Key Takeaways
- A factory relocation in Malaysia runs on several official clocks at the same time, and the slowest one sets your move-in date. For most moves that is power: TNB's own Electricity Supply Application Handbook gives a typical lead time of less than 3 months for a 400 V supply without a substation, 3 to 12 months with a substation, and 6 to 12 months at 11 kV.
- If the new factory already has the power you need, there is no supply project to wait for, so the critical path becomes fit-out plus the council licence. MBDK in Klang lists 14 days for a temporary industrial licence and 30 days for a full risk-category industrial licence.
- Steam boilers, pressure vessels such as air receivers, and lifting machinery such as overhead cranes that carry a DOSH certificate of fitness need fresh written approval for installation at the new address. New emission sources such as boilers, generators and dust collectors need written notice to DOE at least 30 days before the installation work starts.
- After the move, tell SSM about the new business address within 14 days and LHDN within three months, stamp the new tenancy within 30 days of signing, and get a JTKSM accommodation certificate for any worker hostel you provide.
- Overlap rent is the price of the critical path. Map the approvals first, then negotiate a rent-free fit-out period on the new lease and a flexible exit on the old one instead of paying two full rents for months.
This guide is general information, not legal or tax advice. Every timeline below comes from the agency that sets it; where no agency publishes a clock, we say so instead of guessing.
How long does a factory relocation take in Malaysia?
There is no single official number, because a move is a chain of separate approvals that each have their own clock. What you can do is find the longest chain for your factory and plan around it. The table below lists the stages in order, the published time limit where one exists, and what usually stretches it.
| Stage | What happens | Published clock | What stretches it |
|---|---|---|---|
| 1. Brief and search | Write down amps, floor loading, container access, crane height and the activity you will license; shortlist units | None | A brief that ignores power or zoning |
| 2. Checks and signing | CCC or CF, approved plans, Bomba fire certificate, the incoming TNB supply; sign the tenancy or SPA | Tenancy stamped within 30 days of signing (LHDN) | Unapproved extensions, missing plans |
| 3. Power | Change of tenancy, load upgrade or new substation | Less than 3 months up to 12 months for 400 V and 11 kV (TNB ESAH) | Substation land, council approval of plans |
| 4. Environmental notices | Written notice for emission and effluent sources | At least 30 days before work (Clean Air Regulations 2014) | New boilers, scrubbers, effluent plant |
| 5. Fit-out | Council permit, then the works | Permit needed before work starts | Partitions, ramps and structural works need plans |
| 6. Machine moving | Rigging, transport, re-levelling, DOSH approval and inspection of certified plant | No published clock | Festive road bans, inspection dates |
| 7. Licences and records | Council licence, MIDA, SSM, LHDN, JTKSM | 14 days to 3 months depending on the record | Incomplete files restart the clock |
Step 1: What should you check before you sign a new factory?
Most delays in a relocation are decided before the tenancy or SPA is signed. A factory that looks right on a viewing can still add months if its power, approvals or permitted use do not fit what you run.
The brief that saves months
- Power. Work out the amps your machines need with the factory power calculator, then ask for the latest TNB bill and the rating of the incoming supply. If you need more than the building has, the TNB track below starts at once and becomes your critical path.
- Certified plant. List every steam boiler, air receiver or other pressure vessel and every overhead crane or hoist, because each one triggers a DOSH approval at the new address.
- Emissions and effluent. Note anything that burns fuel, vents dust or fumes, or discharges process water. Each new source needs a DOE notice before installation.
- Workers. Count the workers you house. A new hostel needs its own JTKSM accommodation certificate.
Documents to ask the landlord or seller for
- The CCC or CF and the approved building plans, so you know the extensions are legal.
- The current Bomba fire certificate if the building is a designated premises. Under the Fire Services Act 1988, a fire certificate is renewable every year, and Bomba issues one only after an inspection of the premises.
- The TNB bill and supply details, and whether a substation already serves the lot. Our guide to TNB substations for factories explains what a substation means for land, cost and timing.
For the money side of the same decision, from deposits to fit-out and running costs, see our factory setup cost guide.
Step 2: Which approvals can run at the same time?
Once the new premises are secured, start every track together. Running them one after another is the most common reason a move overruns.
TNB: same load, upgrade or new substation
TNB's handbook separates applications by load and supply voltage.
| Your situation | What TNB needs | Typical lead time in the handbook |
|---|---|---|
| Up to 100 A, moving in with no change in load, or change of tenancy | Application and payment; the step of appointing an electrical contractor is skipped | Set by TNB's customer charter |
| Up to 100 A, new or higher load | Application through a contractor registered with the Energy Commission | Set by TNB's customer charter |
| 400 V and below, no new substation | Above 100 A, an electrical consultant engineer applies | Less than 3 months |
| 400 V and below, with a substation | Substation site, building and cable route | 3 to 12 months |
| 11 kV | Consultant, substation and switchroom | 6 to 12 months |
| 33 kV | Larger supply project | 18 months to 2 years |
The handbook adds that these times assume no delay in local authority approval, and that applicants above 100 A should expect a deposit equal to two months of bills, with a bank guarantee encouraged for deposits above RM2,000.
DOE: 30 days' notice before emission and effluent sources
The Environmental Quality (Clean Air) Regulations 2014 apply to any premises used for industrial or trade purposes. Regulation 5 requires written notification to the Director General not less than thirty days before work that may create a source of emission, or before changes to plant or an air pollution control system. The Industrial Effluent Regulations 2009 set the same thirty-day notice for work that creates a new source of industrial effluent. Build these 30 days into the plan, because the boiler or scrubber cannot go in before them.
DOSH: certified plant needs approval at the new address
The Occupational Safety and Health (Plant Requiring Certificate of Fitness) Regulations 2024, in force since 1 June 2024, cover three kinds of plant: steam boilers, pressure vessels and lifting machinery. Regulation 4(3) says that when plant certified for one location is relocated, the person installing it at the new location must apply for written approval for the installation. A fresh design verification is not needed, but the installation requirements are. A certificate of fitness is valid for 15 months from inspection, and plant that works in portable form without being dismantled keeps its certificate when it moves. Our guide to the Factories and Machinery Act repeal explains how the old rules changed.
Bomba: tell them before a material change
If the new factory already holds a fire certificate, section 32(2) of the Fire Services Act 1988 requires the occupier to give Bomba notice of a material change to the premises before the work begins. New racking, partitions or a change of use can count, so raise them with your fire consultant during the design, not after.
Step 3: How long does the fit-out take, and what needs a permit?
The works themselves depend on your contractor, but the permit comes first. As one example, MBSJ's minor works permit form, issued under by-law 18 of the Uniform Building By-Laws 1984, covers items such as floor and wall finishes, plaster ceilings and painting the outside of a terrace factory with a skylift or scaffolding. It charges a RM100 processing fee, requires approval before any work starts, stays valid for one year, and allows work only from Monday to Saturday, 8.00 am to 6.00 pm, with no work on Sundays or public holidays.
Larger alterations go through separate approvals. MBSJ's factory licence guideline lists renovation, ramp and partition permits as technical approvals the licence waits for. A sensible order is: permits, then floor and electrical works, then compressed air and process piping, then machines. Machines that arrive before the floor and power are ready usually sit idle while the rent runs.
Step 4: How do you plan the machine move?
No agency publishes a time limit for moving machines, so the plan rests on your own production schedule and three outside dates.
- Road bans. JPJ announces bans on goods vehicles for festive seasons. For Chinese New Year 2026, the ban ran on 14 to 15 February and 21 to 22 February 2026. Check JPJ's notices before you book trailers.
- DOSH approval and inspection. Certified boilers, receivers and cranes cannot run at the new address until the installation approval and the inspection for a certificate of fitness are done, so book them early.
- Lifting equipment. Mobile cranes used for the move are lifting machinery too. Ask the rigging contractor for each crane's current certificate of fitness.
Move in phases where you can: stock and non-critical lines first, then the bottleneck machines, so that one line keeps running at the old site while the new one is commissioned.
Step 5: Which licences and records change after the move?
- Council licence. A council premises licence is issued for the premises, so the new factory needs its own application. MBDK lists 14 days for a temporary industrial licence and 30 days for a risk-category industrial licence. MBSJ tables factory applications at its licensing technical meeting within 14 working days and can grant a six-month temporary licence while renovation, ramp or partition permits are pending. Our business premise licence guide covers documents and rejections.
- MIDA. If you hold a manufacturing licence, a change of factory location is a post-licensing application, with an evaluation fee of RM750 in MIDA's list of charging fees.
- SSM. Under Practice Directive 2/2017 (revised 5 August 2026), a company must notify SSM of a new business address within 14 days through the Corporate Registry System. If the registered office moves too, section 46(3) of the Companies Act 2016 also gives 14 days.
- LHDN. Section 89 of the Income Tax Act 1967 requires notice of a change of address within three months.
- Worker housing. JTKSM requires an accommodation certificate for all accommodation provided to workers, applied for online, and the employer must report where workers are placed within 30 days. Failing to report can bring a fine of up to RM10,000 for each offence.
How do you keep overlap rent under control?
Overlap rent is the period when you pay for both factories. Its length is roughly your critical path (approvals, fit-out and the machine move) plus the time to hand back the old premises, minus any rent-free period you win on the new lease. Four ways to shorten it:
- Map the critical path before you agree a rent start date. If the new unit needs a substation, the handbook's 3 to 12 months means a rent start a month after signing pays for an empty building.
- Negotiate fit-out time. A rent-free or reduced-rent fit-out period and early access for contractors are commercial terms, so ask before you sign, not after.
- Read the old tenancy now. Check the notice period, any option to renew, what happens if you hold over, and the reinstatement clause, then ask the landlord early for a short extension if your critical path is long.
- Budget the paperwork. Since 1 January 2026, tenancy agreements are stamped under LHDN's self-assessment system, within 30 days of signing.
How is moving a factory different from moving an office or a house?
An office or house move is mostly a logistics job. A factory move also changes regulated things: the power supply rating, certified plant under DOSH, emission and effluent sources under DOE, the Bomba fire certificate, the council industrial licence and, for many manufacturers, a MIDA licence and worker housing. A warehouse sits in between: fewer process approvals, but racking, sprinklers and container access still decide whether the building works for you.
Common mistakes that delay a factory relocation
- Signing before checking the incoming TNB supply against the amps you need.
- Running a relocated boiler, receiver or crane before DOSH approval and inspection.
- Installing a boiler, generator or scrubber without the 30-day DOE notice.
- Starting works before the council permit is issued.
- Booking heavy transport on festive road ban days.
- Forgetting the SSM and LHDN address updates, or moving workers into a hostel without a JTKSM certificate.
Costs, tax and financing: more questions
How can I reduce double rent when relocating a factory?
Work out your critical path first, then negotiate a rent-free fit-out period and early access on the new lease, and a short extension on the old one if needed. Move in phases so one line keeps earning while the other is commissioned, and avoid a rent start date that falls before the power and permits are ready.
Practical steps: more questions
Do I need to update SSM and LHDN after moving my factory?
Yes. SSM must be told of a new business address within 14 days, and of a new registered office address within 14 days as well. LHDN must be told of a change of address within three months under section 89 of the Income Tax Act 1967.
What should a factory relocation checklist include?
At minimum: the power you need against the incoming supply, the CCC or CF and approved plans, the Bomba fire certificate, DOE notices for emission and effluent sources, DOSH approval for certified plant, the council renovation permit and licence, festive road ban dates, and the SSM, LHDN, MIDA and JTKSM updates after the move.
Local timings: how long a factory move in Klang takes from Ms Teh Seok Hoon, and the relocation timeline for Rawang, Serendah and Shah Alam from Jason Low.
Frequently Asked Questions
How do you calculate the cost of relocating a factory?
Add up five groups, using quotes, because there is no standard figure. First, overlap rent: the months you pay for both factories, roughly your approvals, fit-out and machine move plus handing back the old unit, minus any rent-free period. Second, entry costs at the new unit: deposits (commonly four months' rent), stamp duty and legal fees. Third, fit-out and any TNB upgrade. Fourth, machine moving: rigging, transport, re-levelling and DOSH approval for certified plant. Fifth, reinstating the old unit and the production days you lose.
How can I find a suitable factory in a short time?
Write a full brief first and view only units that already meet it: the amps your machines need, floor loading, container access, crane height and the activity you will license. Power matters most, because TNB gives under 3 months up to 12 months for supply work. If the unit already has your power, the timeline becomes fit-out plus the council licence; MBDK in Klang lists 14 days for a temporary industrial licence. Check the CCC or CF, approved plans and fire certificate before signing. Peter Tan or Jason Low can shortlist matching units.
What is the impact of relocating a factory to a different state in Malaysia?
Mostly approvals that start again with new authorities. A council licence is issued for an address, so you apply to the council in the new state, give DOE 30 days' written notice before installing boilers or other emission sources, and get DOSH approval before certified boilers, receivers and cranes run at the new site. A MIDA manufacturing licence needs a change of location application. If you buy, land rules such as state consent and foreign buyer minimum prices differ by state. Update SSM within 14 days and LHDN within three months.
How long does it take to relocate a factory in Malaysia?
It depends on the slowest approval for your factory. If the new building already has enough power, the critical path is usually the fit-out and the council licence, which MBDK lists at 14 days for a temporary industrial licence and 30 days for the full one. If TNB must build a substation, its handbook gives 3 to 12 months at 400 V and 6 to 12 months at 11 kV.
How long does TNB take to upgrade power for a factory?
TNB's Electricity Supply Application Handbook gives typical lead times of less than 3 months for a 400 V supply without a substation, 3 to 12 months with a substation, 6 to 12 months at 11 kV and 18 months to 2 years at 33 kV. These assume no delay in local authority approval. Loads above 100 A are applied for through an electrical consultant engineer.
Do I need a new business licence when my factory moves?
Yes. A council premises licence is issued for a specific address, so you apply again to the council of the new location. MBDK lists 14 days for a temporary industrial licence and 30 days for a risk-category industrial licence, and MBSJ can issue a six-month temporary licence while renovation or partition permits are pending.
Do I need DOSH approval to move a boiler, air receiver or overhead crane?
Yes, if it holds a certificate of fitness. Under the 2024 regulations, plant certified for one location that is relocated needs written approval for installation at the new location before it runs. Plant that works in portable form without being dismantled keeps its certificate when it moves.
Do I have to inform DOE before moving my factory?
If you will install anything that creates a source of emission, such as a boiler, generator, scrubber or dust collector, the Clean Air Regulations 2014 require written notice to DOE at least 30 days before the work starts. A new source of industrial effluent has the same 30-day notice under the Industrial Effluent Regulations 2009.