Key Takeaways
- Yes, a factory can install a standby generator. TNB's Electricity Supply Application Handbook (ESAH) allows standby generators at a consumer's premises, provided they stay a separate system from TNB's network, switch over through a suitable, approved changeover facility, and you declare the safe installation to TNB. The Energy Commission (Suruhanjaya Tenaga, ST) and other authorities govern their use.
- The Energy Commission rule turns on capacity. A generator of 5 kW or less needs no licence. Above 5 kW, a factory generator for its own use is a private installation activity that needs a licence under section 9 of the Electricity Supply Act 1990; an installation with a standby generator must otherwise be registered with ST. Yearly fees run from RM30 to RM3,000 by installation capacity.
- A competent person must be in charge. Only people who do not work installations generating more than 5 kW are exempt from holding a certificate of competency, so a factory set needs a chargeman (Penjaga Jentera) registered with ST, recommended by an electrical engineer or supervisor, with one on each shift.
- The DOE must hear from you 30 days before work starts. The Clean Air Regulations 2014 require a written notification, Form AS/PUB/N-JANA, one form per generator, covering exhaust height, acoustic treatment and the noise level at the nearest boundary. Diesel is a controlled item under KPDN storage permits, and used engine oil is scheduled waste.
- In a rented factory, get the landlord's written consent before you order the set. ST asks for the land title or tenancy agreement with a licence application, and the tenancy decides who owns, insures, services and removes the generator when you leave.
This guide is for owners, tenants and buyers of detached and semi-detached factories and large warehouses who need power that does not stop. It explains the law for planning purposes and is not legal advice: your electrical consultant, ST, DOE and Bomba decide what a particular installation needs.
Can a factory install a standby generator in Malaysia?
Yes. Section 1.1.5.2 of TNB's ESAH says standby generators may be used by the applicant at their premises, subject to compliance with the relevant laws. Three conditions come with it: the generator remains a separate system from TNB's distribution system, it takes over from TNB's supply only through a suitable, approved changeover facility, and the owner declares to TNB that the generator is safely installed. The handbook also advises voltage sensitive consumers to fit a suitable time delay on the under voltage relay that governs the generator changeover, so a brief dip does not start the set needlessly.
TNB is only one of five offices that touch a generator project. Each has its own paperwork:
| Authority | What it controls | What you file | When |
|---|---|---|---|
| TNB | Separation from TNB's network and the changeover | Declaration of safe installation | Before the set is connected |
| Energy Commission (ST) | Licence or registration, and the competent person | Private installation licence above 5 kW, or registration of the installation; chargeman registration | Before commissioning |
| DOE state office | Exhaust, emissions and noise | Written notification, Form AS/PUB/N-JANA | At least 30 days before work starts |
| Bomba and the council | Fire separation, emergency power, any new structure | Through building plans, the fire certificate process and notice of a material change | Before work starts |
| KPDN | Diesel as a controlled item | Storage permit for the quantity you keep | Before diesel is stored |
What decides how much of this applies to you: the generator's kW rating, whether it is standby only or runs as a supply source, whether it feeds the building's fire safety systems, the size of the fuel tank, and how close the nearest houses, school or clinic are.
Does a factory generator need an Energy Commission licence?
Above 5 kW, yes, or a registration in its place. The details come from the Electricity Supply Act 1990, the Electricity Regulations 1994 and the exemptions listed on ST's exemption page.
5 kW or less: no licence
Exemption Order P.U.(B) 156/1994 frees anyone who operates an installation with its own source of generation from the licence requirement when the generator's capacity is 5 kilowatts or less. A set sized for factory machinery will be above that line, so plan on the paperwork below.
Above 5 kW: a private installation licence
Section 9 of the Act bars anyone other than a supply authority from operating an installation except under a licence, and the Act's definition of an installation includes prime movers. ST's Guidelines on Licence Application (GP/ST/No.52/2024) list two private installation activities that cover factories: generating electricity for own consumption "such as diesel generator" where the consumer owns the asset, and generating electricity for a temporary purpose from a diesel generator for own consumption.
- Private licences below 5 MW are processed by ST's regional offices; 5 MW and above go through ST's Online Application System.
- The application must be made before the installation is commissioned. For private installations below 30 MW, ST recommends submitting three months before the initial operation date, and the Energy Commission approves.
- The applicant must be an entity established, registered or recognised under Malaysian law and must hold a valid land title or tenancy agreement for the premises.
A standby set: registration of the installation
Section 21 of the Act requires an installation to be registered with ST before completion, unless it belongs to a supply authority or is operated or owned by a licensee. The 1994 exemption keeps that registration duty for two kinds of installation: one with a generator connected to provide standby electricity when the primary supply fails, and one receiving electricity at 11,000 volts or more. ST inspects and tests within 21 days of receiving Form A, then issues a Certificate of Registration (Form B) valid for one to five years.
Exemption Order P.U.(B) 307/2012 exempts an installation licensed under section 9 from separate registration, so a factory ends up holding one of the two, not both. Confirm with the ST regional office which one it will process for your set-up before you commission.
What ST charges
The fees are set by installation capacity in the Second Schedule of the Electricity Regulations 1994. Part IA (licence) and Part I (registration) use the same yearly rates:
| Installation capacity | Fee per year | Registration for 5 years |
|---|---|---|
| 10 kW or less | RM30 | RM150 |
| Above 10 kW to 50 kW | RM165 | RM825 |
| Above 50 kW to 100 kW | RM550 | RM2,750 |
| Above 100 kW to 300 kW | RM1,100 | RM5,500 |
| Above 300 kW to 600 kW | RM1,650 | RM8,250 |
| Above 600 kW to 5,000 kW | RM2,200 | RM11,000 |
| Above 5,000 kW | RM3,000 | RM15,000 |
A licence fee is paid in full for the whole licence period, and ST charges a separate fee for each inspection and test. "Installation capacity" means the maximum power at which the installation can be operated without damage to any part of it. Generators are usually sold by kVA while the bands are in kW, so ask your electrical consultant which figure ST will use for your installation.
Documents ST lists for a generator set
ST's Criteria and Documents Required for Licence Application (Below 5MW), December 2024, has a section for generator sets. It asks for:
- The completed application form and the company's legal status documents.
- A key and layout plan and a schematic diagram, prepared by a competent person under regulation 65 or endorsed by a Professional Engineer.
- The lease or contract agreement of the generator, if it is not owned outright.
- ST's registration letter for the chargeman.
- Form G (Supervision and Completion Certificate) and Form H (Test Certificate).
- Generator details: serial number, model, kVA and kW rating, voltage, amperes, frequency and power factor, plus the engine and alternator nameplates.
Penalties
Operating an installation without the licence section 9 requires carries a fine of up to RM50,000, plus up to RM1,000 for every day the offence continues after conviction (section 37(4)). Failing to register an installation under section 21 carries up to RM25,000, plus up to RM1,000 a day (section 37(8)).
Who has to operate the generator?
A competent person certified and registered with ST. The 1994 exemption from holding a certificate of competency covers only people who do not work installations at higher than low voltage, low voltage installations fed through switchgear of 100 amperes or more, or equipment generating more than 5 kW. A factory generator falls on the regulated side.
- Recommended, then approved. Under regulation 60, an Electrical Services Engineer, a Competent Electrical Engineer or an Electrical Supervisor (for installations up to 600 V) recommends the competent person, usually a chargeman, and obtains ST's approval. The owner must follow that recommendation.
- One per shift. Regulation 62 requires the competent person on each shift where an installation runs two or more shifts. For a plant running round the clock, read our guide to 24 hour factory operation.
- Monthly visits. Regulation 67 sets minimum inspection visits by the engineer or supervisor: one a month for a low voltage installation fed through switchgear of 100 A or more, two a month from above 600 V up to 11 kV, and four a month above 11 kV. The owner keeps a book of every report, open to ST at all times (regulation 68).
- Who may sign the drawings. Part VI of the Second Schedule limits an Electrical Supervisor to low voltage installations fed through switchgear of 100 A and below, and a Competent Electrical Engineer who is not a Professional Engineer to low voltage; only a Professional Engineer who is a Competent Electrical Engineer or Electrical Services Engineer has no limit.
If your factory already takes TNB supply through switchgear of 100 A or more, it should already have a chargeman and a visiting engineer. Add the generator to their scope and their logbook rather than hiring someone separately for it.
What does the DOE require for a factory generator?
A written notification at least 30 days before installation starts, a design that keeps noise at the neighbours within the guideline, and proper handling of fuel and waste oil.
The written notification
The Environmental Quality (Clean Air) Regulations 2014 apply to any premises used for industrial or trade purposes, and define fuel burning equipment to include an internal combustion engine. Regulation 5 bars any work that may result in a source of emission without prior written notification, which must reach the Director General not less than thirty days before the work begins.
DOE's Form AS/PUB/N-JANA is the form for generators. It goes to the DOE state office where the premises sits, one form for each generator, and asks for:
- schools, clinics, hospitals and other public facilities within 150 metres of the generator;
- engine maker, model, kVA rating and fuel consumption at full and half load;
- operating hours, or "standby only";
- the acoustic design of the generator house, its air intake and outlet attenuators and silencers (both silencers inside the generator house, or inside a brick chimney if fitted outside);
- the noise level at the nearest premises boundary;
- exhaust height above ground and its direction, with an elevation plan;
- a land use and location plan covering 500 metres around the exhaust;
- A1 drawings certified by a Professional Engineer;
- confirmation that the diesel tank complies with DOE's skid tank guidance.
How much noise is allowed at the neighbours?
The DOE's Guidelines for Environmental Noise Limits and Control (2019) recommend these limits for existing built-up areas, measured at the receiving property:
| Receiving land use | Day (7.00 am to 10.00 pm) | Night (10.00 pm to 7.00 am) |
|---|---|---|
| Low density housing, schools, hospitals, places of worship | 60 dBA | 55 dBA |
| Suburban and urban housing, mixed development | 65 dBA | 60 dBA |
| Commercial zones | 70 dBA | 65 dBA |
| Industrial zones | 75 dBA | 75 dBA |
The guideline's own worked example uses a genset: 72 dBA measured at a plant boundary 12 metres from the set becomes about 68.5 dBA at a house 6 metres beyond the boundary, and a receptor would need to be about 26.9 metres from the set to hear 65 dBA. Distance alone buys little, which is why the enclosure, silencers and the side of the building you put the set on matter more than the brand. A set that runs for weekly tests and outages beside a factory facing housing is judged against the night limits for those homes.
Fuel storage
- Tank design. The DOE form asks you to confirm the diesel tank follows DOE's skid tank guidance, so ask the installer to show it.
- KPDN permit. Diesel is a controlled item under the Control of Supplies Act 1961. In a case reported by Bernama on 14 March 2025, a company held a valid Supply Controller permit to store diesel that allowed 15,000 litres; storing more breached regulation 21(1) of the Control of Supplies Regulations 1974, an offence carrying a fine of up to RM2 million for a company's first offence. Size the tank against what your permit allows, and ask your fuel supplier and KPDN whether your quantity needs one.
Used oil and filters are scheduled waste
Under the Environmental Quality (Scheduled Wastes) Regulations 2005, spent lubricating oil is SW 305, and rags and filters contaminated with it are SW 410. A factory may store its own scheduled waste on site for up to 180 days as long as no more than 20 tonnes accumulate; storing more needs the DOE Director General's written approval. Waste oil can go to a recovery facility licensed by DOE.
Where does Bomba come in?
Bomba's interest depends on what the generator feeds and where it sits.
- As the building's emergency power. By-law 253 of the Uniform Building By-Laws 1984 requires an emergency power system for smoke control, emergency lighting, fire alarms, fire pumps, public address and fire lifts where the building needs them, changing over within 60 seconds of a supply failure. It may be a storage battery that holds at least 87.5% of system voltage for 1.5 hours, or a generator set with automatic starting. If your generator is the approved emergency source, it is part of the fire safety installation; see our guide to Bomba requirements for factories and warehouses.
- Fire separation. By-law 139 requires fire risk areas, among them a boiler room or associated fuel storage area and a transformer room, to be separated from the rest of the building by fire resisting construction. Ask your engineer whether your generator room and its fuel tank fall within it.
- A premises with a fire certificate. Section 32(2) of the Fire Services Act 1988 requires the occupier of a designated premises to notify Bomba before starting a material change while a fire certificate is in force; starting without notice is an offence. Adding a generator room and fuel storage is the kind of change to raise with Bomba first.
- A new structure. A brick generator house or a roofed enclosure outside the approved building is new construction, so ask the council's building department whether it needs plan approval before you build it.
Can a tenant install a generator in a rented factory?
Yes, with the landlord's written consent, and the earlier you raise it the better. ST's licensing guidelines require a valid land title or tenancy agreement with the application, and the DOE form is signed by the owner, the occupier or their authorised consultant. Before you order a set, put these in writing with the landlord:
- Location and works. Where the set, the fuel tank and the exhaust go, the plinth, cable route, wall openings and the changeover switch on the main switchboard.
- Whose name the approvals are in. The ST licence or registration, the DOE notification and any KPDN permit; usually the tenant, as the party that operates the set.
- Insurance. Who insures the set and the fuel, and whether the landlord's fire policy needs to be told.
- Servicing. Who appoints the chargeman, keeps the logbook and pays for the scheduled waste contractor.
- The end of the tenancy. Whether you remove the set and make good, or leave it for the landlord at an agreed price. Our guide to reinstatement works when a factory tenancy ends covers what to agree.
A buyer of a factory that already has a generator should check the same papers and state in the sale and purchase agreement whether the set is included, since a generator left by an earlier tenant may not belong to the seller.
What to do when the factory's power is not enough
A generator is a backup or a bridge, not a replacement for TNB supply. Work through it in this order:
- Measure the gap. Turn the machine list into kVA and amps with our guide to how much kVA a factory needs or the factory power calculator.
- Check what the unit really has. The rating of the incoming switchgear and the TNB supply type, not the figure in a listing.
- Apply to TNB for an upgrade. For a rented unit the landlord's consent decides whether it happens; our partner site explains who pays for a TNB upgrade and what to do when the landlord says no.
- Bridge with a generator on its own circuits. While you wait, a set can carry selected machines on a separate board, never connected to TNB's network, as ESAH requires. It is then no longer "standby only" on the DOE form, and it still needs the ST licence for its capacity: ST lists temporary diesel generation for own use as a private licence activity.
- Stagger the big loads. Spreading start-ups and heavy processes lowers the peak the supply has to carry.
- Consider a different unit. If the gap is large and the timeline is short, a factory with the power already in place may be a faster route than a long upgrade with months of diesel in between.
What to check on site before you rent or buy a factory with a generator
- The nameplate kVA and kW rating, and the ST licence or Certificate of Registration in force with its expiry date.
- Form G and Form H, the single-line diagram, and the chargeman's logbook with the engineer's visit reports.
- A copy of the DOE written notification and any later notice for upgraded silencers or exhaust.
- The changeover: automatic or manual, the interlock that keeps it apart from TNB, and the under voltage relay delay.
- The fuel tank: skid tank and bund condition, and the KPDN permit quantity.
- The generator house: acoustic treatment, exhaust height and direction, and the distance to the nearest homes, school or clinic.
- Who owns the set: the landlord, the seller or a previous tenant.
This guide summarises public rules and is not legal advice; confirm your own case with ST, DOE, Bomba, KPDN, the council or a lawyer.
Frequently Asked Questions
Do I need a licence to run a generator at my factory in Malaysia?
Only if it is above 5 kW, which any set sized for factory machinery will be. A generator of 5 kW or less is exempt from licensing under P.U.(B) 156/1994. Above that, the Energy Commission treats own-use generation as a private installation activity needing a licence under section 9 of the Electricity Supply Act 1990, and a licensed installation needs no separate registration.
How much is the Energy Commission fee for a factory generator?
The yearly fee follows installation capacity under the Electricity Regulations 1994: RM30 for 10 kW or less, RM165 above 10 kW to 50 kW, RM550 to 100 kW, RM1,100 to 300 kW, RM1,650 to 600 kW, RM2,200 to 5,000 kW and RM3,000 above that. Registration can be taken for up to five years at five times the yearly rate, and each inspection and test has its own fee.
Can I install a backup generator in a rented factory?
Yes, with the landlord's written consent. The Energy Commission asks for the land title or tenancy agreement with the licence application, and the works usually touch the landlord's main switchboard, walls and compound. Agree the location, whose name the approvals are in, insurance, servicing and whether the set is removed or left at the end of the tenancy.
Can a standby generator run in parallel with TNB supply to lower my bill?
Not as a standby set. TNB's handbook requires standby generators to remain a separate system from its distribution network and to take over only through an approved changeover facility. Any design that runs a generator alongside TNB supply must be raised with TNB and the Energy Commission first.
What should I do if my factory's power supply is not enough?
Work out the real shortfall in kVA from the machine list, check the unit's incoming switchgear, then apply to TNB for an upgrade, which in a rented unit needs the landlord's consent. A generator on separate circuits can bridge the wait, but it needs the Energy Commission licence for its capacity and a DOE notification, so for a large gap a unit with the power already in place may be the faster answer.
Does a hired or rented generator need approval too?
Yes. The Energy Commission lists temporary generation from a diesel generator for own consumption as a private licence activity, and its document list for a generator set includes the lease or contract agreement of the generator. The DOE notification also covers any generator installed at an industrial premises, whoever owns it.
How much does a factory backup generator cost in Malaysia?
There is no published price; it varies with the kVA rating, the enclosure and acoustic work, the changeover switch, the fuel tank and the cable run. The figures set by law are the Energy Commission fees above. Ask each supplier to quote the set, delivery, installation, the acoustic enclosure, the DOE and ST submissions, and servicing separately so you can compare like with like.
What noise level is allowed for a factory generator near houses?
For existing built-up areas, the DOE guideline recommends 65 dBA by day and 60 dBA at night at suburban and urban homes, 60 and 55 dBA at low density homes, schools and hospitals, and 75 dBA day and night at an industrial receiver. Night runs from 10.00 pm to 7.00 am, so a set tested at night or running through an outage is judged against the lower figure.
FactoryHub is dedicated to helping every client find the right factory or warehouse. If you need a unit with the power, space and approvals for a standby generator, contact Peter Tan (REN 12771) at 016-666 6872 or Jason Low (PEA 1478) at 012-288 1834.