai, Johor, 2 acres Buildings of about 115,363 sq ft 5 years Not stated

Sources: Sime Darby Property, The Edge, Axis REIT Annual Report 2020 and The Star.

In the table, the 20-year terms went with the most specialised buildings: a data centre and an aerospace plant. According to The Edge, in the Upeca deal Axis REIT budgeted RM74.16 million for the building and estimated an initial net yield of 7% a year, with rent step-ups after year three, which shows how the rent is set to repay the developer's cost over the lease.

What the National Land Code says about long leases

Under section 221 of the National Land Code, a lease is for a term exceeding three years and is granted by an instrument in Form 15A. The maximum is 99 years for the whole of a lot and 30 years when the lease covers only part of it. Tenancies of three years or less fall under section 223 instead. If the land is charged to a bank, section 226 says the owner cannot grant a lease or tenancy without the chargee's consent, so ask early whether the developer's bank has agreed.

What to settle in a built-to-suit lease before construction starts

  • The full specification, attached to the agreement, and how changes you request later are priced.
  • The handover date, tied to the Certificate of Completion and Compliance (CCC), and what you receive if handover is late.
  • When rent starts, the step-ups, and how rent is set on each renewal.
  • Any option to renew or to buy the property (section 228 of the National Land Code covers options for renewal and for purchase of the reversion).
  • What you must remove or reinstate when the lease ends.

How long does a built-to-suit factory take to deliver?

Time depends on size and specification. For the FedEx warehouse, the agreement was signed on 15 July 2019, work started in August 2019, the CCC was issued on 28 February 2020 and the tenant moved in on 1 March 2020. The Senai buildings for FCI are targeted for completion within 24 months of the agreements, and the second Elmina data centre, agreed in December 2024, is targeted for 2027.

A developer hands over a newly built factory to its tenant at the open roller shutter
IllustrationA developer hands over a newly built factory to its tenant at the open roller shutter

Can You Ask the Developer to Build a Factory According to Production Needs?

Yes. That is what built-to-suit and design and build are for. Write your production needs down before any price is agreed: power, floor loading, clear height, cranes, loading bays, water and effluent, office space and expansion. The developer or contractor designs to that brief, and anything you add after signing is usually priced as a variation.

What to put in the brief

Need What to state Why it matters
Electrical load Every machine with its rating and running hours, plus planned lines Sets the TNB supply and substation; estimate it with our factory power calculator
Floor loading Heaviest machine, rack loads, forklift type, press foundations Sets slab thickness and piling; check it with our floor loading calculator
Clear height and column grid Racking height, crane hook height, widest machine Sets the steel frame and the building height
Overhead cranes Capacity, span and hook height The columns and runway beams must be designed for them
Loading Number of docks or roller doors, truck types, yard and turning space Sets the site layout and yard depth
Utilities Water use, gas, compressed air, effluent treatment, scheduled waste store Each needs space, connections and its own approvals
People Office, canteen, toilets, worker numbers per shift Sets parking and the office block
Expansion Land kept free, an end wall designed to extend Cheaper to plan now than to retrofit
Standards Any GMP, halal, cleanroom or green building target Affects finishes, ventilation and certification

FedEx's warehouse in Batu Kawan is an example of a tenant-driven brief: Axis REIT describes it as customised and built to FedEx's specifications, including a rainwater harvesting system for washing delivery trucks.

How the brief becomes part of the contract

Under Option Module D of the CIDB 2022 form, your written requirements are the "Employer's Requirements". The contractor submits its design documents, and your representative must approve, approve with corrections or ask for resubmission within 14 days; if nobody replies in time, the design is deemed approved. If your comments change the requirements, the contractor can ask for a variation instruction. If the contractor itself changes the design with your consent, any extra cost is the contractor's and any saving is yours. In practice: answer every design submission in writing and on time, and keep a single, updated copy of the requirements.

How Should You Split Production and Office Space in a Factory?

Size the office from the people who will sit in it and the production floor from the machine, racking and forklift layout, then compare the result with what the market builds. Across 424 FactoryHub listings in Selangor that state both the office area and the total built-up area (live listings on 15 November 2026), the office takes a median of 14% of the built-up area, and the share falls as buildings get larger:

Built-up area Listings Median office share Middle half of listings
Under 10,000 sq ft 19 22% 16% to 29%
10,000 to 30,000 sq ft 80 20% 15% to 30%
30,000 to 80,000 sq ft 190 15% 9% to 24%
Over 80,000 sq ft 135 8% 5% to 13%

These are asking listings, so they show what owners have built, not a rule you must follow.

What decides the split

  • Office headcount. Management, sales, purchasing, QA, design and admin staff, plus meeting rooms. Production staff mostly need changing rooms, toilets and a canteen, which you can list separately in the brief.
  • Where the office sits. An office block at the front or on a mezzanine over the loading side leaves the full-height floor for production and keeps visitors away from forklift routes.
  • Letting and resale. An office far larger than the norm for the building size is space the next tenant or buyer may not want to pay for.

Check the approved plan first

On industrial land the office is approved on the building plan as part of the industrial building, serving the production use. Before you enlarge it, or let part of the building to someone else as offices, check the approved building plan, the express condition on the title and the CCC with the council, because a change from industrial to office use may need a fresh approval.

How Do You Control Construction Costs When Building Your Own Factory?

Control cost in the contract before work starts: fix the scope and the brief, price on a standard form such as PAM 2018 or the CIDB 2022 form, agree how variations are valued, hold retention, set liquidated damages for delay and a defects liability period, and approve every change in writing before it is built.

Fix the scope, then manage variations

Under the CIDB 2022 form, a "variation" includes changes to design, quality or quantity, to levels, layout and dimensions, to the order of work or working hours, and a demand to finish earlier. A variation must be instructed in writing. ICLG notes that the right to vary must be written into the contract; without a variation clause, any change of scope needs a separate agreement.

The CIDB form values variations in this order:

  1. Contract rates, where the varied work is similar and done under similar conditions.
  2. Contract rates with a fair allowance, where conditions or quantities differ significantly.
  3. Fair market rates, where neither applies.
  4. Daywork rates with prior written instruction, plus 15% for the contractor's supervision, plant, overheads and profit unless the contract says otherwise.

Every late change you make lands in one of these four boxes, which is why a complete brief before signing is the cheapest cost control there is.

Retention, liquidated damages and security

Item What it does CIDB 2022 default if the Appendix is left blank
Retention A share of each payment held back until defects are fixed 5% retention percentage, up to the limit you set
Liquidated damages A fixed rate you can deduct for each day of late completion Total capped at 10% of the contract sum
Defects liability period The period in which the contractor must fix defects 12 months
Performance security deposit (Option Module F) Security for the contractor's performance 5% of the contract sum
Paying certificates Your deadline to pay a certified amount 21 days

Retention. ICLG describes the conventional Malaysian approach as holding 10% of each progress payment up to a total of 5% of the contract sum, releasing half at practical completion and the rest when defects are made good or the defects period ends. The CIDB 2022 form requires the employer to keep retention money in a separate bank account held on trust for the contractor.

Liquidated damages. Under section 75 of the Contracts Act 1950, as explained by the Federal Court in Cubic Electronics v Mars Telecommunications (2019), you are entitled to reasonable compensation up to the agreed sum without proving actual loss, but the contractor can show the sum is out of proportion to your likely loss. Base the daily rate on your real cost of delay, such as rent on your current premises and lost orders, and keep a note of how you worked it out.

Bonds. ICLG says performance bonds in Malaysia are usually payable on demand, and courts restrain a call only on narrow grounds such as fraud or unconscionability.

Payment disputes

Payment disputes under a written construction contract can go to statutory adjudication under the Construction Industry Payment and Adjudication Act 2012 (CIPAA), which ICLG says averages about 95 working days, and CIPAA makes "pay when paid" clauses void. Service tax and stamp duty on the construction contract are covered in our build or buy guide.

Lorries tip earth fill while a bulldozer and roller compact a raised industrial plot
IllustrationLorries tip earth fill while a bulldozer and roller compact a raised industrial plot

How Much Does It Cost to Fill Land for Industrial Land?

There is no official rate. The cost is the volume of compacted fill needed to raise the whole site to the required platform level, times a contractor's rate per cubic metre, plus ground treatment if the soil is soft, testing and approvals. The main drivers are volume, the fill material and its haul distance, and soft ground.

Step 1: work out the volume

One acre is about 4,046.86 m². The arithmetic below shows the compacted volume needed before any settlement:

Fill height 1 acre 2 acres 5 acres
0.5 m about 2,023 m³ about 4,047 m³ about 10,117 m³
1.0 m about 4,047 m³ about 8,094 m³ about 20,234 m³
2.0 m about 8,094 m³ about 16,187 m³ about 40,469 m³

The height comes from the platform level the council and JPS will require, compared with the existing ground and the road. Our due diligence guide explains how to check it. Ask every contractor whether the rate is per loose or per compacted cubic metre, because loose fill shrinks when compacted.

Step 2: allow for settlement on soft ground

On soft clay, the ground sinks under the new fill, so you pay for more fill than the height difference. A 2026 study by Universiti Teknologi Malaysia researchers on a site in Kuala Langat with about 20 to 25 m of soft marine clay calculated that 3.5 m of fill (platform fill plus surcharge) would settle 1,419 mm. With prefabricated vertical drains installed to about 25 m depth at 1.0 m spacing, 90% of the main settlement was expected in about four months.

A geotechnical paper by Ir. Tan Yean Chin of Gue & Partners explains why: the extra fill placed to make up for settlement adds load and causes further settlement, so engineers design the fill thickness by repeated calculation. The treatment options it lists include preloading, surcharging, vertical drains, staged construction, excavating and replacing soft soil, stone columns and piles. Each adds cost or waiting time, which is why a soil investigation should come before you agree a land price.

Step 3: the fill material and where it comes from

The National Land Code defines "rock material" to include common earth, sand, laterite, clay and soil. Under sections 70 to 72, extracting, removing and transporting it is done under a permit issued by the Land Administrator in Form 4C, and section 426 makes doing it without lawful authority an offence punishable by a fine of up to RM500,000, jail of up to five years, or both. Ask the contractor where the fill comes from and whether the source holds a permit.

For a published price point, the Department of Statistics Malaysia recorded average February 2026 prices in its central region (Kuala Lumpur, Melaka, Negeri Sembilan, Selangor and Johor) of RM69.40 per metric tonne for mining sand and RM77.27 per tonne for river sand, including transport for 30 km from the outlet. Fill hauled from farther away costs more, and sand is sold by the tonne while fill is measured in cubic metres, so compare quotes per compacted cubic metre placed on your site.

Step 4: approvals, testing and the boundary

Filling is earthworks. Under section 70A of the Street, Drainage and Building Act 1974, nobody may start earthworks without first submitting plans and specifications to the local authority and getting its approval. Budget for the engineer's design, compaction testing, and the drains, slopes or retaining walls needed where your platform ends up higher than the neighbours. On a developer's plot or a built-to-suit project, ask whether the land is handed over at platform level and who bears the cost if it settles later.

Common Mistakes to Avoid

  1. Signing design and build on a one-page brief. Everything missing from the requirements comes back later as a variation.
  2. Approving changes on site by word of mouth. Only written instructions count, and you lose control of the final cost.
  3. Leaving the liquidated damages rate blank or picking a number at random. Base it on your real cost of delay.
  4. Pricing land without the fill and ground treatment. A cheap plot on soft clay can need more fill, drains and months of settlement.
  5. Signing a long built-to-suit lease without registering it in Form 15A or without the developer's bank consent.

When you are ready to compare plots, browse industrial land for sale in Selangor and ask us to check zoning, access and power before you commit.

Frequently Asked Questions

What is a design and build factory in Malaysia?

It is a factory delivered under one contract in which the same contractor designs and builds it. You set out what the factory must do, and the contractor's team plans, designs and constructs it and answers for design faults. In the traditional route, your own architect and engineers design first and contractors then tender to build.

What does a design and build company do?

It takes your requirements and turns them into a finished building: design, approvals, construction and handover, using its own or appointed architects and engineers. Under the CIDB 2022 form's contractor design module, it must also give you direct warranties from its design consultants. You still approve its design submissions and pay for any change to your requirements.

What does built-to-suit mean for a factory?

A developer or landlord builds the factory on its land to your specification, then leases it to you or sells it to you. The developer funds and manages construction, and you commit to the lease or purchase before the building goes up. Selangor examples include built-to-suit lots in Sime Darby Property's Bandar Bukit Raja.

How long is a built-to-suit factory lease usually signed for?

Published Malaysian deals show first terms of 5 to 20 years. A Selangor data centre was leased for 20 years with two five-year renewals, an aerospace plant in Subang for 20 years with two six-year renewals, a FedEx warehouse for 10 plus 5 years, and a Johor factory for 5 years. Leases over three years are granted in Form 15A under the National Land Code.

Can I ask a developer to build a factory according to my production needs?

Yes. Give the developer a written brief before the price is agreed, covering power, floor loading, clear height, cranes, loading bays, utilities, staff facilities and expansion. Attach it to the agreement, because anything added after signing is usually priced as a variation.

How do I control construction costs when building my own factory?

Fix a complete brief, use a standard form such as PAM 2018 or the CIDB 2022 form, agree how variations are valued and only approve changes in writing. Hold retention, set liquidated damages based on your real cost of delay and keep a defects liability period, which the CIDB form sets at 12 months if nothing else is stated.

How much does land filling cost for industrial land in Malaysia?

There is no official rate. Work out the compacted volume (raising one acre by 1 m needs about 4,047 m³), get contractor rates per compacted cubic metre, and add ground treatment, testing and approvals. At one soft clay site in Kuala Langat, 3.5 m of fill was calculated to settle more than a metre, so the real volume can be larger.

Which contract form is used to build a factory in Malaysia?

Private building projects most often use the PAM Contract 2018, with or without quantities. Design and build work can use the AIAC Standard Form of Design and Build Contract (2018) or a bespoke contract, government projects use PWD forms such as PWD Form DB, and the CIDB 2022 form is also available.

Talk to Us Before You Build

Before you commit to a design and build contract or a built-to-suit lease, compare it with what is already standing. Peter and Jason can check whether a ready factory with the power and specification you need is available, look at the land you are considering for zoning, access and flood level, and put you in touch with the right professionals. This guide is general information and not legal advice; confirm the terms with your lawyer, quantity surveyor and engineer.

FactoryHub is dedicated to helping every client find the right factory or warehouse. Contact Peter Tan (REN 12771) at 016-666 6872 or Jason Low (PEA 1478) at 012-288 1834, registered with BOVAEP under CID Realtors Sdn Bhd.