Key Takeaways
- On 18 November 2026, Kapar MP Dr Halimah Ali asked in the Dewan Rakyat whether the government had carried out a cumulative impact assessment for the proposed 656.8 hectare (1,623 acre) industrial park in Bukit Kerayong, Kapar, citing flooding, water and electricity supply, roads and drainage.
- Deputy Digital Minister Datuk Wilson Ugak Kumbong replied that data centre applications are assessed for water and electricity supply, infrastructure capacity and energy efficiency before approval. The published report does not say whether a cumulative assessment has been done for Bukit Kerayong.
- On 20 November, Menteri Besar Dato' Seri Amirudin Shari said he had told local authorities to investigate and list every development project, and that projects failing retention pond requirements may face stop-work orders and revocation of planning permission.
- Selangor Irrigation and Drainage Department (JPS) figures show flood hotspots and flood-risk locations in Klang district fell from 88 in 2022 to 48 in 2025, level with Petaling for the highest count among the districts named.
- For anyone buying, renting or building around Kapar, Meru and Bukit Raja, flood records, drainage approvals and confirmed power and water supply deserve a check before price.
What Was Asked in Parliament
The question came during a Dewan Rakyat session on data centre investment on Wednesday, 18 November 2026. According to The Star, Dr Halimah Ali (PN-Kapar) asked in a supplementary question whether the government had carried out a cumulative impact assessment on the proposed 656.8 hectare (1,623 acre) industrial park in Bukit Kerayong, which she said is expected to host a data centre campus. She raised flooding, pressure on water and electricity supply, and strain on roads and drainage, and asked whether residents would bear the social and environmental costs while investors take the economic benefits. The New Straits Times also reported her concerns.
Deputy Digital Minister Datuk Wilson Ugak Kumbong replied that data centre applications are assessed for water and electricity supply, infrastructure capacity and energy efficiency before approval, and that operators are encouraged to use renewable energy and more efficient technology. The Star's report does not say whether a cumulative assessment has been made for Bukit Kerayong, so that part of the question appears to remain open.
In the same session, Wilson said the Data Centre Task Force, jointly chaired by the Digital Ministry and the Ministry of Investment, Trade and Industry, had approved 27 projects worth an estimated RM225.97 billion up to the previous month.
What Is Planned at Bukit Kerayong
The park was announced on 29 October 2026. SD Guthrie said it had formed a joint venture with Bumi Assets Sdn Bhd and YTL Power International Bhd to develop about 1,623 acres of freehold land in Bukit Kerayong into an integrated industrial development, described as a light to medium industrial park with commercial components and supporting infrastructure. The vehicle is Bukit Kerayong Industrial Developments Sdn Bhd, in which SD Guthrie holds 30% and YTL Power and Bumi Assets hold 35% each. SD Guthrie is selling the oil palm land to the venture for about RM933.57 million, with completion expected by the first quarter of 2027. The details are in our report on the Bukit Kerayong industrial park.
The partners have not announced a data centre at the site. On 2 November, The Star reported that a research house saw data centre facilities as something that "should not be ruled out", with details pending the finalisation and approval of the master concept plan. The same report placed the land about 6km north of Kapar town, where the Kapar Energy Ventures power plant is located.
Flooding next to new projects in this part of Kapar is not a new complaint. In September, Media Selangor reported that the developer of shop-house lots at the Kapar Industrial Park would be fined after its project flooded dozens of homes in Taman Seri Kerayong twice, and state executive councillor Dato' Izham Hashim said there had to be an immediate and long-term solution. That is a separate, smaller project, but it shows how quickly drainage problems surface when land in this low-lying area is cleared.
Selangor Orders Retention Pond Checks on All Projects
Two days after the parliamentary question, the state moved on drainage across Selangor. Winding up the debate on the Supply Enactment 2026 Bill on 20 November, Amirudin said, as reported by Media Selangor:
"My latest directive to local authorities is to investigate and compile an inventory of all development projects, whether road projects, new housing developments, schools, or public facilities, even if they benefit residents."
He warned that ponds can fill with silt if retention pond requirements are not met and maintenance is not carried out regularly, said work could be stopped and planning permission revoked, and added: "We do not want this to affect development." The directive follows his earlier order to halt all development work in Puncak Alam pending a review of the flood mitigation plan and Environmental Impact Assessment.
In the same speech he presented JPS figures, reported the next day. JPS treats an area as a flood hotspot if it floods at least three times within three years, and as a flood-risk area if it has flooded within the past three years. Amirudin said Selangor once had more than 200 flood hotspots and now has 56. Recorded flood incidents fell from 487 in 2023 and 433 in 2024 to 322 in 2025. By district, combined hotspots and flood-risk locations moved as follows:
| District | 2022 | 2025 |
|---|---|---|
| Klang | 88 | 48 |
| Petaling | 55 | 48 |
| Hulu Langat | 97 | 46 |
| Sepang | 73 | 35 |
| Kuala Selangor | 55 | 35 |
Amirudin said quick, small-scale works had cut flood impact by up to 60 per cent in Padang Jawa, Taman Melawis and Jalan Paip in Klang and in Taman Sri Muda in Shah Alam, all badly hit in December 2021.
The Data Centre Question at State Level
Water and power have also come up in the State Assembly. On 17 November, investment, trade and mobility executive councillor Ng Sze Han told the assembly that the federal Data Centre Task Force acts as a gatekeeper on adequate water and electricity supply, and that the state is preparing for higher demand with the Energy Commission and Air Selangor. He said the relevant departments could require Environmental and Social Impact Assessments, and that PLANMalaysia@Selangor's Data Centre Planning Guidelines will be reviewed to align with federal guidelines.
Why It Matters for Factory Owners, Tenants and Buyers
Kapar is one of the busiest industrial markets north of Port Klang. JPPH-registered transactions recorded 126 industrial deals worth RM969.16 million in Kapar in the 12 months to August 2026. Over 24 months, registered industrial land had a median of RM100 psf of land, detached factories a median of RM14.9 million (RM306 psf of land), and 292 registered factory tenancies a median rent of RM1.40 psf a month. The full breakdown is on our Kapar transaction prices and rents page.
Three points follow from this week's news:
- Flood checks are getting stricter. Projects that skipped or neglected retention ponds risk stop-work orders. If you are buying a factory still under construction, or land that still needs planning permission, that can mean delay.
- Utilities are part of the debate. A park of this size, possibly with data centre use, will draw on the same water and grid as the factories around it. Nothing published says supply to existing factories will be cut, but supply confirmed in writing matters more when demand is rising.
- Scrutiny, not a stop. No order has halted Bukit Kerayong. The land sale is not due to complete until the first quarter of 2027, so it does not change what you can rent or buy in Kapar today.
What to Do Now
- Before you buy or rent in Kapar, Meru or Bukit Raja: ask whether the street or estate has flooded in the last three years, look at the JPS flood records and compare the floor level with the road. Our guide on how to check flood risk before renting or buying a factory sets out the steps.
- If you are buying a unit under construction: ask the developer for the approved drainage and retention pond plan and who maintains it, and read the late delivery clause in the sale and purchase agreement.
- If you need high power or heavy water use: have the landlord or developer confirm the TNB supply in amps and the water connection in writing before you sign.
- Owners in low-lying parts of Klang: keep the drains around your lot clear and check that your insurance covers flood, because buyers and tenants are asking more questions.
- Tenants whose lease ends within two years: plan with the stock already standing in Kapar and Sungai Kapar Indah rather than waiting for Bukit Kerayong.
Frequently Asked Questions
Where is the Bukit Kerayong industrial park?
It covers about 1,623 acres of freehold former oil palm land in Bukit Kerayong, Kapar, in Klang district, Selangor. The Star placed it about 6km north of Kapar town, near the Kapar Energy Ventures power plant. It is being developed by Bukit Kerayong Industrial Developments Sdn Bhd, owned by SD Guthrie (30%), YTL Power (35%) and Bumi Assets (35%).
Will the Bukit Kerayong park have a data centre?
The partners have not announced one. The Kapar MP described the park as expected to host a data centre campus, and a research house quoted by The Star said data centre facilities should not be ruled out while the master concept plan is still to be finalised and approved. Treat it as possible but unconfirmed.
What did Selangor order on retention ponds?
On 20 November 2026, Menteri Besar Amirudin Shari said he had told local authorities to investigate and compile an inventory of all development projects for compliance with flood mitigation requirements. Projects that fail retention pond requirements may face stop-work orders and revocation of planning permission. He said the aim is not to stop development.
Is Klang still a flood-prone district?
JPS figures show combined flood hotspots and flood-risk locations in Klang district fell from 88 in 2022 to 48 in 2025. That is a clear improvement, but 48 is level with Petaling for the highest count among the districts named, so a flood check on any Klang or Kapar factory is still worth doing.
Does this change factory prices or rents in Kapar now?
No published figure shows a change yet. JPPH-registered data to August 2026 show a median industrial land price of RM100 psf of land and a median factory rent of RM1.40 psf a month in Kapar. The Bukit Kerayong land sale is due to complete in the first quarter of 2027, so any effect on supply is years away.