Key Takeaways
- A green certified factory is an industrial building rated under a recognised scheme: GBI (Industrial New Construction or Industrial Existing Building), GreenRE (Industrial Facilities or Existing Industrial Facilities) or LEED. Malaysia has no legal status called an "ESG-compliant factory": the certificate, the energy and water data and the landlord's paperwork are what a tenant's ESG team actually checks.
- Multinationals ask because their own reporting now reaches the buildings they use. Under the National Sustainability Reporting Framework, listed issuers and non-listed companies with revenue of RM2 billion and above adopt the ISSB standards in phases from 2025 to 2027, and a site using 21,600 GJ of energy or more in 12 consecutive months falls under the Energy Efficiency and Conservation Act 2024.
- The certification fee is published: GBI charges RM8,000 to RM45,000 for a new building and RM6,000 to RM19,000 for an existing one up to 100,000 m², excluding SST, and a GBI or GreenRE rating must be renewed every three years. The cost of the upgrades themselves depends on the building and needs a consultant's quote.
- JPPH-registered tenancies do not record whether a unit is certified, so no registered figure proves a "green rent premium". Compare total occupancy cost (rent plus 12 months of TNB bills) inside the same estate instead.
- An older factory can be upgraded and certified under GBI's Industrial Existing Building tool or GreenRE's Existing Industrial Facilities tool. Rainwater harvesting has been a building plan requirement for detached buildings with a roof of 100 m² or more since the 2011 by-law amendment that Selangor gazetted, and EV chargers must follow the Energy Commission's 2025 guidelines.
What is a green certified factory in Malaysia?
A green certified factory is one whose design and operation have been scored by an independent rating body on energy, water, indoor environment, site, materials and innovation, and which holds a valid certificate. Three schemes matter for industrial buildings in Selangor and the Klang Valley.
GBI, GreenRE and LEED compared
| GBI | GreenRE | LEED | |
|---|---|---|---|
| Run by | Greenbuildingindex Sdn Bhd | GreenRE Sdn Bhd, set up by REHDA in 2013 | U.S. Green Building Council |
| Tools for factories | Industrial New Construction (INC), Industrial Existing Building (IEB) | Industrial Facilities (IND 2.0), Existing Industrial Facilities (EIND 2.0) | BD+C for new buildings, O+M for buildings occupied at least one year |
| Rating levels | Certified 50 to 65, Silver 66 to 75, Gold 76 to 85, Platinum 86 to 100 points | Bronze from a score of 50, Silver from 76, Gold from 86, Platinum from 91 | Certified 40 to 49, Silver 50 to 59, Gold 60 to 79, Platinum 80+ |
| Validity | Re-assessed every three years | Certificate valid three years from the Final Certificate | Check the terms of the LEED system used |
Sources: GBI rating system, GBI assessment process, GreenRE IND 2.0 tool, GreenRE certification and USGBC LEED.
For a factory the scoring leans on energy. In GBI's Industrial New Construction reference guide, energy efficiency carries 33 of 100 points, indoor environment 22, site planning 18, materials 10, water 10 and innovation 7. Certified industrial buildings are still few: GBI's project directory listed 61 certified Industrial New Construction projects and 6 Industrial Existing Building projects in its registry figures as of 31 October 2026.
Is an "ESG-compliant factory" a legal status?
No. ESG describes how a company manages environmental, social and governance matters, and it is reported by the company, not stamped on a building. For manufacturers, MITI's i-ESG Framework sets out the path, with Phase 1.0 running from 2024 to 2026. A green building certificate is the strongest single piece of building evidence a landlord can hand over, but a tenant will also want the data behind it.
Why do multinational tenants and buyers prefer green certified factories?
Because the factory's electricity, water and waste end up in their reports. The Securities Commission's NSRF FAQ (issued 14 January 2026) sets the timetable:
- Main Market issuers with market capitalisation of RM2 billion and above began in 2025, other Main Market issuers in 2026, and ACE Market issuers and non-listed companies with annual revenue of RM2 billion and above in 2027.
- Groups 1 and 2 are expected to disclose all relevant Scope 3 (value chain) emissions from 2027 and 2028, and Group 3 from 2030. Scope 3 is where a customer counts its suppliers, which is why exporters supplying multinationals are now asked for data too.
- The aim is reasonable assurance on Scope 1 and Scope 2 emissions for Group 1 from reporting periods beginning on or after 1 January 2027.
The energy law adds a second layer. Under the Energy Efficiency and Conservation Act 2024, in force since 1 January 2025 in Peninsular Malaysia, a consumer using 21,600 GJ or more in 12 consecutive months must appoint a registered energy manager within 3 months of the Energy Commission's notice, run an energy management system within a year, file yearly reports and submit an energy audit report within a year of the notice and then every 5 years. The Energy Commission gives large manufacturing plants as an example of such users, and its energy consumer page sets out the deadlines. On top of that, MOF's Economic Outlook 2027 lists a carbon tax "in the pipeline", beginning with the iron and steel industry.
What MNC tenants usually ask to see
| They ask for | Why | What to check on site |
|---|---|---|
| The certificate and score sheet | Proof of the rating and its date | Certificate level, tool used, expiry (three-year cycle) |
| 12 months of TNB bills and sub-meter readings | Scope 2 data and energy intensity | Separate meters for production, office and chillers; GBI awards points for electrical sub-metering |
| A roof ready for solar | Own renewable supply | GreenRE's Platinum prerequisite asks for a roof pitch of 5 to 30 degrees, checked static loads, a mounting system and roof access |
| A green electricity option | Renewable claims without a roof system | TNB's Green Electricity Tariff premium from as low as 3 sen/kWh on a 3-year subscription; GET Greenpath, open since 1 August 2025, serves tenant accounts not registered directly with TNB |
| Water data | Water reporting | Rainwater tank, water meters, leak detection |
| EV charging bays | Fleet and staff targets | Spare electrical capacity and a compliant charger circuit |
| Recent energy audit | Baseline for targets | GreenRE's existing industrial tool gives credit for an audit by an Energy Commission approved auditor within the last two years |
Power is usually the first constraint: check the incoming supply with the factory power calculator before promising chargers or electrified equipment, and see our guide to TNB ToU for factories for how the tariff shapes the bill.
How much does green certification cost, and who pays?
The rating body's fee is fixed by floor area; consultants, modelling, commissioning and the upgrades are quoted separately and vary with the building, so ask for written quotes before you budget.
| Gross floor area (m²) | GBI new construction (incl. INC) | GBI existing building (incl. IEB) | GreenRE new building | GreenRE existing building |
|---|---|---|---|---|
| Up to 4,000 | RM8,000 | RM6,000 | RM8,000 | RM6,000 |
| 4,001 to 10,000 | RM10,000 | RM9,000 | RM10,000 | RM9,000 |
| 10,001 to 30,000 | RM20,000 | RM12,000 | RM20,000 | RM12,000 |
| 30,001 to 50,000 | RM32,000 | RM14,000 | RM32,000 | RM14,000 |
| 50,001 to 100,000 | RM45,000 | RM19,000 | RM45,000 | RM19,000 |
Sources: GBI registration fees (rates exclude service tax; GBI's home page notes 8% SST on its invoices from 1 March 2024) and the GreenRE fee brochure dated March 2022 (excluding SST, 20% off for REHDA members). GreenRE also charges RM5,000 (new) and RM3,000 (existing) below 2,000 m². Above 100,000 m² both bodies quote project by project. GBI's fee covers one design assessment and one completion and verification assessment; renewal is extra.
Tax allowances: what changes on 1 January 2027
For qualifying spending from 1 January 2024 to 31 December 2026, MGTC's GITA Asset guideline gives a 100% allowance for green buildings, EV charging systems and battery storage, and 60% for solar, rainwater harvesting and listed efficient equipment, set off against 70% of statutory income. The asset must be new, owned by the company and for its own use; a green building claim needs the Final Green Building Certificate and a Green Cost Certificate, filed within 36 months of the spending.
Budget 2027 extends GITA from 1 January 2027 to 31 December 2030 with a new list: 100% for locally made EV infrastructure, wastewater recycling and rainwater harvesting systems and for renewable energy combined with battery storage, 60% for the other listed items, with applications to MGTC within 24 months of purchase. Green buildings are not on the 2027 to 2030 list. This is not tax advice: confirm eligibility with MGTC and your tax adviser.
Who pays in a tenancy
The landlord normally pays to certify the building, because the certificate stays with the title. Items the tenant installs for its own use (chargers, meters, process equipment) are the tenant's, and the tenancy should say whether they stay or are removed at the end. Agree this in writing before work starts, alongside the repair and reinstatement terms.
Is the rent higher for a green certified factory?
There is no registered evidence either way. JPPH tenancy records give rent, area and location, not certification. For context, the Shah Alam registered data shows 119 factory tenancies in the 24 months to August 2026, with a median of RM1.71 psf/month and a typical range of RM1.28 to RM2.47 psf/month. Where a unit sits in that range is decided by power, clear height, loading, condition, location and the tenancy terms, and a certificate is one of those features.
What to do instead of trusting a "green premium":
- Compare like with like in the same estate using registered rents and prices.
- Ask the landlord for 12 months of TNB bills and water bills for the unit, then compare rent plus utilities, not rent alone.
- Check the certificate date: a lapsed rating is worth little to an ESG team.
- Put the landlord's obligations (renewal, meter access, roof access for solar) into the tenancy.
Do factories in Selangor need rainwater harvesting?
Yes, for new detached buildings with a large roof. The Uniform Building By-Laws 1984 (Amendment 2011) require building plans to show the rainwater harvesting system (SPAH) for bungalows and semi-detached houses with a roof of 100 m² or more, and for all categories of detached buildings with a roof of 100 m² or more. KPKT asked every state to adopt it on 14 July 2011, and Selangor was among the five states that had gazetted it by March 2013, according to PLANMalaysia's SPAH implementation guide. Ask the council's building department whether your factory type falls within "detached buildings": older factories approved before the gazette often have no system.
By-law 115(2) sets the design rules:
- rainwater must not enter the public water supply tank; mains water may top up the rainwater tank only through a one-way check valve or an inlet at least 225 mm above the tank's overflow level;
- SPAH outlets must be clearly marked "Bukan Untuk Tujuan Minuman atau Mandian" (not for drinking or bathing);
- gutters need enough slope that water does not pond; and
- rainwater pipes must be green.
For certification, GBI's industrial new construction tool gives 1 point for rainwater harvesting that cuts potable water use by at least 15% and 2 points for at least 30%, with uses such as toilet flushing, landscape irrigation, floor washing and industrial process water. On a site visit, look for the tank, the first-flush filter, the pump, green pipework and a sub-meter.
Can a factory install EV chargers, and what rules apply?
Yes, within the Energy Commission's Guidelines on Electric Vehicle Charging System (GP/ST/No. 54/2025, dated 24 February 2025):
- Mode 1 charging is not allowed; only Modes 2, 3 and 4 may be used.
- Each charger needs a dedicated final circuit, with the cable armoured, metal sheathed or run in conduit, and no joints.
- Enclosures need at least IP41 indoors and IP44 outdoors.
- Wiring must be done by a competent person, and the charger model needs an Energy Commission Certificate of Approval (Modes 2 and 3) or release letter (Mode 4), obtained by its maker, importer or seller.
- Chargers need reverse power flow protection unless they only charge one way, and maintenance records must be kept.
Anyone carrying out an activity under section 9(1) of the Electricity Supply Act 1990 in relation to the charging system needs a licence. Under the Energy Commission's licence criteria, the application is made by a charge point operator before commissioning, with local authority approval or the building owner's consent letter and drawings from a competent person or professional engineer. If you plan to charge visitors' or other companies' vehicles, plan for that licence; if the chargers serve only your own fleet, ask the Energy Commission how your set-up is treated. For the certification side, GBI's industrial tool awards a point for reserving 5% of car park bays for green vehicles, and GreenRE IND 2.0 gives a credit for one priority bay per 100 car park lots and one charger per 200 bays.
Can an older factory be upgraded and certified?
Yes. GBI's Industrial Existing Building tool gives energy efficiency 38 of 100 points and water efficiency 12, and GreenRE's Existing Industrial Facilities tool applies to buildings completed more than one year, using real operating data. A practical order of work:
- Collect 12 months of electricity and water bills and add sub-meters where loads are mixed.
- Commission an energy audit to see where the most energy can be saved.
- Fix lighting zoning, controls, ventilation and air-conditioning plant.
- Have an engineer check the roof structure before any solar plan.
- Add rainwater harvesting and water-saving fittings where the roof and plumbing allow.
- Set aside green vehicle bays and plan charger circuits within the available supply.
- Provide recycling storage and a building user manual.
- Register with the rating body and book the assessment.
Two checks before any of this: structural or external changes may need council approval, so keep the building's CCC position clean; and a tenant needs the landlord's written consent and an agreed reinstatement position. Separate guides cover solar on a rented factory, TNB power upgrades and repair responsibilities.
Will a green industrial property be worth more?
Nobody can show it from registered sales: JPPH transfers do not record certification, and FactoryHub does not forecast prices. What a buyer or valuer can verify is lower running cost backed by bills, a valid certificate, readiness for EECA duties and a wider pool of multinational tenants. What cuts the other way: a certificate that lapses at the three-year renewal, upgrades that belong to a departing tenant, and paying for features the next occupier does not need. Check same-estate registered prices on the industrial transactions page and, if you are selling, see which upgrades are worth doing first in this partner guide on selling a factory vacant or tenanted.
Costs, tax and financing: more questions
Do Selangor's assessment tax rebates for green features apply to factories?
No. Selangor's 2026 assessment tax rebate for green features, the Insentif Kediaman Mesra Alam Sekitar, is aimed at residential owners. Factory owners should look at the federal GITA allowances instead.
This guide explains rules and published fees; it is not legal or tax advice.
Practical steps: more questions
How long does GBI certification take?
GBI assesses the design first and verifies the completed building within 12 months of completion or once it is 50% occupied, whichever comes first. GreenRE asks for site verification within six months of operation or 50% occupancy, and no later than one year after the CCC. The total time depends on the works.
Frequently Asked Questions
What is a green industrial park in Malaysia?
A green industrial park, also called an eco-industrial park, is an industrial estate planned and managed to improve its environmental, social and economic performance as a whole, not just building by building. Malaysia has no official rating or legal status for it yet: MITI and the World Bank held a workshop in June 2025 to gather views on a National Eco-Industrial Park Programme. In Selangor, PKNS uses the name for GRIP Kota Puteri near Rawang, a 377-acre managed industrial park whose Phase 1 is due in 2027. Ask for each building's own GBI or GreenRE certificate.
How can a factory reduce its carbon emissions?
Measure first, then cut use, then change the power source. Collect 12 months of TNB bills, add sub-meters for production, office and chillers, and commission an energy audit to find where the most energy can be saved. Next fix lighting zoning, controls, ventilation and air-conditioning plant. Then add rooftop solar under Solar ATAP once an engineer has checked the roof, or buy renewable power through TNB's Green Electricity Tariff. Ask your tax adviser whether GITA allowances apply to the equipment.
How can a factory meet the ESG requirements of international clients?
By giving them data, not labels: Malaysia has no legal status called an ESG-compliant factory. Multinational clients usually ask for 12 months of TNB bills and sub-meter readings, a recent energy audit, water data, and a valid GBI or GreenRE certificate if the building has one, because their own reports now count their suppliers' emissions (Scope 3). MITI's i-ESG Framework sets the path for manufacturers, and a site using 21,600 GJ of energy or more in 12 months also has duties under the Energy Efficiency and Conservation Act 2024.
How does a factory set up rainwater harvesting?
Rain from the roof runs through the gutters and a first-flush filter into a storage tank, and a pump sends it to uses such as toilet flushing, landscape irrigation, floor washing or process water. The by-laws say rainwater must never enter the public water supply tank, mains top-up must go through a one-way check valve or an inlet at least 225 mm above the tank's overflow, outlets must be marked not for drinking or bathing, and the pipes must be green. Ask your engineer to size the tank and the council what your plans must show.
What are the requirements for green buildings in Malaysia?
There is no general law forcing a factory to be green certified. The binding rules are specific: rainwater harvesting on detached buildings with a roof of 100 m² or more under the 2011 by-law amendment where the state has gazetted it, EV charger standards from the Energy Commission, and energy management duties for sites using 21,600 GJ or more a year. Certification under GBI, GreenRE or LEED is voluntary.
What is the difference between GreenRE and GBI certifications?
GBI is run by Greenbuildingindex Sdn Bhd and GreenRE by a company set up by REHDA. Both have separate tools for new and existing industrial buildings, both score out of a points system with four levels, and both require renewal every three years. GreenRE's levels run from Bronze to Platinum, GBI's from Certified to Platinum, and their published fees for the same floor area are similar.
Is green certification mandatory for factories in Malaysia?
No. It is voluntary, though some tenants make it a condition of their lease. What is mandatory depends on the building and the user: rainwater harvesting for qualifying detached buildings, safety rules for EV chargers, and EECA duties for large energy users.
Can a tenant get a rented factory certified?
The tenant can drive and fund the work, but the building owner signs as the applicant with the rating body and must consent to alterations. Agree in the tenancy who pays the fee, who keeps the installed equipment and who renews the rating every three years.