Key Takeaways
- Size a plastics factory from the machine list, not from tonnage alone. In one maker's current servo hydraulic range, nameplate power (motor plus barrel heaters) is 25.6 kW for a 900 kN machine, 44.1 kW at 2,600 kN and 127.4 kW at 8,000 kN. Ten 2,600 kN machines already pass 350 kVA before any chiller or compressor, the level at which TNB's handbook calls for a cable straight from a new substation.
- In DOE's siting guideline, plastic products made by injection, extrusion or blow moulding are medium industry (category 3) with a 200 m overall buffer from homes. Plastic film, sheet and packing articles need 150 m, other rubber products 250 m, and custom mixing and blending of resins is heavy industry at 500 m.
- Overhead cranes, steam boilers and compressed air receivers that are not excluded need a certificate of fitness under the Occupational Safety and Health (Plant Requiring Certificate of Fitness) Regulations 2024, in force since 1 June 2024. Each certificate is valid for 15 months from the inspection.
- Spent hydraulic oil (SW 306), spent lubricating oil (SW 305), contaminated containers (SW 409), contaminated rags and filters (SW 410) and ink waste (SW 417) are scheduled wastes: notify DOE within 30 days of first generating them, and store no more than 20 tonnes for no longer than 180 days.
- Resin, regrind and packed goods are combustible. In Selangor a single storey factory above 2,000 m² needs hose reels and sprinklers, and so does a store of combustible products above 1,000 m² or 7,000 m³. Ask for the sprinkler design basis before you sign.
This guide is for owners and managers choosing a factory for injection moulding, blow moulding, film and bag making or rubber moulding in Selangor, Kuala Lumpur or Negeri Sembilan. It explains the rules and is not legal advice: your consultant engineer, the council, DOE, DOSH and Bomba decide what a particular building needs.
How many amps does a plastic injection moulding factory need?
Add up the nameplate power of every moulding machine and every auxiliary, decide how much of it runs at the same time, convert that to kVA and amps, and compare the result with the TNB supply the building already has. There is no fixed "amps per tonne". Power depends on the drive (servo hydraulic or all electric), the barrel size and the heater bands of each model.
What one maker's datasheet shows
Yizumi's current SKIII servo hydraulic specification sheet lists the maximum motor power, heater power, oil tank, weight and size of each model. Five of its models show how the numbers climb with clamping force:
| Model (clamping force) | Max motor power | Heaters (larger barrel) | Nameplate total | About amps at 400 V | Oil tank |
|---|---|---|---|---|---|
| UN90SKIII (900 kN) | 17.8 kW | 7.8 kW | 25.6 kW | 43 A | 120 L |
| UN160SKIII (1,600 kN) | 25.2 kW | 12.1 kW | 37.3 kW | 63 A | 167 L |
| UN260SKIII (2,600 kN) | 28.7 kW | 15.36 kW | 44.1 kW | 75 A | 230 L |
| UN450SKIII (4,500 kN) | 58.6 kW | 39.22 kW | 97.8 kW | 166 A | 510 L |
| UN800SKIII (8,000 kN) | 76.4 kW | 51 kW | 127.4 kW | 216 A | 720 L |
The amps use TNB's own figures. Its Electricity Supply Application Handbook (ESAH 3.1) supplies three phase at 400 V and requires consumers below 132 kV to keep their power factor at 0.85 or higher, so amps = kW x 1,000 / (1.732 x 400 x 0.85). These are nameplate maximums, not what the meter will record: a servo machine reaches its peak only in parts of the cycle and heaters work hardest at warm up. Your own machines may differ, so use their nameplates.
Two things stand out. Power does not rise in step with tonnage: the 2,600 kN model needs only about 18% more than the 1,600 kN model at nameplate, while the 4,500 kN model needs more than double the 2,600 kN one. And the heater share grows with the barrel, so a larger injection unit on the same clamp changes the total.
The rest of the plant
The moulding machines are only part of the load. Add these from their own nameplates:
- chillers, cooling tower pumps and fans
- resin dryers, hopper loaders and central conveying blowers
- mould temperature controllers
- granulators beside the machines
- air compressors
- robots, conveyors, printing or assembly lines, lighting, the office and air conditioning
A worked example of the method
Ten machines like the 2,600 kN model come to 10 x 44.06 kW = 440.6 kW at nameplate.
- At a power factor of 0.85: 440.6 / 0.85 = about 518 kVA, or about 748 A at 400 V.
- If your engineer assumes only 80% runs together: 352.5 kW, about 415 kVA and about 599 A.
- Both are above 350 kVA. In ESAH Table 3-1, a maximum demand above 350 kVA up to 1,000 kVA needs a direct underground cable from a new substation, and from 1,000 kVA the supply moves to 11 kV through a TNB switching station.
That is before a single chiller or compressor. The figures show the method only; your plant needs its own load list.
What to check on site
- The TNB bill and supply contract, which show the declared maximum demand, and the rating of the main switchboard and incoming breaker. Our guide on how much kVA a factory needs explains how to read each one.
- Whether the substation feeding the unit is shared or dedicated to the lot.
- Room for capacitor banks if your power factor would fall below 0.85.
- Spare ways in the distribution boards near the machine rows, and cable routes from the main switch room.
Run your own machine list through the factory power calculator.
How much cooling water does a moulding plant need?
There is no standard figure. Mould cooling and hydraulic oil cooling are set by each machine and mould, and your process engineer sizes the chiller or cooling tower from them. What the building must give you is space, water supply, drainage and power for that plant.
What decides it
- The number and size of the machines, and the resins you run, since cycle times and mould temperatures differ by material.
- The cooling arrangement: an open cooling tower, a closed circuit cooler or a chiller, often a mix of chilled water for the moulds and tower water for the hydraulic oil coolers.
- Whether the mould temperature controllers run on water or oil.
What the water costs
A cooling tower loses water to evaporation and bleed off, and you pay for the make up water. In Selangor, Kuala Lumpur and Putrajaya, Air Selangor's tariff review charges commercial and other non domestic premises RM3.51 per m³ for the first 35 m³ a month and RM3.83 per m³ above that, from 1 September 2025 as the New Straits Times reported. Ask the landlord for recent water bills and the meter size.
What to check on site
- A level yard or roof area with drainage for the cooling tower and chillers, clear of fire engine access and hydrants. Section 26 of the Fire Services Act 1988 makes it an offence to cover up, enclose or conceal a fire hydrant.
- Pipe routes from the plant to each machine row: trenches in the slab or overhead racks.
- Where bleed off and any wash water will go. If DOE treats it as industrial effluent, it needs treatment to the discharge standard, so ask before you design.
- Compressed air. An air receiver is a pressure vessel. Unless it falls within an exclusion in the Second Schedule of the 2024 certificate of fitness regulations, such as a design pressure not above 15 psig, it needs DOSH design verification and a certificate of fitness.
How strong must the floor be for injection moulding machines?
Start from each machine's weight and footprint, add the mould, and check the result against the slab's design load. The heaviest machines may need their own foundation. The same datasheet gives:
| Model | Machine weight | Footprint (L x W) | Average over the footprint |
|---|---|---|---|
| UN90SKIII (900 kN) | 2,800 kg | 4.49 x 1.13 m (5.1 m²) | about 0.55 t/m² (5.4 kN/m²) |
| UN260SKIII (2,600 kN) | 6,700 kg | 5.87 x 1.53 m (9.0 m²) | about 0.75 t/m² (7.3 kN/m²) |
| UN450SKIII (4,500 kN) | 15,000 kg | 8.32 x 1.99 m (16.6 m²) | about 0.91 t/m² (8.9 kN/m²) |
| UN800SKIII (8,000 kN) | 32,000 kg | 10.14 x 2.34 m (23.7 m²) | about 1.35 t/m² (13.2 kN/m²) |
The average hides the real question. The weight comes down through the machine's feet as point loads, the mould adds its own weight between the platens, and clamping and injection add vibration. Silos, mould racks and stacks of resin bags are loads too. Check:
- the slab's design load on the approved structural drawings or an engineer's letter, for the ground floor and any upper floor
- cracks, settlement and soft ground, which matter more on reclaimed and coastal land
- whether the heaviest presses need a separate foundation, which is structural work with its own approval
Try your machine weights in the floor loading calculator.
How high should the factory be for dryers, silos and an overhead crane?
Measure the crane's hook height and the clear height under the lowest beam, truss or light fitting, not the roof apex. The machine heights in the datasheet are before the hopper, dryer and loader that sit on top: 1.94 m for the 900 kN model and 2.62 m for the 8,000 kN model.
Crane height and capacity
To lift a mould in from above, the hook must clear the machine, plus the tallest mould, plus the slings and lifting eye. Write those numbers down for your heaviest and tallest mould and compare them with:
- the crane's safe working load, which must exceed the heaviest mould with its lifting gear
- the hook height at its highest point
- the crane's coverage over every machine row and the mould store
The certificate of fitness
Under the Occupational Safety and Health (Plant Requiring Certificate of Fitness) Regulations 2024, in force since 1 June 2024, steam boilers, pressure vessels and lifting machinery need a certificate of fitness. Before installation the design must be verified by DOSH, and the foundation must be designed and built to withstand the load imposed on it (regulation 4). The certificate is valid for 15 months from the date of inspection, a periodical inspection must be done before it expires, and an owner who sells, leases or transfers the plant must notify the officer or licensed person within 30 days (regulation 5). When you buy or rent a factory with a crane, ask for the current certificate and agree who notifies the transfer. Jason Low's guide to factories with overhead cranes covers the DOSH steps in more detail.
Silos and blown film towers
Outdoor resin silos stand on their own foundations, need tanker access for bulk deliveries, and must stay clear of fire engine access and hydrants. Ask the council whether a silo and its foundation need plan approval before you order one. Blown film lines for packaging need height for the film bubble and the rollers above it: get the line's overall height from its maker and compare it with the clear height under the lowest truss.
Can a medium industry lot be used for plastics?
Yes, it is the usual fit. In DOE's Guidelines for the Siting and Zoning of Industry and Residential Areas (2012), processing new or recycled resin into products by compression, extrusion, injection or blow moulding and casting is category 3, medium industry. A lot whose title says Industri Sederhana and whose local plan zones it for medium industry matches that class. A light industry lot is a risk to raise with the council in writing before you sign.
| Activity (MSIC 2008 code in the guideline) | DOE category | Overall buffer | Primary buffer |
|---|---|---|---|
| Plastic products by compression, extrusion, injection or blow moulding and casting (22222) | 3, medium | 200 m | 150 m |
| Plastic plates, sheets, film, foil, pipes, packing articles and tableware (22222) | 3, medium | 150 m | 100 m |
| Other rubber products, vulcanised or not (222212219) | 3, medium | 250 m | 200 m |
| Rubber tyres and inner tubes (222212211) | 3, medium | 350 m | 300 m |
| Corrugated paper, paperboard containers and paper sacks (171701702) | 3, medium | 250 m | 200 m |
| Printing, including printing directly onto plastic (181811811) | 4, light | 150 m | 100 m |
| Resins and plastics in primary forms, including custom mixing and blending of resins (202012013) | 2, heavy | 500 m | 350 m |
- The overall buffer is the distance DOE expects between the factory and homes or other sensitive receptors. The primary part lies outside your boundary and must always be met; the rest can be inside your lot as setbacks, car parks or offices.
- The plastics and rubber rows add a 20 m buffer around auxiliary equipment such as boilers, blowers, generator sets, pumps and fuel storage of 1,000 litres.
- Compounding your own masterbatch or blending resins for others on a custom basis can move you into the heavy row. Describe the whole process when you apply.
The land title, the council's local plan and the DOE grade must all agree. Our guide to light, medium and heavy industry explains how to check each one and Selangor's own buffer standards.
What DOE approvals does a plastics, packaging or rubber factory need?
Moulding plastic parts is not among the industry activities listed in the EIA Order 2015, which names chemicals, petrochemicals, cement, lime, shipyards, smelting, iron and steel, and pulp and paper. What usually applies to a moulding plant is prior written notification under the clean air rules, the scheduled waste rules and, where there is process wastewater, the effluent rules.
Clean Air Regulations 2014
Regulation 5 of the Environmental Quality (Clean Air) Regulations 2014 requires the owner or occupier to give DOE written notification not less than 30 days before work that may result in a source of emission, before building premises for a purpose that may result in a new source of emission, and before changing plant in a way that materially changes emissions. In a plastics or rubber plant this usually means:
- boilers and thermal oil heaters, common in rubber moulding
- standby generators: DOE's guidance document for fuel burning equipment says a generator using more than 15 kg of liquid fuel per hour needs written notification before installation starts
- fume extraction from purging, printing or coating
Printing, coating and other surface treatment with organic solvents, at a solvent consumption capacity above 200 tonnes a year, is in the regulations' First Schedule, which must apply the best available techniques.
Scheduled wastes
Under the Environmental Quality (Scheduled Wastes) Regulations 2005, a waste generator must notify DOE of new categories and quantities within 30 days of generating them (regulation 3), and may store its own scheduled wastes for 180 days or less as long as no more than 20 tonnes accumulate on site (regulation 9). Containers must be compatible, durable and closed, and incompatible wastes go in separate containment. Typical codes in a moulding and packaging plant:
| Waste | Code |
|---|---|
| Spent lubricating oil | SW 305 |
| Spent hydraulic oil | SW 306 |
| Waste of non-halogenated organic solvents | SW 322 |
| Containers, bags or equipment contaminated with chemicals or mineral oil | SW 409 |
| Rags, plastics, papers or filters contaminated with scheduled wastes | SW 410 |
| Waste of inks, paints, pigments, lacquer, dye or varnish | SW 417 |
The oil volumes are real: the datasheet lists a 230 litre tank on the 2,600 kN model and 720 litres on the 8,000 kN model. Plan a roofed, bunded scheduled waste store with its own access from the start.
What fire protection does resin and finished goods storage need?
Resin, regrind, film and boxed products are combustible goods, so the fire systems depend on the floor area, the volume and how high you stack. Selangor's Tenth Schedule in Sel. P.U. 142/2012 sets the minimum fixed systems:
| Space | Fixed system |
|---|---|
| Single storey factory, 1,001 to 2,000 m² | Hose reel |
| Single storey factory, above 2,000 m² | Hose reel and sprinklers |
| Single storey store of combustible products, 501 to 1,000 m² and below 7,000 m³ | Hose reel |
| Single storey store of combustible products, above 1,000 m² or 7,000 m³ | Hose reel and sprinklers |
| Building with hazardous processes | Hose reel, sprinklers, gas or pressurised hydrant, as Bomba requires |
Note 1 of the Schedule treats rooms used to store materials in quantities deemed hazardous, indoor storage of flammable liquids, transformer and switch rooms, plant rooms and boiler rooms as hazardous areas, and the factory section adds that special risks or hazardous processes or storage must have the fire protection Bomba requires. Printing inks and solvents for packaging fall here.
What to check:
- The sprinkler design basis from the M&E engineer: the hazard and storage height it was designed for. Stacking resin bags or cartons higher than that is a common gap.
- Where the resin store, scheduled waste store and ink room will sit, and whether they need fire rated walls.
- If the building holds a fire certificate, section 32(2) of the Fire Services Act 1988 requires the occupier to notify Bomba before starting a material change to the premises.
Our Bomba requirements guide covers hose reel distances, hydrants and who pays in a rented factory.
Packaging and rubber products: what changes?
Plastic packaging: film, bags and containers
- Film, sheet and packing articles sit in the medium row with a 150 m overall buffer, smaller than moulded products at 200 m.
- Blown film towers need height, and bag making and slitting need long, clear floor runs.
- Printing on film or bags brings solvent inks: hazardous storage for Bomba, SW 322, SW 417 and SW 418 for DOE, and the 200 tonne solvent line in the clean air rules.
Paper packaging
Corrugated boxes and paper sacks are medium industry at 250 m, a larger buffer than plastic moulding.
Rubber products
- Other rubber products are medium at 250 m and tyres at 350 m.
- Curing presses are often heated by steam or thermal oil. A steam boiler needs a certificate of fitness, a boiler is fuel burning equipment that needs 30 days' written notice to DOE, and the guideline asks for a 20 m buffer around it.
- Making synthetic rubber in primary forms is heavy industry (category 2, 500 m).
Checklist before you sign
| Item | What to ask for |
|---|---|
| Power | TNB bill, declared maximum demand, main switchboard rating, substation location |
| Cooling | Yard or roof space, drainage, water bills, meter size |
| Floor | Design load on approved drawings, slab condition, foundations for big presses |
| Height and crane | Clear height under the lowest truss, crane safe working load, hook height, current certificate of fitness |
| Zoning | Express condition on the title, local plan zoning, distance to the nearest house, school or hospital |
| DOE | Process description, boiler or generator plans, scheduled waste store location |
| Fire | Fire system drawings, sprinkler design basis, fire certificate status |
Other questions owners ask at this stage, such as TNB upgrade costs, clear height against ceiling height, mezzanine approval and scheduled waste management, have their own FactoryHub guides.
Frequently Asked Questions
What are the requirements for a plastic injection moulding factory in Malaysia?
You need enough TNB supply for every machine and auxiliary, space and drainage for chillers and cooling towers, a slab strong enough for the presses, crane hook height for mould changes, and a lot zoned for medium industry. DOE classes plastic moulding as category 3 with a 200 m overall buffer from homes. Add DOSH certificates for cranes and pressure vessels, DOE scheduled waste registration and fire protection suited to stored resin.
How many amps does a plastic factory need?
Add the nameplate kW of each machine and auxiliary, apply how much runs together, and convert with amps = kW x 1,000 / (1.732 x 400 x 0.85). On one maker's datasheet a 900 kN machine is about 43 A at nameplate and an 8,000 kN machine about 216 A. Ten 2,600 kN machines come to about 748 A before chillers and compressors, which is above the 350 kVA level where TNB calls for a cable from a new substation.
Can a medium industry lot be used for a plastics factory?
Usually yes. DOE's siting guideline puts plastic products made by injection, extrusion or blow moulding in category 3, medium industry, with a 200 m overall and 150 m primary buffer. Confirm the express condition on the title and the local plan zoning, and measure the distance to the nearest house, school or hospital.
Can I run plastic injection moulding in a light industry factory?
It is a risk. DOE grades the activity itself as medium, so a light industry title or zone may not match, and a lot close to housing may not meet the buffer. Ask the council's planning department in writing before you sign, and describe the full process, including any printing, compounding or boilers.
Do I need DOE approval to start a plastic injection moulding factory?
An ordinary moulding plant is not on the industry list of the EIA Order 2015, so no EIA is needed for that reason alone. You must still give DOE written notice at least 30 days before installing a new source of emission such as a boiler or a large generator, and notify scheduled wastes within 30 days of first generating them. Process wastewater brings the effluent rules in as well.
What buffer zone does a rubber products factory need?
DOE's 2012 siting guideline puts other rubber products in category 3 with a 250 m overall and 200 m primary buffer, and rubber tyres at 350 m and 300 m. It also asks for a 20 m buffer around boilers, blowers, generator sets, pumps and fuel storage. Synthetic rubber in primary forms is heavy industry at 500 m.
Does an overhead crane in a factory need a DOSH certificate?
Yes. Lifting machinery is a plant requiring a certificate of fitness under the 2024 regulations, which need DOSH design verification before installation and a certificate valid for 15 months from each inspection. When a factory with a crane is sold or leased, the owner must notify the officer or licensed person within 30 days.
What equipment does an injection moulding plant need besides the moulding machines?
Most plants also run chillers or cooling towers, resin dryers and loaders, mould temperature controllers, granulators, air compressors, and often robots and conveyors. Each adds to the power, floor, water and space you need, so list them with their nameplates before you compare factories. Compressed air receivers that are not excluded, and any steam boiler, also need DOSH certificates.