Key Takeaways

  • On 25 November 2026, Deputy Energy Transition and Water Transformation Minister Datuk Seri Abdul Rahman Mohamad told the Dewan Rakyat that the Selangor Irrigation and Drainage Department (JPS) is carrying out three immediate flood works in the Sungai Rasah basin, due between February and March 2027.
  • One of them sits near the Bukit Raja junction: an outlet structure, a flap gate and a flood wall costing RM199,000, scheduled for completion on 17 February 2027. A flood wall at Taman Intan (RM200,000) is due the same day, and a flood wall with a flap gate at Taman Rashna (RM350,000) on 17 March 2027.
  • The permanent fix, an RM40 million scheme with a water control gate at the mouth of Sungai Rasah, a pump house, a flood retention basin and riverbank retaining walls, is still at preliminary design. Physical work is targeted to start in the second quarter of 2028 and finish by 2031, or possibly by 2029 if the job is split into two tenders.
  • Until then, six mobile pump units are deployed at four high-risk spots: Taman Rashna, Taman Intan, the area near the Bukit Raja junction and the AEON supermarket area.
  • For anyone running, renting or buying a factory around Bukit Raja and the Federal Highway side of Shah Alam, flash floods on these routes will be handled by walls and pumps for several more rainy seasons, so site checks, insurance and delivery plans should allow for it.

What Was Announced in Parliament

The answer came during a Special Chamber session in the Dewan Rakyat on Wednesday, 25 November 2026. Azli Yusof (PH-Shah Alam) asked about the status of flood control plans for the Sungai Rasah basin after the recent flash floods in Shah Alam and Klang. According to the Bernama report carried by The Star and Free Malaysia Today, the deputy minister listed three immediate projects that JPS Selangor is building now:

Location Works Cost Scheduled completion
Near the Bukit Raja junction Outlet structure, flap gate and flood wall RM199,000 17 February 2027
Taman Intan Flood wall RM200,000 17 February 2027
Taman Rashna Flood wall and flap gate RM350,000 17 March 2027

JPS has also placed six mobile pump units across four high-risk locations, namely Taman Rashna, Taman Intan, the area near the Bukit Raja junction and the AEON supermarket area, to drain floodwater faster and shorten the time water stands on the roads.

The RM40 million long-term scheme

For the long term, the government has approved RM40 million under the First Rolling Plan of the 13th Malaysia Plan (13MP). The money covers a water control gate at the estuary of Sungai Rasah, a pump house, a flood retention basin and riverbank retaining walls.

The deputy minister said the project is in the preliminary design stage. Physical work is targeted to begin in the second quarter of 2028 and to be completed by 2031. His ministry has proposed splitting the RM40 million into two separate tenders, which could bring completion forward to 2029. A key focus is stopping water from Sungai Klang overflowing into high-risk areas in Shah Alam; that component alone is estimated at between RM15 million and RM20 million, depending on the final scope and technical studies. He added that the final scope still depends on the studies and detailed designs prepared by the consultants.

Why This Corner Keeps Flooding

Earlier this month, The Star reported that Selangor had approved RM800,000 for immediate works, including pumps, around the i-City junction in Shah Alam and Taman Rashna in Klang, which Menteri Besar Datuk Seri Amirudin Shari said could be completed as early as December. That approval followed repeated flash floods around i-City, Section 7 and Taman Rashna in October. On 28 October, Jalan Keluli 1C near i-City flooded for the second day running, and a day earlier flooding along the Federal Highway near i-City caused severe traffic congestion.

The same report explains the cause in plain terms. Shah Alam mayor Datuk Zabidah Safar said the flooding was mainly caused by Sungai Rasah overflowing into a JPS drain that runs alongside the Federal Highway before discharging into Sungai Klang. When high tides raise Sungai Klang, the main drain can be overwhelmed and water flows back into low-lying areas. State infrastructure committee chairman Datuk Izham Hashim linked the problem to the absence of a water gate on the way into Sungai Rasah, and named Taman Rashna, i-City, Section 7 Shah Alam and Bandar Bukit Raja in Klang for mitigation works.

That is why the long-term scheme puts a control gate and a pump house at the river mouth. Until that gate exists, a heavy downpour that coincides with a high tide can still back water up into the low spots, and the walls and pumps being built now are meant to keep that water off the roads and out of homes and premises for shorter periods.

River water backing up a roadside drain floods a low junction while a raised factory platform stays dry
IllustrationRiver water backing up a roadside drain floods a low junction while a raised factory platform stays dry

What It Means for Factory Owners, Tenants and Buyers

Bukit Raja is one of Klang's main industrial areas, and many factories and warehouses around it move goods through the Federal Highway and NKVE connections. When the junction area floods, lorries queue or divert, deliveries slip and staff arrive late. FMT noted that flooding in early November caused congestion on the route from the Bukit Jelutong toll plaza to the NKVE.

Three points stand out:

  • The near-term works are small and local. Together the three projects cost RM749,000. They should help the specific spots named, but they do not change how Sungai Klang behaves at high tide.
  • The structural fix is years away. Even on the faster two-tender path, the river mouth gate is not due before 2029, and the official target is 2031.
  • Flood risk is site by site. A factory on a raised platform a few hundred metres from a low junction may never take water, while an older unit at road level beside a monsoon drain can. Asking prices rarely show this, which is why registered deals and site history matter more than a listing.

To see what factories and land in the area have actually sold and rented for, use the registered Bukit Raja industrial transactions, which come from JPPH records rather than asking prices.

Practical Steps

If you already rent or own a factory near the Sungai Rasah basin

  1. Know your levels. Compare your floor and loading bay level with the road outside and the nearest drain. Ask the landlord or neighbours for the dates and depth of past floods, and look for old watermarks on walls and roller shutters.
  2. Lift what matters. Keep stock on racks or pallets, and make sure the main switchboard, compressors and machine control panels sit above the highest past water line.
  3. Check your insurance wording. A standard fire policy does not cover flood unless flood is added as an extension. Read the policy, and see this guide to fire insurance for shops and factories on what the add-ons cover.
  4. Plan deliveries around warnings. Watch MetMalaysia heavy rain warnings and the high tide period, keep an alternative route that avoids the low junction, and agree with key customers what happens when a delivery slot is missed.
  5. Read your lease. Find out who pays for flood damage to the building, and whether rent pauses if the premises cannot be used.

If you are about to buy or sign a lease

  • Visit after a heavy downpour, not only on a dry morning.
  • Ask the owner directly whether the unit or the access road flooded in 2021, in October 2026 or in November 2026, and get the answer in writing.
  • Look at where the site's drain discharges and whether there is a flap gate or a raised outlet.
  • For land or new projects, check the retention pond and drainage approvals. Selangor has already warned developers that weak retention ponds can lead to stop-work orders, as covered in our report on Bukit Kerayong and the state's retention pond checks.

Dates to watch

  • 17 February 2027: flood wall and outlet near the Bukit Raja junction, and the Taman Intan flood wall.
  • 17 March 2027: Taman Rashna flood wall and flap gate.
  • Second quarter of 2028: target start of physical work on the RM40 million Sungai Rasah scheme.
  • 2029 or 2031: completion, depending on whether the two-tender plan is adopted.

Frequently Asked Questions

When will the flood wall near the Bukit Raja junction be finished?

The outlet structure, flap gate and flood wall near the Bukit Raja junction cost RM199,000 and are scheduled for completion on 17 February 2027. The deputy minister gave the date in the Dewan Rakyat on 25 November 2026. Six mobile pumps, including one location near the junction, cover the area in the meantime.

What is the RM40 million Sungai Rasah flood scheme?

It is a long-term project approved under the First Rolling Plan of the 13th Malaysia Plan. It includes a water control gate at the mouth of Sungai Rasah, a pump house, a flood retention basin and riverbank retaining walls. It is at preliminary design, with physical work targeted to start in the second quarter of 2028 and finish by 2031, or possibly by 2029 if it is split into two tenders.

Why do the Federal Highway and i-City areas flood after heavy rain?

According to the Shah Alam mayor, Sungai Rasah overflows into a drain beside the Federal Highway that empties into Sungai Klang. When high tides raise Sungai Klang, that drain can be overwhelmed and water flows back into low-lying areas. The planned gate at the river mouth is meant to stop this backflow.

Should I avoid buying a factory in Bukit Raja because of floods?

Not as a rule, because flood risk depends on the exact lot, its platform level and its drainage, not on the area name. Check the unit's flood history, visit after heavy rain and confirm the insurance terms before you commit. Registered transaction prices for Bukit Raja give a better picture of value than asking prices.