Key Takeaways
- CNC machining, welding, laser cutting and structural steel are medium industry; stamping and foundries are heavy. In the Department of Environment's (DOE) Guidelines for the Siting and Zoning of Industry and Residential Areas (October 2012), machining and metal treatment and structural metal products are Category 3 with a 250 m overall buffer from homes, forging, pressing, stamping and roll forming are Category 2 at 350 m, and casting of iron, steel and non-ferrous metals is Category 2 at 500 m.
- A light industrial title is the wrong starting point for most metal work. Selangor splits industrial land into light, medium and heavy in the express condition of the title, and land used against its condition is liable to forfeiture under section 127 of the National Land Code.
- Power, floor and crane decide whether the building can do the job. A load above 350 kVA needs a direct cable from a new substation under TNB's handbook, Selangor's building by-laws add at least 20% to imposed loads for machinery impact and vibration, and every powered crane needs DOSH design verification and a certificate of fitness valid for 15 months.
- Noise, fumes and waste have their own limits. DOE's noise guideline allows 70 dBA by day and 65 dBA at night in industrial zones of new developments, and spent cutting emulsion, lubricating oil and hydraulic oil are scheduled wastes you may keep on site for up to 180 days and 20 tonnes.
- Where and for how much: in FactoryHub's experience, Pulau Indah, Kapar, Banting (Olak Lempit) and Jenjarom take medium and heavy work. With RM5 million, the JPPH-registered median semi-detached factory in Klang and Port Klang sold for RM5 million on a median 15,861 sq ft of land.
Metal fabrication, CNC machining, stamping and steel work put more demands on a factory than almost any other use: heavier machines, bigger power loads, cranes, noise, fumes and oily waste. A unit that suits a warehouse or an electronics assembler can fail on every one of these. This guide is for owners, tenants and buyers choosing a factory for metalwork in the Klang Valley, and it answers the questions that decide a deal: which zoning class you need, how much power, what floor loading, whether you need a crane, which DOE and DOSH rules apply, which areas take this work and what a RM5 million budget buys.
It explains rules in general terms and is not legal, engineering or environmental advice: confirm your case with the council, DOE, DOSH, TNB and your own engineers. Separate FactoryHub guides go deeper into overhead cranes, TNB power upgrades, DOE approvals and scheduled waste.
What zoning class does a metal fabrication, CNC or stamping factory need?
Short answer: medium industry for most fabrication, machining and finishing, and heavy industry for stamping, forging, roll forming and casting. DOE grades the activity, not the product, and its siting guideline gives each activity a category and a buffer distance from houses, schools and hospitals.
These rows come from Appendix B of DOE's 2012 guideline. The overall buffer is the distance DOE expects between the activity and sensitive receptors; the primary buffer is the part that must lie outside your own boundary.
| Activity (MSIC code) | DOE category | Overall buffer | Primary buffer |
|---|---|---|---|
| Machining and metal treatment: boring, turning, milling, grinding, welding, laser cutting, sandblasting, plating, anodising, heat treatment (252592592) | 3, medium | 250 m | 200 m |
| Structural steel, metal doors, windows, gates, industrial frameworks (252512511) | 3, medium | 250 m | 200 m |
| Tanks, reservoirs and metal containers (252512512) | 3, medium | 250 m | 200 m |
| Hand tools, press tools, moulds and general hardware (252592593) | 3, medium | 200 m | 150 m |
| Bolts, nuts, springs, wire products and other fabricated metal (252592599) | 3, medium | 200 m | 150 m |
| Motor vehicle parts: brakes, gearboxes, axles, exhausts, body parts (29293) | 3, medium | 250 m | 200 m |
| Machine tools, presses and metal forming machinery (282822822) | 3, medium | 300 m | 250 m |
| Mining, quarrying and construction machinery (282822824) | 3, medium | 300 m | 250 m |
| Forging, pressing, stamping and roll forming of metal, powder metallurgy (252592591) | 2, heavy | 350 m | 300 m |
| Rolling and finishing mills, cold drawn bars, welded tubes (24241) | 2, heavy | 350 m | 300 m |
| Casting of iron and steel, and of non-ferrous metals including die casting (242432431, 242432432) | 2, heavy | 500 m | 350 m |
| Recovery of metal and other scrap (38383) | 2, heavy | 350 m | 300 m |
Why stamping lands in heavy industry
DOE describes Category 2 industries as those that "generate excessive noise and/or vibration exceeding safe limits", while Category 3 has "moderate noise and/or vibration with no significant residual impact" and Category 4 (light) has none or very low potential for noise and vibration. Press shops, forges and foundries sit on the wrong side of that line.
How the buffer works
The guideline treats the overall buffer as the sum of a primary buffer outside your lot (roads, drains, car parks, commercial uses, warehouses without hazardous goods) and a secondary buffer inside it (offices, car parks, setbacks). The primary buffer must always be met. Classify every process you will run, not only your main product: if one line is stamping, the site has to suit a Category 2 activity.
The planning buffer in Selangor
Councils carry the same idea into their local plans. Subang Jaya's local plan 2035, for example, sets a 300 m buffer with a 20 m planting strip for heavy or high risk industry, 150 m and 10 m for medium, and 50 m and 10 m for light, subject to DOE's requirements from time to time. Our guide to light, medium and heavy industry explains how the title, the local plan and the DOE grade interact.
Can a light industrial lot be used for metal fabrication or CNC work?
Short answer: not for stamping, forging or casting. For a CNC or welding shop it is still a mismatch, because DOE grades machining and welding as Category 3, so you would be running a medium activity on land conditioned for light industry.
The rule
Selangor's land office circular PTG 4/98 standardised express conditions on titles and split the industry category into Industri Ringan (light), Industri Sederhana (medium) and Industri Berat (heavy). Under section 127 of the National Land Code, any breach of a condition makes the land liable to forfeiture to the state. Section 124 lets the proprietor apply to the State Authority to alter the category of land use or its conditions, so a change is possible but it is the owner's application, on the state's timetable and terms.
What decides it for a particular unit
- The exact wording of the express condition on an official title search, not the listing or the estate name.
- The zoning of the lot in the council's local plan.
- The distance from your process area to the nearest house, school, hospital or place of worship, measured against the DOE buffer for your heaviest activity.
- Whether the owner will apply to vary the condition, and who carries the time and the premium. These vary by lot; ask the land office before you rely on it.
What to look at on site
Look behind the row as well as in front of it. Terrace and semi-detached factories share walls, so vibration from a press travels to the neighbour, and many light industrial rows back onto housing.
How much power does a metal fabrication or CNC factory need?
Short answer: it depends on your machine list, so add it up before you view. FactoryHub starts shortlisting metal fabrication factories at 500 A three-phase, which is about 346 kVA at 400 V (1.732 x 400 V x 500 A), and that sits just under the point where TNB requires a new substation.
TNB's Electricity Supply Application Handbook sets the minimum supply scheme by maximum demand:
| Maximum demand | Supply voltage | TNB minimum supply scheme |
|---|---|---|
| Above 100 kVA to 350 kVA | 400 V | Underground cable from a feeder pillar or a new or existing substation, subject to TNB's system study |
| Above 350 kVA to 1,000 kVA | 400 V | Direct underground cable from a new substation |
| 1,000 kVA up to under 5,000 kVA | 11 kV | Fed through a TNB 11 kV switching station; extra land may be needed |
Power quality matters for welding and presses
The same handbook requires the consumer to keep its equipment electromagnetically compatible with TNB's network and lists limits at the point of common coupling, including a 1% voltage step for frequent switching, a short term flicker severity (Pst) of 1.0 and total harmonic voltage distortion of 5% at 400 V. Banks of welding sets, large motors starting under load and induction heating are the kind of loads an electrical engineer should check against these limits before you sign.
What to check
- The rating of the main switchboard and the TNB meter, not the figure in the advertisement.
- Whether a substation sits on or next to the lot, and whether there is room for one if your load grows.
- Your load in amps: convert the machine list with the factory power calculator.
What floor loading does stamping or heavy machinery need?
Short answer: there is no single figure; your heaviest machine, its footprint and its impact decide it. FactoryHub's starting point for metal fabrication shortlists is 5 t/m² (1 t/m² is about 9.8 kN/m²), and presses or large machining centres often need their own foundation on top of that.
The rule
By-law 68 of the Selangor Uniform Building By-Laws requires the design to allow for dynamic effects from machinery, runways and cranes, to provide for concentrated loads including impact and vibration from installed machinery with an increase of not less than 20% or the MS EN 1991-1-1 minimum, whichever is higher, and to carry equipment loads while machines are installed or moved. By-law 69 requires crane gantry girders to be designed for vibration, shock from slipping slings, acceleration and braking, and wheel impact.
An illustration
A 20 tonne press on a 2 m by 3 m base averages about 3.3 t/m² before impact; with the 20% minimum it is about 4 t/m², and that is before the point loads under its feet. An existing building was designed for the use declared when it was approved, so nobody checks this for you when you move in.
What to check
- The imposed load marked on the approved structural plans.
- Slab condition: cracks, settlement and old machine pits.
- Whether the press or heavy CNC needs an isolated foundation, and whether the landlord allows the slab to be cut.
Work out your machine loads with the floor loading calculator, then have a Professional Engineer confirm them.
Does a metal fabrication factory need an overhead crane, and what does DOSH require?
Short answer: for steel structures, plate, coils and heavy dies, usually yes. What matters is the safe working load, the hook height, the span and whether the columns and runway beams were designed for crane loads.
The rule
The Occupational Safety and Health (Plant Requiring Certificate of Fitness) Regulations 2024, in force since 1 June 2024, list three kinds of plant that need a certificate of fitness: steam boilers, pressure vessels and lifting machinery. Whoever installs one must first obtain design verification from DOSH. The certificate is valid for fifteen months from the date of inspection. Installing an overhead travelling crane with a standard I or H beam girder and a safe working load above 4,000 kg must be done by a competent person. An owner who sells, leases, transfers or disposes of such plant must notify a DOSH officer or licensed person within thirty days.
What to check
- A copy of the crane's current certificate of fitness and its design verification.
- The safe working load plate and the clear height under the hook at full lift.
- Whether the crane stays with the building or leaves with the outgoing tenant, written into the offer.
What noise, air and waste rules apply to a metal works factory?
Short answer: noise is judged at your boundary and at the nearest homes, worker exposure has its own limit, any new stack or extract needs prior notice to DOE, and oily and metal wastes are scheduled wastes with storage limits.
Noise at the boundary
DOE's Guidelines for Environmental Noise Limits and Control (third edition) set these LAeq levels by receiving land use. Day is 7 am to 10 pm and night is 10 pm to 7 am.
| Receiving land use | New development, day / night | Existing built up areas, day / night |
|---|---|---|
| Low density residential, schools, hospitals, worship | 55 / 50 dBA | 60 / 55 dBA |
| Suburban residential (medium density) | 60 / 55 dBA | 65 / 60 dBA (suburban and urban residential) |
| Urban residential (high density), mixed development | 65 / 60 dBA | 65 / 60 dBA |
| Commercial business zones | 65 / 60 dBA | 70 / 65 dBA |
| Industrial zones | 70 / 65 dBA | 75 / 75 dBA |
Measurements are taken at the property boundary of the industrial premises and at the nearest receptors of concern, and the guideline names drop hammers among sources of impulsive sound. If you plan night shifts, see our separate guide to 24 hour factory operation.
Noise inside the factory
DOSH explains that the Occupational Safety and Health (Noise Exposure) Regulations 2019, in force since 1 June 2019, treat as excessive a daily noise exposure above 82 dB(A), a daily dose above 50%, a maximum level above 115 dB(A) at any time or a peak above 140 dB(C). Press shops and grinding bays usually need a noise risk assessment from day one.
Fumes, dust and furnaces
Under regulation 5 of the Environmental Quality (Clean Air) Regulations 2014, you must give DOE written notification at least thirty days before work that may create a new source of emission, before changing plant in a way that materially changes emissions, or before modifying an air pollution control system. Think of a dust collector on a shot blast room, a paint booth or a furnace stack. Ferrous foundries melting 1 tonne or more a day, and non-ferrous plants with a capacity of 0.5 tonne or more a day of lead or cadmium, or 2 tonnes or more a day of other metals, fall in the First Schedule: they must apply the best available techniques and file an emission declaration every year.
A full environmental impact assessment is for much larger plants. The EIA Order 2015 puts iron and steel making from scrap at 200 tonnes or more a day, from iron ore at 100 tonnes or more a day, and primary smelting of aluminium or copper of any size in its Second Schedule, which requires public display and comment.
Scheduled wastes
The Environmental Quality (Scheduled Wastes) Regulations 2005 list the codes a metal shop usually generates:
| Code | Waste |
|---|---|
| SW 305 | Spent lubricating oil |
| SW 306 | Spent hydraulic oil |
| SW 307 | Spent mineral oil and water emulsion, such as soluble cutting fluid |
| SW 104 | Dust, slag, dross or ash containing aluminium, copper, chromium, nickel and other listed metals, excluding slag from an iron and steel factory |
| SW 105 and SW 204 | Galvanic sludges and sludges containing metals, typical of plating lines |
| SW 409 and SW 410 | Contaminated containers, and rags, filters or plastics contaminated with scheduled wastes |
You must notify DOE within 30 days of generating a new category of scheduled waste, keep an inventory, and store it for no more than 180 days and no more than 20 tonnes unless DOE approves more. Plating, pickling and washing lines also need effluent treatment: Selangor brought a Zero Discharge Policy to the Teluk Gong industrial area in April 2025.
Which Klang Valley areas take metal fabrication and heavy machinery work?
Short answer: in the experience of FactoryHub's Peter Tan and Jason Low, Pulau Indah and Westport, Kapar, Banting (Olak Lempit) and Jenjarom take medium and heavy industry; Northport is mainly medium; listings that name a class put Telok Gong, Bukit Raja and Telok Panglima Garang mainly in the medium class; Meru is light and medium; and most of Shah Alam is light. That is a starting point for the search, never a substitute for the title and the council.
The JPPH-registered figures below come from FactoryHub's industrial transactions pages (24 months to August 2026, sale psf is per sq ft of land):
| Area | Class FactoryHub mostly sees | JPPH-registered reference |
|---|---|---|
| Pulau Indah, Westport and PIIP | Medium and heavy | Detached factory median RM17.49 million; industrial land RM79 psf of land |
| Kapar | Medium and heavy | Semi-detached median RM6.3 million; detached RM14.9 million; industrial land RM100 psf of land |
| Telok Panglima Garang and Jenjarom | Medium, with heavy in Jenjarom | Semi-detached median RM6.67 million; industrial land RM75 psf of land |
| Telok Gong | Mainly medium; Zero Discharge Policy since 2025 | Detached median RM19 million; industrial land RM65 psf of land |
| Shah Alam | Mostly light | Semi-detached median RM5.92 million |
Telok Gong has older medium and heavy plants, and our partner site's Telok Gong notes cover its planning history; anyone planning a heavy process there should confirm with the Klang council (MBDK) first.
What can RM5 million buy for a metal works factory in Selangor?
Short answer: usually a semi-detached or cluster factory, not a detached one. In JPPH-registered transactions over the 24 months to August 2026:
- Klang and Port Klang: semi-detached factories sold at a median RM5 million (typical range RM3.5 million to RM7.58 million) on a median 15,861 sq ft of land; detached factories at a median RM14.9 million.
- Kapar: semi-detached median RM6.3 million (RM4 million to RM8.4 million) on a median 21,864 sq ft of land.
- Telok Panglima Garang and Jenjarom: cluster factories at a median RM4.51 million (RM4.21 million to RM5.85 million) on a median 13,153 sq ft of land, and industrial land at a median RM6 million (RM3.3 million to RM7.28 million).
- Shah Alam: semi-detached median RM5.92 million on a median 10,779 sq ft of land, though most of it is light industry.
If the process needs a detached building, renting is the other route: registered detached factory tenancies in Klang and Port Klang had a median rent of RM19,700 a month for about 15,090 sq ft. Leave room in the budget for what the price does not include: a power upgrade, crane, machine foundations, fume and dust extraction and effluent treatment. These costs vary with the unit, so ask for quotes before you commit. Our guide to what factory you can buy with your budget in Selangor covers cash, loans and instalments.
What should you check on site before you sign?
- The express condition on an official title search: light, medium or heavy industry.
- The lot's zoning in the local plan and the distance to the nearest house, school or hospital.
- The DOE category of every process you will run, using the table above.
- The main switchboard rating, the TNB supply and room for a substation.
- The imposed load on the approved structural plans and the slab's condition.
- Crane capacity, hook height, certificate of fitness and design verification.
- Door width and height, yard space and turning room for long steel and trailers.
- Space for scheduled waste storage, a dust collector and, if you plate or wash, effluent treatment.
- Who the neighbours are and how close the nearest homes sit to your noisiest bay.
- A certificate of completion and compliance (CCC) or certificate of fitness for occupation, and a fire certificate where required.
FactoryHub's metal fabrication factory requirements page lists live factories that state at least 500 A and 5 t/m².
Approvals, title and rules: more questions
Do I need a manufacturing licence from MIDA?
Under the Industrial Co-ordination Act 1975, MIDA says manufacturing companies with shareholders' funds of RM2.5 million and above, or 75 or more full-time paid employees, must apply for a manufacturing licence. The licence is for the company, separate from the council's premises licence and from DOE and DOSH requirements.
Practical steps: more questions
What does an automotive parts factory need?
Parts and accessories for motor vehicles are Category 3 with a 250 m overall buffer, but a parts plant that stamps its own panels or brackets also runs a Category 2 activity at 350 m. Plan the site for the stamping line, with the power, floor loading and noise distance it needs, rather than for the assembly area.
Is steel processing medium or heavy industry?
It depends on the process. Cutting, sawing, laser cutting, grinding and welding of metal pieces are Category 3. Rolling and finishing mills, cold drawing of bars and wire, welded tube making and roll forming are Category 2 with a 350 m overall buffer.
Frequently Asked Questions
I have RM5 million to buy a metalworking factory in Selangor. Which industrial area suits me?
Start where medium and heavy industry is allowed: in FactoryHub's experience, Pulau Indah and Westport, Kapar, Banting (Olak Lempit) and Jenjarom, while most of Shah Alam is light industry. RM5 million usually buys a semi-detached or cluster factory, not a detached one. In JPPH-registered deals over the 24 months to August 2026, semi-detached factories in Klang and Port Klang had a median of RM5 million and cluster factories in Telok Panglima Garang and Jenjarom RM4.51 million. Keep money for power, crane and foundations, and confirm the zoning with the title and the council.
Where can I find a factory suitable for CNC machining?
Look for medium industrial land, because DOE grades machining and welding as Category 3 with a 250 m buffer from homes. In the experience of FactoryHub's Peter Tan and Jason Low, Northport, Telok Gong, Bukit Raja and Telok Panglima Garang are mainly medium, Meru is light and medium, and Pulau Indah, Westport, Kapar and Jenjarom also take heavier work, while most of Shah Alam is light. The title decides, so check its express condition, the distance to the nearest houses, the power supply and the floor loading for your heaviest machine.
Where can I rent a factory suitable for heavy machinery?
Start in areas that take medium and heavy industry. In the experience of FactoryHub's Peter Tan and Jason Low, these are Pulau Indah and Westport, Kapar, Banting (Olak Lempit) and Jenjarom, while Northport, Telok Gong and Bukit Raja are mainly medium and most of Shah Alam is light. Then check the unit: the floor load on the approved structural plans (FactoryHub starts heavy shortlists at 5 t/m²), whether presses need their own foundation, crane capacity and power. Confirm the zoning with the title and the council.
Can I run a CNC machining workshop in a terrace factory?
DOE grades machining, welding and laser cutting as Category 3, medium industry, with a 250 m overall buffer. Many terrace factory rows carry light industry titles and sit close to housing, so check the express condition and the distance to the nearest homes first. Power is the other limit: a terrace unit rarely has room for a substation if your machines push the load past 350 kVA.
Can I set up a foundry in Selangor?
Yes, but only on land and in an area that suit heavy industry. DOE puts casting of iron, steel and non-ferrous metals in Category 2 with a 500 m overall buffer, and a ferrous foundry melting 1 tonne or more a day must apply the best available techniques and file a yearly emission declaration under the Clean Air Regulations 2014. Making iron and steel from scrap at 200 tonnes a day or more also needs a full EIA with public comment.
What floor loading do I need for a stamping press?
Start from the press's operating weight, its base area and its impact. Selangor's building by-laws require at least a 20% increase in imposed loads for machinery impact and vibration, and heavy presses often need their own isolated foundation. FactoryHub shortlists metal fabrication factories from 5 t/m², but only a Professional Engineer can confirm a particular slab.
Do I need DOE approval to open a metal fabrication factory?
Most fabrication shops are not EIA activities, but DOE rules still apply. You must notify DOE in writing at least 30 days before installing a new emission source such as a dust collector, paint booth or furnace, notify it within 30 days of generating a new category of scheduled waste, and keep the site within DOE's siting buffers and noise limits.
What specs should a heavy machinery maker look for in a factory?
DOE grades metal forming machinery, machine tools and construction or mining machinery as Category 3 with a 300 m overall buffer. Look for a medium or heavy industry title, an overhead crane sized for your heaviest assembly, high clear height under the hook, a floor rated for your machines plus at least 20% for impact, wide doors and a yard for trailers, and power above 350 kVA if you test machines on site.