Key Takeaways

  • Start with the title, not the site visit. The land must carry the category "industry" under section 52 of the National Land Code, and its express conditions must allow your kind of factory. Agricultural land needs a state-approved conversion first, and that is never guaranteed.
  • A converted title is not a building approval. You still need planning permission, which lapses after 12 months if work has not started, plus council approval for earthworks, roads and drains, and building plans.
  • Filling, piling and levelling are "earthworks". They need council approval under section 70A of the Street, Drainage and Building Act, with fines up to RM50,000 or five years' jail for working without it. No official price list for filling exists: it depends on the volume between today's ground and the platform level JPS and the council require.
  • Rivers and slopes take land away from you. JPS sets river reserves from 5 m to 50 m depending on river width, and in Selangor no development may go within the 50 m river reserve without written permission from the LUAS Director. Slopes above 35 degrees are closed to development except infrastructure.
  • Power decides the timeline. Above 350 kVA, TNB requires a new substation on your land, and from 1,000 kVA an 11 kV supply typically takes 6 to 12 months.

What should you check before buying industrial land, and in what order?

Check the paper first, then the planning position, then the ground. A title or planning problem can kill the purchase; a ground problem usually only raises the cost, so you want the deal-breakers answered before you spend on boreholes and surveys. Ask for these before you sign anything binding, or make the sale and purchase agreement conditional on them.

# What to check Where the answer comes from What can go wrong
1 Owner, category of land use, express conditions, encumbrances Official land search on e-Tanah or at the land office Category is agriculture, a condition bars your use, a caveat or charge is registered
2 Zoning in the local plan and any existing planning approval Council planning department or PLANMalaysia@Selangor Zoning does not fit your industry class; a layout approval has gone stale
3 Road frontage and legal access Title plan, certified plan, site visit Land is landlocked or reached only through someone else's lot
4 Power, water and sewerage TNB, Air Selangor, Indah Water No substation capacity nearby; long lead times
5 River, drain and other reserves JPS, LUAS, land office A reserve cuts the usable area
6 Ground level, flood history and required platform level Licensed surveyor, JPS, council Heavy filling needed before you can build
7 Soil and slopes Geotechnical engineer, boreholes, terrain map Soft ground, peat pockets or unstable slopes
8 Financing Your bank, in writing Lower margin or refusal on raw or unconverted land

Our guide to land searches on e-Tanah Selangor shows how to order and read the search for step 1.

Is the land converted to industrial use, and does the title allow your factory?

Look at two things on the title: the category of land use and the express conditions. Converted industrial land shows the category "industry" (on a Malay-language title, Perusahaan). If it shows "agriculture" or "building", a factory is not yet allowed on it.

What the category and conditions mean

The National Land Code has three categories of land use: agriculture, building and industry (section 52). Its implied conditions do the sorting: building-category land may not be used for industrial purposes (section 116), while industry-category land may be used only for industrial purposes, meaning factories, workshops, warehouses and similar buildings for manufacture, processing, storage, transport or distribution of goods, and the industry must start operating within three years of the date the land became industrial (section 117). For land in the building or industry category, section 122 lets the State Authority impose conditions on how much of the land may be built on, the type, design, height and structure of buildings, the dates by which a building must be started or completed, and the uses the building may be put to. Read every express condition, because a title can be in the industry category and still limit you, for example to a light industry use or a building deadline.

If the land is still agricultural

The owner can apply to the State Authority under section 124 to change the category. Approval is the state's decision, it comes with a premium and new conditions, and the clock under the idle-land rules starts once the land becomes industrial. Our industrial land conversion guide walks through the application. If you buy before conversion, tie the balance of the price to the approval and agree in the contract who pays the premium.

Title category is not the same as planning zoning

The title category is a land law control. Planning is separate: under section 19 of the Town and Country Planning Act 1976, nobody may carry out development without planning permission. The council checks your proposal against the local plan, so an industrial title in an area zoned for something else, or for a lighter class of industry than yours, is a problem to solve before you pay.

What planning conditions and approvals come with building a factory?

Expect four approvals from the council, often filed together: planning permission (KM), earthworks (KT), roads and drainage (JP) and building plans (PB). Majlis Perbandaran Selayang's 2026 planning application pack lets these be submitted at the same time when no land matters such as subdivision or conversion are involved.

Which agencies comment, and what they ask for

The same pack lists what each technical agency wants with a planning application:

Agency What it asks for
JPS (drainage) Stormwater management report and hydraulic calculations following MSMA
Indah Water Sewerage engineering report with population equivalent and layout
DOE EIA approval where the project needs one
JKR Traffic impact assessment for 45,000 sq ft of floor area or 200 units; road safety audit if the site fronts a federal or main state road; slope analysis and geotechnical report where relevant
Minerals and Geoscience Department Geological assessment where relevant
Air Selangor Water supply technical form
TNB Maximum demand calculation certified by a registered electrical engineer
LUAS Its own planning checklist
Malaysian Highway Authority Valid access approval if the site takes access from a highway

Faster approvals for factories in planned areas

Under the SPEED Selangor initiative described in the same pack, planning permission for factories, and for warehouses and logistics facilities that support manufacturing, can be approved in 9 days. The site must be in a planned area consistent with the local plan, have a layout (master plan) approval no more than five years old without substantive change, have a valid title free of restrictions, have infrastructure and utilities available and already have the technical agencies' support. This is the practical difference between "ready" land in an approved industrial layout and a raw lot: the ready lot can qualify for the fast track; the raw lot has to build the case from scratch.

Deadlines once you have approval

Planning permission lapses 12 months after it is granted if the development has not started, unless you apply to extend it before it lapses (section 24, Act 172). Before building starts, the structural plans, calculations and any other reports the council requires must be submitted (section 70(9A), Act 133). Our guide on building your own factory versus buying one covers the full approval route, construction cost and the CCC.

A consultant and a factory owner review a site layout plan on a cleared industrial plot
IllustrationA consultant and a factory owner review a site layout plan on a cleared industrial plot

Does the land have road access, power and water?

Ask for proof of each, not a verbal assurance. Raw land can be bought without utilities, but you then carry the cost and the waiting time of bringing them in.

Road access

Check that the lot touches a public road on the title plan, not only on the ground. If the only way in crosses a neighbour's lot, the National Land Code lets the owner apply to the Land Administrator in Form 28a for a private right of way between the land and a public terminal, which section 387 defines as the foreshore, a river, a railway station or a public road (sections 388 to 390). Compensation is payable to the owner whose land is used, as determined by the Land Administrator (section 393). This takes time and is not automatic, so a landlocked lot should be priced as one.

Electricity

TNB's Electricity Supply Application Handbook sets out when a development needs its own substation:

Maximum demand Substation requirement (ESAH 3.1, Table 3-2)
Up to 350 kVA A new 11/0.4 kV substation may be required, subject to TNB's system study
Above 350 kVA to below 1,000 kVA A new 11/0.4 kV substation is required
1,000 kVA to below 5,000 kVA 11/0.4 kV and/or 11 kV substations; a new main distribution substation (PPU) may be required

The substation land is transferred or leased to TNB at a nominal RM10. A TNB briefing published by MIDA gives typical lead times and land sizes: 11 kV supply for 1,000 to below 5,000 kVA takes 6 to 12 months and needs a 13.0 m by 14.2 m site; 33 kV for 5,000 to 25,000 kVA takes 18 months to 2 years on a 30 m by 30 m site; 132 kV takes 3 to 5 years. TNB notes that lead time depends on the distance and complexity of the site. Our TNB power upgrade guide explains the application and charges.

Water and sewerage

At planning stage, Air Selangor reviews a water supply technical form under the Water Services Industry (Water Reticulation and Plumbing) Rules 2016, and Indah Water reviews a sewerage report. Neither publishes a single cost for a new industrial connection. Ask each, in writing, where the nearest main or public sewer is, whether it has capacity for your demand, and who builds and pays for the pipe to your boundary.

Ready-infrastructure land versus raw land

Lot in an approved industrial layout Raw or isolated lot
Roads and drains Built to the approved layout You design, apply and build
Power Planned in the layout; check spare capacity Substation land and lead time are yours
Water and sewer Mains usually in the estate road Distance to the nearest main decides cost
Approvals Can qualify for SPEED fast track if criteria are met Full process, more agency reports
What to verify Layout approval date, conditions on your lot, platform level already built Everything in this guide

Is a soil investigation needed before buying industrial land?

Legally, the reports are triggered when you apply to build, not when you buy. Commercially, a site investigation before you commit is how you find out whether the price still works, because soft ground, buried rubbish or a high water table change the foundation design and the earthworks bill.

When the rules require ground reports

On hilly land, the PLANMalaysia guideline for hill and highland development requires a geotechnical investigation and slope stability analysis by a geotechnical engineer, geological mapping by a registered geologist, a drainage report following MSMA and an earthworks plan by a registered engineer. The Selayang planning pack asks for a JKR slope analysis and geotechnical report and a geological assessment "where relevant". Under the KPKT slope management guideline (2021), earthworks applications on Class III and IV slopes must include a slope stability or geotechnical report, and works on slopes steeper than 25 degrees with more than 10 m of vertical height need that report verified by an accredited checker. On flat land no rule we found sets a number of boreholes, but no engineer can design piles or a ground slab for heavy racking or machines without ground data, and the council may ask for any report it needs before building starts.

What a site investigation should tell you

  • The soil layers and how deep firm ground lies, which decides pile type and length
  • The groundwater level
  • How much the ground will settle under new fill and floor loads
  • Whether there is old fill, peat, soft clay or dumped material
  • Signs of contamination; a separate FactoryHub guide covers environmental site assessments

The cost depends on the number and depth of boreholes and the laboratory tests. Ask the seller for written permission to enter the land, and get a quote based on your building footprint.

How much does filling cost, and what are the earthworks rules?

No government body publishes a standard price for land filling. The bill depends on the volume of fill (the area multiplied by the height between existing ground and the platform level you need), the fill material and where it comes from, haulage, compaction testing and any treatment of soft ground. Get a topographic survey from a licensed land surveyor and a cut and fill calculation from your engineer before you agree a price for the land.

Earthworks need approval

Under section 70A of the Street, Drainage and Building Act 1974, nobody may start earthworks without first submitting plans and specifications to the local authority and getting its approval. "Earthworks" includes excavation, levelling, filling with any material, piling, building foundations and felling trees. The council can attach conditions, order the works stopped if it certifies that safety is at risk, and on conviction a person working without approval faces a fine up to RM50,000, jail up to five years, or both, plus up to RM500 a day for a continuing offence. Never let a seller "fill it for you" without approved plans: you inherit the problem.

How high must the platform be, and how do you check the flood level?

JPS's guideline on development involving rivers says buildings need an adequate platform level to reduce flood damage, that the minimum depends on the local area, and recommends designing against the 100-year flood for urban areas and the 50-year flood for agricultural areas near rivers. Ask the council and the district JPS office for the platform level they will require on your lot, then compare it with the existing ground and the road. For history, check river levels on Public Info Banjir and JPS Selangor's flood information portal, and ask neighbours how high water rose in past floods. The same JPS guideline asks developments of 10 hectares or more to provide retention ponds, sized at 3% to 5% of the development area, so a large site also loses land to drainage. A separate FactoryHub guide covers checking flood risk on an existing factory.

An excavator and a roller build a compacted earth platform on low land while a surveyor checks levels
IllustrationAn excavator and a roller build a compacted earth platform on low land while a surveyor checks levels

Can you build on sloping land or next to a river?

Yes, within limits. Both take usable land away from you and add reports, so measure the net buildable area before you compare prices.

Slopes

The PLANMalaysia guideline treats any slope of 15 degrees or more as hill slope and sorts land into four classes:

Class In-situ slope What it means for development
I Below 15 degrees All types can be considered on lowland, subject to the local plan
II 15 to 25 degrees, no signs of erosion or instability (also flatter land with such signs, ridges or flood-threat areas) Only the listed uses; extra engineering controls
III 25 to 35 degrees Only the listed uses; an EIA is required for every project
IV Above 35 degrees No development except infrastructure such as roads, bridges and power lines

The uses listed for Classes II and III are housing, shops, offices, hotels, training institutes and community facilities. Factories are not on the list, and other developments go to the State Authority with advice from the National Physical Planning Council. The guideline also requires an independent checker and slope inspections every five years. The KPKT guideline adds buffer zones: a structure near the toe of an unprotected cut or natural slope steeper than 70 degrees must stand at least twice the slope height away. For a factory, the practical answer is to buy land that is already Class I, or to price the cut and fill and retaining works into the deal.

Rivers and drains

JPS sets the minimum river reserve by the width of the waterway between its banks:

Waterway width between banks Minimum reserve width from the banks
More than 40 m 50 m
20 to 40 m 40 m
10 to 20 m 20 m
5 to 10 m 10 m
Less than 5 m 5 m

A lined channel needs at least 5 m on each side, and JPS asks for planning that faces the river across a 50 m corridor beyond the reserve. Permanent structures are discouraged inside the reserve. In Selangor, LUAS adds its own control: its conditions, as published in Majlis Perbandaran Hulu Selangor's 2022 planning guideline, bar diversion, filling or any development within the 50 m river reserve without the written permission of the LUAS Director, and require written permission under section 43(1) of the LUAS Enactment 1999 for works touching flood zones or river reserves. Ask the land office whether a reserve is already gazetted and whether any part of the lot sits inside it.

Can you get a bank loan to buy industrial land?

Yes. Banks do finance vacant industrial land, but on their own credit terms rather than a published cap. CIMB, for example, lists vacant land alongside industrial and commercial property for its SME property financing, with financing up to RM20 million, subject to its terms. The bank's valuer will look at the same things as this checklist, so access, conversion status and title conditions affect what the bank will lend. Ask each bank in writing for the margin, tenure and whether it will also finance construction in stages. Our guide on buying industrial land as an investment covers holding costs, idle-land conditions and the RPGT on resale.

This guide explains the rules and what to ask; it is not legal, tax or engineering advice. Confirm your own case with your lawyer, engineer and the authorities.

Costs, tax and financing: more questions

Can I get a bank loan to buy industrial land?

Yes, many banks finance vacant industrial land, on their own terms. The margin and tenure depend on the bank, your company's income and the land itself, including its access and conversion status. Ask several banks for written terms before you sign the sale and purchase agreement.

Site checks with local detail: buying industrial land in Klang to build by Ms Teh Seok Hoon, and land site checks in Rawang and Serendah by Jason Low.

Frequently Asked Questions

How do you check the soil conditions of industrial land in Malaysia?

Hire a geotechnical engineer to carry out a site investigation: boreholes drilled across your planned building footprint, with laboratory tests on the samples. The report shows the soil layers and how deep firm ground lies, the groundwater level, how much the ground will settle under fill and floor loads, and any old fill, peat, soft clay or dumped material. Get the seller's written permission to enter the land, ask for a quote based on your footprint, and do it before you commit.

What should I check before buying industrial land in Malaysia?

Check the title first: the owner, the category of land use, the express conditions and any caveat or charge. Then confirm the zoning with the council, legal road access, power, water and sewer capacity, any river or drainage reserve, the platform level you must build to, and the soil and slopes. Finally, get the bank's lending terms in writing.

Can I build a factory on land that is not converted to industrial?

No. Land in the agriculture or building category must first be converted to the industry category by the State Authority under section 124 of the National Land Code, and you still need planning permission and council approvals after that. The Code's implied conditions limit buildings on agricultural land to the purposes it lists (section 115) and bar industrial use of building land (section 116).

Is soil investigation required before buying land in Malaysia?

It is not required to buy, but it is required in practice to build. Hillside sites need geotechnical and slope stability reports with the planning and earthworks applications, and on any site the engineer needs ground data to design foundations. Doing it before you commit tells you whether piling and filling costs still make the price worthwhile.

How much does land filling cost in Malaysia?

There is no official rate. The cost depends on how many cubic metres of fill you need between the existing ground and the required platform level, the fill material, haulage, compaction and any soft ground treatment. Get a topographic survey and an engineer's cut and fill estimate, then quotes from contractors.

Can I build a factory next to a river?

You can build next to the river reserve, not in it. JPS sets reserves of 5 m to 50 m depending on the river's width, and in Selangor any development within the 50 m river reserve needs the LUAS Director's written permission. Deduct the reserve from the usable area before you compare prices.

Can I build a factory on a hill slope in Malaysia?

Slopes below 15 degrees can be considered for all types of development, subject to the local plan. On 15 to 35 degree slopes the guideline lists housing, commercial and institutional uses, not factories, and slopes above 35 degrees are closed to everything except infrastructure. Any factory proposal on sloping land needs geotechnical, geological and drainage reports.

What if the industrial land has no electricity or water?

You can still build, but you carry the time and cost of bringing utilities in. Above 350 kVA TNB requires a new substation on your land, and from 1,000 kVA an 11 kV supply typically takes 6 to 12 months. Ask Air Selangor and Indah Water in writing where the nearest main or sewer is and who pays to extend it.