Key Takeaways
- Add up the nameplate kW of every machine and building load, take the share that runs at the same time, divide by the power factor (TNB requires at least 0.85) to get kVA, then work out amps as kVA x 1,000 / (1.732 x 400). At 0.85, every kW of running load needs about 1.7A at 400V.
- TNB's supply bands decide what you are really asking for: a three phase whole current supply goes up to 72 kVA (100A), a CT metered 400V supply goes up to 1,000 kVA, a load above 350 kVA (about 505A) needs a new substation, and from 1,000 kVA the supply moves to 11kV.
- Check a factory from TNB's own records, not the advert: the supply contract (declared maximum demand and CT size), the meter (whole current or CT, and the CT ratio), the tariff on the bill, and only then the main incoming breaker.
- Up to 100A, an electrical contractor registered with the Energy Commission applies on myTNB. Above 100A, an Electrical Consultant Engineer registered with the Board of Engineers Malaysia applies, with a load list that includes every motor and its starter.
- TNB's typical lead time is under 3 months at 400V without a new substation, 3 to 12 months with one, and 6 to 12 months at 11kV. On an upgrade you pay the difference in TNB's load charge plus a deposit of about two months' bill.
How much kVA do I need for my factory? Work it out from your machine list, not from the size of the building. For example, 104 kW of machines running together at a power factor of 0.85 is about 122 kVA, or about 177A on TNB's 400V three phase supply, and about 221A once you leave 25% room to grow. This guide shows how to do that sum, how to check what a factory already has before you rent or buy it, and what TNB asks for, charges and takes to give you more. It is general information, not electrical engineering advice: the final figure is signed off by a registered electrical engineer and approved by TNB.
How do I work out the kVA and amps my factory needs?
TNB plans every supply around maximum demand (MD), the highest load a factory draws. Its application for electricity supply asks for two figures in kW, the total connected load and the maximum demand, and lists welding set load on its own line. So the sum runs in four steps.
Step 1: List every load and its nameplate rating
Write down every machine with the kW on its nameplate and the number of units. If a plate shows horsepower, 1 hp is 0.746 kW. Then add the building itself: air compressors, chillers and cooling towers, cold rooms, air conditioning, lighting, the office, pumps and any welding sets. The total is your connected load.
Step 2: Decide how much runs at the same time
Machines rarely all run at full load together. The share that does is a judgment about your process: a line that runs every machine at once is close to 100%, a job shop where machines take turns is lower. TNB's Electricity Supply Application Handbook (ESAH 3.1) says a maximum demand declared by a consultant must come with the connected load and the design calculations, so note why you chose the figure. The FactoryHub factory power calculator starts at 80% running together and lets you change it.
Step 3: Convert kW to kVA and amps
TNB defines power factor as kW divided by kVA (myTNB FAQ) and requires consumers below 132kV to keep it at 0.85 or higher (ESAH 1.1.4.3). So:
- kVA = running kW / power factor
- Amps at 400V three phase = kVA x 1,000 / (1.732 x 400)
- kW = kVA x power factor
Step 4: Leave room to grow
Add spare capacity for the machines you expect to add during the lease or ownership. The calculator starts at 25%. Do not overdo it on a medium voltage supply: TNB charges a Connected Load Charge there when your recorded demand falls short of what you declared, as our TNB substation guide explains.
Example: a machine list worked through
These figures are an example of the method only. Use the nameplates of your own machines.
| Load | Units | kW each | Total kW |
|---|---|---|---|
| Production machines | 4 | 15 | 60 |
| Chiller | 1 | 30 | 30 |
| Air compressor | 1 | 22 | 22 |
| Lighting, office and air conditioning | 18 | ||
| Connected load | 130 |
- Running together at 80%: 130 x 0.8 = 104 kW.
- kVA at a power factor of 0.85: 104 / 0.85 = about 122 kVA.
- Amps at 400V: 122.4 x 1,000 / (1.732 x 400) = about 177A.
- With 25% room to grow: about 221A, or about 153 kVA (130 kW).
This factory is past the 100A limit of a whole current supply, so it needs a CT metered supply, and the application must go through a consultant engineer. At 130 kW it falls in the 121 to 180 kW band of TNB's connection charge table, which uses a 300/5 CT.
What the sum leaves out
- Motor starting. TNB's load summary asks for each motor's size, type of starter, starting current and starts per hour (ESAH Appendix 6). ESAH Table 1-4 also limits the voltage step a load may cause when it switches: 1% for frequent starting, 3% for infrequent starting once in two hours or more, and 6% for starting once or twice a year. A large motor started direct on line can need a soft starter or a bigger supply even when the running load fits.
- Single phase. TNB gives single phase 230V only up to 12 kVA of maximum demand (myTNB). Any factory with real machinery needs three phase.
- Standby generators. The same load list sizes a generator. ESAH 1.1.5.2 allows standby generators, but they must stay separate from TNB's network and you must declare their safe installation to TNB.
Which TNB supply band does my number fall into?
The bands come from myTNB's business supply table and ESAH Table 3-1. Amps are at 400V three phase.
| Maximum demand | About amps | What TNB gives |
|---|---|---|
| Up to 12 kVA | Single phase 230V | Single phase service from the existing low voltage network |
| Up to 72 kVA | Up to 100A | Three phase whole current meter, from the existing low voltage network |
| Above 100A up to 100 kVA | About 100A to 145A | CT metered, from the existing low voltage network subject to TNB's study |
| Above 100 kVA to 350 kVA | About 145A to 505A | CT metered, cable from a feeder pillar or a new or existing substation, subject to TNB's study |
| Above 350 kVA to 1,000 kVA | About 505A to 1,443A | CT metered, direct cable from a new substation |
| 1,000 kVA to under 5,000 kVA | Above about 1,443A | 11kV through a TNB switching station, with your own transformers |
The line that changes a project is about 505A. Above it, TNB needs a new substation, and ESAH 1.3.4 requires its land to be transferred or leased to TNB for a nominal RM10. Land sizes and substation types are in our TNB substation guide.
How do I check how much power a factory really has?
An advert that says "300A" may mean the main breaker, the TNB approval or a guess. Check in this order.
1. The TNB supply contract
The application form signed with TNB records the supply type, including "3 Phase with CT (CT Size) Amps", the voltage level (230V, 400V, 11kV or 33kV), the total connected load in kW and the maximum demand in kW. TNB defines declared maximum demand as the consumer's power requirement in kW or MW "as contracted with TNB". Ask the owner for a copy, or for the latest upgrade application.
2. The meter
ESAH 3.3.1 rates three phase whole current meters at 10A to 100A, and ESAH 3.5.0 says low voltage consumers taking more than 100A per phase need current transformers (CTs) for metering. So a meter with the supply cables running straight through it means 100A or less, and a separate meter panel wired to CTs means more. The CT ratio, such as 400/5, is set by TNB and written in the supply contract; a registered electrical contractor can confirm it at the meter panel.
TNB's Connection Charge Book (2025 edition) ties each CT size to a maximum demand band, so the ratio shows what the supply was planned for:
| CT ratio | Maximum demand band | TNB load charge |
|---|---|---|
| 150/5 | 61 to 90 kW | RM4,050 |
| 200/5 | 91 to 120 kW | RM5,400 |
| 300/5 | 121 to 180 kW | RM8,100 |
| 400/5 | 181 to 240 kW | RM10,800 |
| 600/5 | 241 to 360 kW | RM16,200 |
| 800/5 | 361 to 480 kW | RM21,600 |
| 1000/5 | 481 to 600 kW | RM27,000 |
| 1200/5 | 601 to 720 kW | RM32,400 |
| 1500/5 | 721 to 850 kW | RM38,250 |
TNB notes that the CT ratio on site is subject to technical requirements, so treat it as strong evidence rather than a certificate. Above 1,000 kVA (850 kW), the book says supply must be taken at medium voltage.
3. The TNB bill
TNB's tariff now follows supply voltage (myTNB billing components): the old Tariff D is now the Non-Domestic Low Voltage tariff, and E1 and E2 are now Medium Voltage General and Medium Voltage ToU. A medium voltage bill charges every kW of maximum demand, which TNB defines as twice the highest number of kWh supplied in any 30 consecutive minutes of the month, so 12 months of bills show how close the current occupier runs to the supply. A low voltage bill shows usage rather than capacity, so rely on the contract and the meter there. Our TNB tariff 2026 guide for factories explains every line of the bill.
4. The main switchboard
The main incoming breaker belongs to the occupier. A large breaker does not mean TNB approved that much power. The myTNB FAQ also says a contractor may not upgrade only the fuse without applying to TNB, because any change to TNB's meter or fuse is prohibited.
5. Form G, Form H and the single line diagram
The last wiring job should have left Form G (supervision and completion certificate) and Form H (test certificate) from the registered electrical contractor, which TNB asks for with every upgrade application. The single line diagram shows the incoming switch, busbar and outgoing circuits.
How do I apply to TNB for more power?
ESAH 1.1.5.1 splits every new supply and every upgrade into two routes: up to 100A, and above 100A.
Up to 100A
- Appoint an electrical contractor from the Energy Commission's list. TNB advises asking several for quotations first.
- The contractor submits the application with Form G and Form H. Online applications on myTNB cover a maximum demand of up to 60 kW (100A); large power consumers apply at Kedai Tenaga.
- Pay the connection charge, RM10 stamp duty and the security deposit.
- TNB installs the meter and connects the supply.
Above 100A
- Appoint one Electrical Consultant Engineer registered with the Board of Engineers Malaysia, with an appointment letter (ESAH Appendix 5).
- Where building works need planning approval (Part A), plans go to the local authority or One Stop Centre. TNB takes up to 14 days to comment at each stage and agrees the substation number, size and location with your consultant.
- In Part B the consultant applies through myTNB and the TNB local office with the load summary, a Power Quality Compliance Declaration, CT metering details, the single line diagram and the switchroom layout.
- TNB checks the documents, runs a system study, holds a joint meeting and confirms the final proposal in writing.
- TNB issues a Notice of Connection Charges, and you pay.
- If a substation is needed, you build it to TNB's specification and hand it over.
- Your electrical contractor applies for the meter, and TNB energises the supply.
What a tenant needs
For commercial and industrial customers, TNB's document list (ESAH Appendix 2) asks for proof of land ownership or consent from the landowner and the Development Order from the local authority, besides the tenancy agreement pages. The supply contract also requires you to tell TNB of any extension or alteration to the installation. Get the landlord's written consent, and agree who pays and who owns the new equipment at the end of the lease, before you sign. Our partner site's guide on what to check before renting a factory in Rawang covers the rest of that checklist.
How much does a TNB upgrade cost?
- Low voltage load charge. TNB charges by the declared maximum demand band. For non-domestic three phase supply, 11 to 37 kW is RM1,700 and 38 to 60 kW is RM2,700; CT metered bands are in the table above. On an upgrade you pay the difference between the new and the existing load charge, so moving from 38 to 60 kW (RM2,700) to the 121 to 180 kW band (RM8,100) costs RM5,400 in load charge.
- Conditions. These rates apply when the source is within 6 km, and when the substation land and building are handed over for RM10 or no substation is needed. Beyond 6 km TNB adds cable charges, and special requests or council requirements are charged on top.
- Medium voltage. RM45 per kW of declared maximum demand. For 5 years after an upgrade, TNB can levy a Connected Load Charge if recorded demand falls below the reference.
- Deposit. About two months' estimated bill; above RM2,000 TNB encourages a bank guarantee (ESAH 1.3.6).
- Outside TNB. The consultant, the contractor, cables, the switchboard and any substation building are quoted separately.
The book's terms were approved by the Energy Commission from 15 January 2021 and can change, so go by the figure in your Notice of Connection Charges.
How long does a TNB upgrade take?
ESAH 1.3.5 gives TNB's typical supply project lead time, provided there is no delay in local authority approval:
| Supply | Typical lead time |
|---|---|
| 400V and below, without a substation | Less than 3 months |
| 400V and below, with a substation | 3 to 12 months |
| 11kV | 6 to 12 months |
| 33kV | 18 months to 2 years |
| 132kV and above | 3 to 5 years |
Time is usually lost before TNB starts: Part A approvals, a landlord who has not consented, resubmitted drawings, or substation land without a title, which needs a 12 month bank guarantee renewed until the land is transferred. TNB asks applicants to apply as early as possible.
Upgrade, or find a factory that already has the power?
If your number stays inside the band the unit already has, an upgrade is a paperwork job. If it crosses about 505A where no substation exists, you need land for one, and on a rented unit only the owner can give it. Then a factory whose supply is already energised is usually faster: see high-power factories in Selangor, and our TNB amperage guide for the ranges different industries tend to look for.
Common mistakes to avoid:
- Comparing amps with kVA, or kW with kVA, without the power factor.
- Taking the breaker rating as the TNB supply.
- Leaving out the compressor, chiller, cold room or welding sets.
- Ignoring how large motors start.
- Declaring far more than you need on medium voltage.
- Signing a lease before the landlord agrees to the upgrade.
Costs, tax and financing: more questions
How much does it cost to upgrade a factory to three phase power?
On TNB's table, a non-domestic single phase overhead supply up to 10 kW carries a RM450 load charge and a three phase supply of 11 to 37 kW carries RM1,700, so the difference is RM1,250. Underground cabling, more distance, the contractor's wiring and a larger deposit come on top.
Can I rent a factory and upgrade the TNB supply myself?
Yes, but TNB asks commercial and industrial applicants for proof of land ownership or the landowner's consent. Above about 505A a new substation is needed and its land goes to TNB, which only the owner can agree to. Settle consent, cost and reinstatement in the tenancy before you sign.
Frequently Asked Questions
What kind of factory is 600 amp power suitable for?
600A, about 416 kVA or roughly 353 kW of running load at a power factor of 0.85, suits food processing (typically 300A to 800A) and is the usual starting point for a small plastic injection moulding factory. Larger injection or CNC lines often need 800A to 1,500A, and cold storage 1,000A to 2,000A. TNB needs a new substation for a supply above about 505A, so a unit with 600A already energised can save the 3 to 12 months that work typically takes. Size it from your machine list with an engineer.
Is 800 amp power enough for a factory?
For many factories, yes. 800A is about 554 kVA, enough for roughly 471 kW of running load at a power factor of 0.85. That covers most food processing (typically 300A to 800A) and the lower end of plastic injection moulding and CNC machining (800A to 1,500A). Cold storage (1,000A to 2,000A) and metal stamping, electroplating or foundry work (1,500A to 3,000A and above) usually need more. Add up your machines, allow room to grow, and check the TNB supply contract before you sign.
How do I apply for three-phase power for a factory?
You apply to TNB through a registered professional, not on your own. Up to 100A (72 kVA), appoint an electrical contractor registered with the Energy Commission: they do the wiring and submit the application with Form G and Form H, online on myTNB for up to 60 kW. Above 100A, an Electrical Consultant Engineer registered with the Board of Engineers Malaysia applies with your load list. You pay TNB's connection charge, RM10 stamp duty and a deposit, then TNB installs the meter. A tenant also needs the landlord's written consent.
How do I know how much kVA I need?
Add the nameplate kW of all your machines and building loads, multiply by the share that runs at the same time, and divide by the power factor, usually 0.85. Add room to grow. For example, 104 kW running at 0.85 is about 122 kVA, or about 153 kVA with 25% spare. A registered electrical engineer confirms the figure before it goes to TNB.
How many kVA is 400 amps 3 phase?
At 400V three phase, 400A is 1.732 x 400 x 400 / 1,000, about 277 kVA. At a power factor of 0.85 that carries about 236 kW of running load. It sits in TNB's band above 100 kVA to 350 kVA, which is CT metered and fed from a feeder pillar or substation after TNB's study.
How do I work out kW from kVA?
Multiply kVA by the power factor: 100 kVA at 0.85 is 85 kW. TNB requires a power factor of at least 0.85 for supplies below 132kV, and its load summary asks about capacitor banks, which are the usual way to raise it.
How long does TNB take to upgrade power supply to a factory?
TNB's handbook gives under 3 months at 400V when no new substation is needed, 3 to 12 months when one is, and 6 to 12 months at 11kV, assuming no delay in local authority approval. Any upgrade above 100A goes through a consultant engineer, so allow time for drawings and the system study.
How do I upgrade my factory's electricity supply to three phase?
Appoint an electrical contractor registered with the Energy Commission. The contractor submits the application with Form G and Form H, online on myTNB for up to 60 kW (100A) or at Kedai Tenaga for larger loads. You pay the connection charge difference, RM10 stamp duty and an extra deposit, then TNB changes the meter.