Key Takeaways

  • TNB charges a factory that upgrades the difference between the new and the old load charge. On the 400V CT-metered scale the charge runs from RM4,050 (61 to 90 kW) to RM38,250 (721 to 850 kW), so going from about 300A to about 800A costs RM13,500 in load charge. Add an extra security deposit, RM10 stamp duty, and your own consultant, contractor, cables and switchboard.
  • The amps you want decide the route: up to 100A a registered electrical contractor applies; above 100A a consultant engineer applies; above 350 kVA (about 505A) TNB needs a new substation on your land; from 1,000 kVA (about 1,443A) TNB supplies 11kV and you buy and own the transformers.
  • TNB's typical lead time is under 3 months at 400V without a new substation, 3 to 12 months with one, and 6 to 12 months at 11kV, provided local authority approvals are not delayed.
  • 3,000A is possible, but not as a TNB low voltage supply. At about 2,078 kVA it is fed at 11kV through a TNB switching station, with your own transformers stepping down to 400V. TNB's medium voltage load charge is RM45 per kW of declared maximum demand.
  • TNB bills whoever applies, but a tenant cannot finish an upgrade alone: TNB asks industrial applicants for the landowner's consent, and only the registered owner can transfer or lease substation land to TNB. Settle who applies, who pays and what happens at the end of the lease before you sign.

A TNB power upgrade for a factory costs the difference in TNB's published load charge plus a deposit and stamp duty, and whatever your own engineer, contractor and site works cost on top. What makes the bill small or large is the route your target amps fall into: a meter change, a new substation on your land, or an 11kV intake with your own transformers. This guide is for the buyer, tenant or owner of a factory or warehouse who needs more power than the unit has. It covers what TNB charges, how long each route takes, when a substation or your own transformer is needed, whether 3,000A is possible, and how to handle a landlord who says no.

The figures come from TNB's Electricity Supply Application Handbook (ESAH 3.1), TNB's Connection Charge Book (2025 edition), whose terms the Energy Commission approved from 15 January 2021, and the Electricity Regulations 1994. To turn a machine list into amps, start with our guide on how much kVA your factory needs or the factory power calculator; this guide picks up once you know the number.

Which upgrade route applies to the amps you need?

TNB plans every supply around maximum demand (MD), the highest load the factory draws. The band your new MD falls into decides who must apply, whether TNB needs a substation, and what voltage you receive. Amps below are at 400V three phase (amps = kVA x 1,000 / (1.732 x 400)).

Target supply About amps at 400V Who applies What TNB requires (ESAH Table 3-1)
Single phase 230V, up to 12 kVA Single phase only Contractor registered with the Energy Commission Service from the existing low voltage network
Three phase, whole current meter Up to 100A Contractor registered with the Energy Commission Service from the existing low voltage network, subject to TNB's study
Above 100A to 100 kVA, CT metered About 100A to 145A Electrical Consultant Engineer registered with the Board of Engineers Malaysia Existing low voltage network, subject to TNB's study
Above 100 kVA to 350 kVA About 145A to 505A Consultant engineer Cable from a feeder pillar or a new or existing substation, subject to TNB's study
Above 350 kVA to 1,000 kVA About 505A to 1,443A Consultant engineer Direct cable from a new substation
1,000 kVA to below 5,000 kVA Above about 1,443A, including 3,000A Consultant engineer 11kV through a TNB switching station; more land for a 33/11kV main distribution substation (PPU) may be needed

Three rules from the handbook sit behind the table. A three phase whole current meter is rated 10A to 100A, and low voltage consumers taking more than 100A per phase need current transformer (CT) metering. Consumers below 132kV must keep their power factor at 0.85 or higher, so 1,000 kVA carries about 850 kW. And the table is a minimum: if TNB's system study finds that a higher supply scheme is needed for quality of supply, TNB's scheme prevails.

How much does a TNB power upgrade cost?

TNB's own part is a published formula: the load charge difference, a larger deposit and RM10 stamp duty, with cable, special request and land costs only where they apply. Everything on your side of the meter is quoted privately and varies with the site, so ask your consultant for a bill of quantities and compare quotations.

What TNB charges

Item Rule Source
Load charge at 400V By declared MD band. Non-domestic single phase up to 10 kW: RM450 overhead or RM1,700 underground. Three phase 11 to 37 kW: RM1,700; 38 to 60 kW: RM2,700. CT metered: RM4,050 (61 to 90 kW) up to RM38,250 (721 to 850 kW) Connection Charge Book, Table 1
Load charge at 11kV, 22kV or 33kV RM45 per kW of declared MD Connection Charge Book, 3.2
Upgrade You pay the difference between the new and the existing load charge Connection Charge Book, 4.1(a)(iii)
Distance Above 6 km from the nearest source that can meet your load, cable charges per metre, for example RM149 per metre for 11kV 240mm² underground cable. The same rates apply to service cable beyond 30 m Connection Charge Book, Table 2; ESAH
Special requests and council conditions Full cost or the cost difference, for example horizontal directional drilling required by a council. An extra 11kV feeder is RM50,000 per unit of switchgear, plus cable Connection Charge Book, 4.1(c) and Table 3
Security deposit About two months' bill; a load change needs an additional deposit; above RM2,000 TNB encourages a bank guarantee ESAH 1.3.6; myTNB upgrade page
Stamp duty RM10 myTNB upgrade page

The 400V rates apply where the substation land and building are handed to TNB for a nominal RM10, or where no substation is needed. The connection charge can be paid in instalments with a surcharge; TNB starts work after the first payment and connects only when the balance is paid. If you cancel before TNB starts work, it keeps an administration fee of 10% of what you paid, capped at RM5,000 for low and medium voltage.

Worked examples: TNB's load charge for common factory upgrades

Amps are converted at 400V three phase and a power factor of 0.85 (kW = amps x 1.732 x 400 x 0.85 / 1,000). TNB charges on the MD you declare, and the binding figure is the one in its Notice of Connection Charges.

Upgrade Declared MD Load charge before and after TNB load charge payable
Single phase overhead to three phase, up to 37 kW Up to 37 kW RM450 to RM1,700 RM1,250
Three phase 100A to about 300A About 59 kW to about 177 kW RM2,700 to RM8,100 RM5,400
About 300A to about 800A About 177 kW to about 471 kW RM8,100 to RM21,600 RM13,500
About 800A to about 1,200A About 471 kW to about 707 kW RM21,600 to RM32,400 RM10,800
About 1,200A to about 3,000A (moves to 11kV) About 707 kW to about 1,767 kW RM32,400 to about RM79,500 at RM45 per kW About RM47,100 on the upgrade rule; confirm with TNB

Costs outside TNB that usually decide the budget

  • People. A consultant engineer above 100A and an electrical contractor registered with the Energy Commission. Their fees are quoted, not published.
  • Your side of the meter. A main switchboard and cables sized for the new current, a cable trench from TNB's substation to your main switchroom, and a metering panel or cubicle (ESAH 1.3.6).
  • The substation site, where one is needed. A 7m x 5m plot for a compact substation, transferred to TNB for RM10. For compact substation applications submitted after 22 November 2024, TNB says it builds the plinth and installs the unit at its own cost; you still identify the site with TNB, get planning permission or authorisation for it, mark the boundaries, have a licensed land surveyor confirm it is free of encroachments, and submit a soil investigation report certified by an engineer. An indoor substation is a building you put up to TNB's specification (7.6m x 5.7m single chamber, 10.6m x 5.7m double chamber) and hand over with its Certificate of Completion and Compliance.
  • At 11kV. Your own switchgear, transformers, protection and consumer substation, plus a 7.6m x 5.7m building for TNB's 11kV switching station, the size ESAH lists for a large power consumer.
  • No title yet for the substation land. A 12 month bank guarantee to TNB, renewed until the transfer or lease is registered.

What keeps costing after an 11kV upgrade

  • Connected Load Charge (CLC). RM8.50 per kW each month for any shortfall between your recorded MD and the reference MD. An existing medium voltage consumer adding load carries it for 5 years; a low voltage consumer who moves up to medium voltage is treated as a new supply and carries it for 6 years. The reference is 85% of the yearly MD you declared in the early years and 75% of your final MD in the last two years, or your highest recorded MD if that is higher. If you declare a final MD of 1,767 kW and never draw more than 1,000 kW, the reference in year 5 is about 1,325 kW and the charge is about RM2,760 that month.
  • Liquidated damages. If you fail to take supply or terminate within 5 years, TNB charges 1/120 x (60 minus the months since commissioning) x (TNB's project cost minus your connection charge).
  • Energy Commission. Section 21 of the Electricity Supply Act 1990 requires an installation to be registered with the Commission unless it is exempted, as the Energy Commission's installation page sets out; your consultant will confirm whether yours is. The yearly fee follows capacity: RM1,650 for 300 to 600 kW and RM2,200 for 600 to 5,000 kW. Regulation 67 of the Electricity Regulations 1994 also sets inspections by a competent person: at least one visit a month for an installation up to 600V fed through switchgear of 100A or more, and two a month from 600V to 11kV, which only an Electrical Services Engineer or a Competent Electrical Engineer may do.

How do you apply to TNB for more power, step by step?

Up to 100A, including single phase to three phase

  1. Appoint an electrical contractor from the Energy Commission's list. TNB advises asking several for quotations first.
  2. The contractor submits the application with Form G (supervision and completion certificate) and Form H (test certificate). Online applications on myTNB cover a maximum demand of up to 60 kW (100A); large power consumers apply at Kedai Tenaga.
  3. You pay the connection charge difference, RM10 stamp duty and the additional deposit.
  4. TNB changes the meter and connects the supply.

Above 100A

If the works need planning approval, Part A comes first: the plans go to the local authority or One Stop Centre, TNB comments within up to 14 days at each stage, and TNB and your consultant agree the number, size and location of substations. A dispute over TNB's proposal goes to TNB's State General Manager. Part B is the supply application:

  1. Appoint one Electrical Consultant Engineer by letter (ESAH Appendix 5).
  2. The consultant applies through myTNB and the TNB local office with the Appendix 4 checklist: total load in kW, site plan with the substation site, substation and switchroom layouts, single line diagram, motor loads, a power quality compliance declaration and, for substation land, Borang A and a copy of the title.
  3. TNB checks the documents, runs a system study and asks for amendments by letter.
  4. A joint meeting settles the substation, cable route and metering; TNB confirms its final proposal in writing.
  5. TNB issues a Notice of Connection Charges, and you pay.
  6. For large developments, TNB and the applicant may sign an Electricity Infrastructure Agreement.
  7. You complete and hand over the substation site or building; TNB installs and commissions its equipment.
  8. Your contractor applies for the meter, and TNB energises the supply.
Consultant engineer and factory owner review drawings while a contractor checks the meter panel
IllustrationConsultant engineer and factory owner review drawings while a contractor checks the meter panel

How long does a TNB power upgrade take?

TNB's typical lead time depends on the voltage and on whether a substation must be built. ESAH 1.3.5 gives these figures, provided local authority approval is not delayed:

Route Typical TNB lead time
400V and below, no new substation Less than 3 months
400V and below, with a new substation 3 to 12 months
11kV 6 to 12 months
33kV 18 months to 2 years
132kV and above 3 to 5 years (fast track 12 to 24 months on conditions)

The clock usually slips before TNB starts: a landlord who has not signed, planning permission for a substation site, drawings sent back for amendment, a substation plot without a title, or, at 11kV, the delivery time of your own transformers and switchgear. TNB asks applicants to apply as early as possible and keep it informed of progress. Line up your fit-out period and rent start with these figures, not with the day you sign.

Does a factory need its own substation or transformer, and can it go to 3,000A?

When TNB needs a substation on your lot

Above 350 kVA, about 505A, ESAH requires a direct cable from a new substation. The Connection Charge Book adds that any load above 60 kW must provide substation land, and that at 60 kW or less TNB may still ask for one if the nearest substation cannot meet the load. TNB's own guidance says a new substation is considered when existing substations can no longer support the increased demand. The land goes to TNB for RM10, and TNB keeps the right to use the substation to supply other consumers.

A compact substation serves up to 1,000 kVA for commercial and industrial use, subject to a matching metering kiosk. TNB rules it out, in favour of an indoor substation, at sites identified for circuit breakers, places with more than two 11kV feeders, MSC status areas and inside attached substation buildings. Land sizes and every substation type are in our TNB substation guide.

Who buys the transformer

  • At 400V, you never buy TNB's transformer. It sits in TNB's substation, TNB installs and commissions it, and you pay the connection charge and provide the land (and, for an indoor substation, the building).
  • At 11kV and above, the transformers are yours. ESAH notes that TNB does not supply voltages outside its standard levels, but consumers can make their own transformation arrangements. You buy, own and maintain the transformers, switchgear and protection. No official price list exists: the cost depends on rating, type and supplier, so get the consultant's specification and competing quotations.

Can a factory get 3,000A?

Yes, through an 11kV intake. At 400V, 3,000A is about 2,078 kVA. The Connection Charge Book says loads above 1,000 kVA (850 kW) must take supply at medium voltage, and ESAH feeds 1,000 kVA up to below 5,000 kVA directly through a TNB 11kV switching station, with land for a 33/11kV main distribution substation if TNB's study calls for it. So a "3,000A factory" is an 11kV customer whose own transformers feed a large 400V main switchboard. Plan for:

  • A load charge of RM45 per kW, about RM79,500 for 1,767 kW, less your existing load charge on an upgrade.
  • Your own 11kV switchgear, transformers and consumer substation, and the 7.6m x 5.7m building for TNB's switching station.
  • 6 to 12 months of TNB lead time, plus equipment delivery.
  • 6 years of CLC if you move up from low voltage, and two competent person inspections a month.

If you need 2,000A or more on a fixed date, it is usually faster to start from a unit with an 11kV intake that is already energised: see high-power factories in Selangor.

Is there enough power supply in the industrial estate?

Nobody can confirm it from the roadside. Every scheme below 1,000 kVA in ESAH Table 3-1 is "subject to system capability study by TNB", and that study only runs once your consultant submits the load. What you can do is narrow the risk before you commit:

  • Read the unit's own record. The TNB supply contract (declared MD and CT size), the meter's CT ratio and 12 months of bills show what the unit was planned for. Our kVA guide explains each document.
  • Look for the substation, then check whose it is. A TNB substation on the lot or in the row helps, but it may already feed the neighbours, and TNB may use it for others. The title shows whether land was transferred or leased to TNB.
  • New estates. TNB plans substations for a development on the total MD of all its parcels (ESAH Table 3-2), so ask the developer for the substation layout and the TNB comments on the approved plan.
  • Large loads. From 1,000 kVA a main distribution substation site may be needed, and from 5,000 kVA supply moves to 33kV.

The safest order is to have your consultant submit the application and obtain TNB's written final proposal before you commit, or to make the tenancy or the sale and purchase agreement conditional on it.

Engineer studies the substation at the end of a factory row, with cables running to each unit
IllustrationEngineer studies the substation at the end of a factory row, with cables running to each unit

Who pays for a power upgrade when you rent, the landlord or the tenant?

No TNB rule decides it. TNB charges whoever applies, and the Connection Charge Book puts the connection charge and the substation land costs on the consumer or developer; between landlord and tenant it is whatever the tenancy agreement says. Four facts should shape that negotiation:

  • The upgrade stays with the building. When a new consumer takes over premises whose TNB equipment is in good condition, TNB charges a reconnection fee of RM3 at low voltage or RM80 at medium voltage instead of a new connection charge, so the next tenant inherits the supply. The substation plot is transferred or leased to TNB for RM10 and is no longer the owner's to use.
  • The account and the deposit belong to the applicant, usually the tenant.
  • At 11kV, a CLC period can pass to the next occupier. A new consumer taking over through a change of tenancy continues the previous consumer's remaining CLC period.
  • The tenant's own switchboards and cables are tenant's works. Whether they stay or must be removed at the end is a reinstatement question; see our reinstatement works guide.
Arrangement Usually fits when Write into the tenancy
Tenant pays everything The upgrade serves the tenant's process and the term is long enough to use it Landlord signs TNB consent and Borang A within a set number of days; tenant need not downgrade or remove TNB works at the end
Landlord pays and recovers through rent The extra supply makes the unit easier to let later Rent step from the energisation date; who owns the switchboard
Split: landlord pays what stays (land, substation building, intake), tenant pays connection charge, deposit and its own distribution Both sides gain A cost cap for each side and what happens if TNB's study asks for more
Tenant pays, landlord credits rent The landlord agrees the value but not the cash outlay The credit schedule and a refund if the lease ends early through no fault of the tenant

In multi-tenanted commercial premises, ESAH 1.1.5.6 lets the owner take a bulk supply (with a public distribution licence from the Energy Commission) or individual supplies. If you sit on the owner's bulk supply, only the owner can apply for more.

What can you do if the landlord will not upgrade the power?

You cannot go over the landlord's head. TNB's document checklist (ESAH Appendix 2) asks commercial and industrial applicants for proof of land ownership or the landowner's consent and the local authority's development order. Above 100A, the consultant's checklist also needs the owner's details, Borang A for the substation land and a copy of the title, and only the registered owner can transfer or lease a substation site. Your options are to change the deal, change the load or change the unit.

  1. Find out exactly what is refused. Signing a consent letter, giving up a substation plot and paying for the works are three different requests. On a small lot the 7m x 5m plot is often the real objection.
  2. Ask for consent without land. If your target stays at or below about 505A (350 kVA), TNB may supply from the existing network after its study, so only the consent letter is needed.
  3. Take the cost and the risk off the landlord. Offer to pay the TNB charges and the land transfer costs, to leave the TNB works in place at the end, and to sign a longer term. If the title is charged to a bank, ask the owner's lawyer what the bank must approve.
  4. Lower the peak. Ask your engineer whether power factor correction, soft starters or staggered machine starts keep the maximum demand within the current band; TNB's application already asks for motor starters and capacitor banks.
  5. Use a generator as a stopgap. ESAH allows standby generators, subject to the law, as a separate system connected through an approved changeover; the Energy Commission and other authorities govern their use.
  6. Leave, or never sign. If the offer letter or tenancy promised a supply the unit does not have, take legal advice before withholding rent or walking away. Better, write the upgrade into the offer letter: the landlord's signatures within a set number of days, TNB's written proposal as a condition, and rent starting from energisation.
  7. Move to a unit that already has the power. A factory whose intake is energised at your amps avoids the landlord question and the lead time.

Mistakes that cost months

  • Asking a contractor to fit a bigger fuse or breaker instead of applying. myTNB states that any change to TNB's meter or fuse without applying is prohibited.
  • Treating the amps in an advert as approved supply, instead of reading the supply contract and the CT ratio.
  • Paying a connection charge before the landlord has signed, then paying the cancellation fee.
  • Declaring far more than you will use at 11kV, then paying the CLC every month.
  • Starting rent on a date that ignores the 3 to 12 month substation lead time.

Practical steps: more questions

My landlord will not upgrade the power. What can I do?

TNB needs the landowner's consent, and only the owner can hand over substation land, so you cannot apply around the landlord. Offer to carry the cost and risk, keep your demand below about 505A so no new substation is needed, ask your engineer to lower the peak, use a generator as a stopgap, or move to a unit that already has the supply.

Can a factory get 3000A from TNB?

Yes, but as an 11kV supply. 3,000A at 400V is about 2,078 kVA, above the 1,000 kVA limit for low voltage supply, so TNB feeds you through an 11kV switching station and you own the transformers that step it down. The load charge is RM45 per kW of declared maximum demand and the typical lead time is 6 to 12 months.

Can my electrician just install a bigger breaker or fuse to get more power?

No. Your main breaker belongs to your installation, but the supply TNB approved is set by your contract and meter, and myTNB states that changing TNB's meter or fuse without an application is prohibited. Any increase goes through an application by a registered contractor or, above 100A, a consultant engineer.

This guide summarises TNB's and the Energy Commission's published rules for Peninsular Malaysia; it is not legal, tax or engineering advice, and your consultant engineer and TNB have the final word for your site. Tariffs after an upgrade, backup generators and solar on a rented factory are covered in separate FactoryHub guides.

For a unit in Klang, see Ms Teh Seok Hoon on substation costs and who pays in Klang; for Rawang, Serendah and Shah Alam, Jason Low on landlord terms and 3,000A upgrades.

Frequently Asked Questions

Where can I buy a factory with a 2,000A power supply?

On FactoryHub, most factories for sale stating 2,000A or more are in the Port Klang belt and Kapar, with some in Shah Alam, Telok Panglima Garang and Semenyih. At 400V, 2,000A is about 1,386 kVA, above the 1,000 kVA at which TNB supplies at 11kV, so such a factory normally has its own transformers and switchgear, which pass to you with the sale. Ask for the TNB supply contract, the declared maximum demand and the transformer maintenance records. Search by amperage on FactoryHub or ask Peter Tan or Jason Low.

How much does it cost to upgrade a factory's power supply with TNB?

TNB charges the difference between the new and the existing load charge. On its 400V scale that is, for example, RM13,500 to go from about 300A to about 800A, and RM10,800 from about 800A to about 1,200A. You also pay an additional deposit, RM10 stamp duty, and your consultant, contractor, switchboard and any substation works.

How much does TNB charge for 3-phase installation?

For non-domestic supply, TNB's load charge is RM1,700 for a three phase supply of 11 to 37 kW and RM2,700 for 38 to 60 kW. Upgrading from a single phase overhead supply pays the difference, for example RM1,250 to reach the 11 to 37 kW band. Stamp duty of RM10, an additional deposit and the contractor's wiring come on top.

How long does TNB take to upgrade power supply to a factory?

TNB's handbook gives under 3 months at 400V when no new substation is needed, 3 to 12 months when one is, and 6 to 12 months at 11kV, assuming no delay in local authority approval. Above 100A a consultant engineer must prepare the application, so allow time for drawings and TNB's system study.

Does my factory need its own substation?

If your maximum demand goes above 350 kVA, about 505A at 400V, TNB requires direct supply from a new substation, and loads above 60 kW must provide the land. Between about 145A and 505A, TNB decides after its study whether an existing substation or feeder pillar can carry you.

How much does a transformer cost for a factory?

At 400V you do not buy one: the transformer belongs to TNB, and you pay the connection charge and provide the substation land. From 1,000 kVA (about 1,443A) you take 11kV and buy your own transformers and switchgear; TNB publishes no price, so get your consultant's specification and competing quotations.

Is there enough power supply in my industrial area?

Only TNB's system study, run on your consultant's application, gives a firm answer. Before that, read the unit's TNB supply contract, CT ratio and bills, find out whether the nearby substation also feeds other factories, and make your lease or purchase conditional on TNB's written proposal.

Who pays for the power upgrade in a rented factory, the landlord or the tenant?

TNB bills whoever applies, usually the tenant, and the tenancy agreement decides who bears the cost. Because the upgraded supply stays with the building and the next occupier only pays a reconnection fee, tenants often ask the landlord to share the cost, credit rent or waive reinstatement of the TNB works.