Key Takeaways
- The One Stop Centre (OSC), or Pusat Setempat, is the unit inside every local council that takes in development applications, sends them to the council's departments and to outside agencies such as TNB, Bomba, JPS and IWK, and puts them to the council's OSC Committee for a decision.
- For a factory or warehouse, the OSC handles planning permission (Kebenaran Merancang, KM), building plans, earthworks, road and drainage, landscape and temporary permits, and later receives the start-of-work notice and the CCC.
- All 12 Selangor councils and all 7 Negeri Sembilan councils are on KPKT's OSC 3.0 Plus Online system. Your consultant, not you, files the application.
- Under KPKT's Manual OSC 3.0 Plus, a medium-category KM filed together with its building and engineering plans has a limit of 57 to 99 calendar days. Selangor's SPEED Selangor lane caps qualifying factory projects at 30 days from a complete application.
- In Selangor, the planning permission fee for a factory, workshop, store or warehouse is RM100 per 100 square metres of gross floor area. Building plan fees, development charges and other contributions are charged on top.
What is the One Stop Centre (OSC) in Malaysia?
The One Stop Centre is a unit inside each local council (Pihak Berkuasa Tempatan, PBT). Instead of an owner going to the planning department, the building department, the engineering department, TNB, Bomba, JPS, the land office and the water operator one by one, the consultant files the whole package once at the OSC. The OSC circulates the plans, collects every agency's technical comments and tables the file at the OSC Committee, which approves, approves with conditions or rejects.
The Manual OSC 3.0 Plus published by the Ministry of Housing and Local Government (KPKT) gives the background:
- OSCs were set up at councils in Peninsular Malaysia from 13 April 2007, after a Cabinet decision on 21 March 2007 to speed up government services.
- OSC 3.0 came in on 1 June 2014 and organised every project into six processes, from plan approval to the building being fit to occupy.
- The OSC Committee in each council is set up under section 28 of the Local Government Act 1976 (Act 171). Planning permission comes under the Town and Country Planning Act 1976 (Act 172) and building plans under the Street, Drainage and Building Act 1974 (Act 133).
- The current rulebook is the Manual OSC 3.0 Plus (first edition 2019, second printing June 2020), which sets the checklists and the number of days for each step, and runs on the OSC 3.0 Plus Online system.
Is this the same as MIDA's OSC?
No. Search results for "one stop centre" also show other offices with the same name. MIDA ran a One Stop Centre for business travellers from 2 October 2020 and phased it out on 1 April 2022, when Malaysia reopened its borders (MIDA). If your question is about building, extending or changing the use of a factory, the OSC you need is the one at your local council.
Which council's OSC handles my factory?
The council that bills the property's assessment tax (cukai pintu) is the one whose OSC you file with. These are the councils listed on KPKT's OSC 3.0 Plus portal (Selangor, Negeri Sembilan), with industrial areas each one covers:
| Council | Industrial areas it covers (examples) |
|---|---|
| Majlis Bandaraya Diraja Klang (MBDK) | Klang, Port Klang, Pulau Indah, Kapar, Meru, Telok Gong, Pandamaran |
| Majlis Bandaraya Shah Alam (MBSA) | Shah Alam sections, HICOM Glenmarie, Bukit Jelutong, Kota Kemuning |
| Majlis Bandaraya Petaling Jaya (MBPJ) | Petaling Jaya, Kota Damansara |
| Majlis Bandaraya Subang Jaya (MBSJ) | Subang Jaya, USJ, Taman Perindustrian Puchong, Kinrara |
| Majlis Perbandaran Kajang (MPKj) | Kajang, Balakong, Bangi, Semenyih, Beranang |
| Majlis Perbandaran Kuala Langat (MPKL) | Banting, Jenjarom, Telok Panglima Garang |
| Majlis Perbandaran Selayang (MPS) | Selayang, Rawang, Kepong Industrial Park |
| Majlis Perbandaran Hulu Selangor (MPHS) | Serendah, Batang Kali, Bukit Beruntung |
| Majlis Perbandaran Kuala Selangor (MPKS) | Kuala Selangor, Ijok, Puncak Alam |
| Majlis Perbandaran Sepang (MPSep) | Sepang, Dengkil, Cyberjaya |
| Majlis Perbandaran Ampang Jaya (MPAJ) and Majlis Daerah Sabak Bernam (MDSB) | Ampang; Sabak Bernam |
| Negeri Sembilan councils | Seremban, Port Dickson, Jempol, Rembau, Tampin, Kuala Pilah, Jelebu |
Postcodes can mislead. Kepong Industrial Park has a Kuala Lumpur postcode but MPS Selayang runs it, as our partner site explains in Kepong Industrial Park: KL address, Selangor rules. Kuala Lumpur has its own entry point: DBKL runs its own OSC 3.0 Plus Online portal, separate from the Selangor councils' listing, which went live on 1 January 2025. By August 2025 DBKL said development orders were taking 14 days on average online against 42 days on paper (The Star).
Which factory applications go through the OSC?
The manual lists the applications a council OSC accepts, separately or together:
- Land matters filed with a layout KM: conversion with subdivision or amalgamation (section 124A of the National Land Code) or surrender and re-alienation (section 204D)
- Planning permission, for a layout or for the building itself
- Road and drainage plan, earthworks plan and street lighting plan
- Building plan
- Landscape plan
- Temporary permits: temporary buildings, hoarding, signboards, workers' quarters on site and batching plants
- Names for a park, road or building
- Amendments to approved plans, and extensions or renewals of approvals
After approval, the same channel receives the records: Form B (start of work), interim and final inspection notices, Forms G1 to G21 and Form F or F1 (the CCC).
The OSC does not issue everything a factory needs. The council's business premise licence, the MIDA manufacturing licence, DOE notifications for boilers and emissions and the annual Bomba fire certificate are applied for separately, although several of these agencies comment on your plans through the OSC.
Does a change of use need planning permission?
Yes, when it is a material change. The manual explains that Act 172 groups development needing KM into three kinds: operational works (building, engineering, mining and industrial work), a material change in the use of land or a building, and subdivision or amalgamation of land. Its own example is a house turned into an office without any building work, which still needs KM. For a factory owner, turning a plain warehouse into a food plant or a chemical store can count the same way, and Selangor's fee table has its own line for a material change of use of an industrial building.
When can a factory skip planning permission?
The manual sets out an Exemption from Planning Approval (ExPA) under subsection 19(2) of Act 172 for one single-storey detached light industrial building. All of these must apply:
- The industry is light industry under the DOE Guidelines for Siting and Zoning of Industries.
- The plot sits in an approved layout or master plan, the land matters are settled and the title has been issued.
- The plot is not more than 1 acre, and the new building is one storey.
- There is no cut and fill beyond site clearing, and the infrastructure is ready to connect.
- For rebuilding or altering, the added floor area is not more than 500 sq ft and the height does not increase.
The exemption covers planning permission only. Building plans, the CCC and the agencies' requirements still apply.
What about small renovations?
Minor works use a separate permit (Permit Kerja Ubah Suai Kecil). The manual's checklist asks for Form A under the Uniform Building By-Laws 1984, the processing fee, plans signed by the owner and by a registered architect, draughtsman or consulting engineer, the latest assessment tax and quit rent receipts, a copy of the title, Form 49 for a company and colour photos of the site.
Who submits the application, and what does the owner prepare?
Your consultant files it. The manual defines the Principal Submitting Person (PSP) as the qualified professional who submits building plans to the council and later issues the CCC: a professional architect, a professional engineer, or a registered building draughtsman for buildings of not more than 2 storeys and 300 square metres. Most factories are larger than that, so in practice the PSP is an architect or engineer. The consultant uploads the drawings and documents to OSC 3.0 Plus Online, and in March 2026 the portal posted a manual for registering digital certificates and signing digitally.
The owner supplies the documents behind the drawings. From the manual's planning permission checklist, these fall on you:
| Document | Why it is needed |
|---|---|
| Land title or official title search, with the bank's consent if the land is charged, or the SPA if you are still buying | Proves your right to develop the land |
| Current quit rent (cukai tanah) and assessment tax (cukai pintu) receipts | Land office and council records |
| Company papers: M&A, Form 24 and Form 49, with a letter authorising the signatory | Required when the applicant is a company |
| Power of attorney or SPA if the applicant is not the registered owner | Land office requirement |
| Consent for right of way if access crosses land you do not own | Access approval |
| Maximum demand estimate certified by a registered electrical engineer, and the current bill for an existing building | TNB's comments |
| EIA approval, stormwater (MSMA) report, geology report and sewerage report where relevant | DOE, JPS, JMG and IWK comments |
Work out your power load early with the factory power calculator. The supply level affects which category your application falls into, as the next section shows.
How long does OSC approval take for a factory?
The manual counts calendar days, so weekends and public holidays are included. Its Table 6.1 sets these limits for applications filed together:
| Applications filed together | Time limit |
|---|---|
| Small-category KM with building and engineering plans | 42 to 98 days |
| Medium-category KM with plans | 57 to 99 days |
| Large-category Type B KM with plans | 71 to 115 days |
| Large-category Type A KM with plans | Up to 300 days |
| Plans only, no KM needed | 50 to 92 days |
If the OSC Committee approves with conditions on the plans, the applicant gets two consecutive committee meetings to comply. Miss them and the committee can reject the application.
Which category is my factory in?
The manual sorts KM by intensity and risk, and the council sets the category:
- Small: up to four houses in an approved layout, one private house, or a subdivision of under 2 acres with no building work.
- Medium: development that follows the land's express condition or an approved layout, with one or more building uses at around 1:2 plot ratio intensity and public utilities.
- Large Type B: around 1:3 intensity, a private sewage treatment plant, or a 275kV or 132kV main intake.
- Large Type A: needs advice from the National Physical Planning Council under subsection 22(2A) of Act 172, such as a new town of more than 100 hectares or more than 10,000 people.
Power is a useful guide for factories. In the manual's utility table, TNB supply of up to 350kVA from the existing network sits in the small column, a main switching station at 33kV or 11kV for 350kVA up to 25MVA sits in medium, and supply above 25MVA at 275kV or 132kV sits in large.
Are there faster lanes for industrial projects?
Industrial Green Lane (IGL). KPKT's procedure dated 22 January 2024 started at ten pilot councils, including Majlis Perbandaran Klang (now MBDK) and Majlis Bandaraya Seremban. It cuts approval from 99 days to 29 for industrial projects in a planned estate with an approved layout master plan, where the Notice 5A land premium is paid, the site and outside utilities are ready, the EIA, traffic and road safety reports are approved, and the building is not meant for leasing to someone other than the owner. A technical briefing chaired by the mayor or council president comes first, agencies give early comments within 14 days, and the business licence can be applied for at 80% construction and approved within 24 hours of the CCC.
SPEED Selangor. The state's SPEED Selangor guideline, in force from 1 October 2025, covers industrial buildings, including factories, warehouses and logistics facilities, in planned industrial areas or zoned for industry in the local plan. Its main rules:
- The whole process is capped at 30 days from a complete application: up to 21 days of pre-consultation and up to 9 days for the formal approval.
- 30% of the development fee is paid upfront and is not refunded if the project does not go ahead.
- If the 30 days run out, an appeal must be decided within 14 days.
- Early site works (clearing, hoarding, light levelling) can be approved within 24 hours.
- A 6-month temporary business licence is possible at 80% construction, extendable by up to 6 more months. Machines may be installed for commissioning but not full production.
- The full licence must be issued within 24 hours of the CCC deposit.
- The title must be free of restrictions on development, which the guideline lists as charges, caveats, transfers and court orders.
In practice, MBPJ cut its window for high-impact projects from 30 days to 25, and NXP's project in the Sungai Way Free Industrial Zone was submitted on 10 August and approved on 4 September 2026 (The Star). KPKT said over 130 applications had gone through its fast-track mechanisms by July 2026 and that it is adding AI to OSC 3.0 Plus Online to flag incomplete documents (The Star).
How much are the OSC fees for a factory?
In Selangor, the planning permission fee follows the Planning Control (General) (Selangor) (Amendment) Rules 2025. Majlis Perbandaran Selayang's 2026 Form A prints the table (MPS):
| Planning permission item | Fee |
|---|---|
| Factory, workshop, store or warehouse | RM100 per 100 square metres of gross floor area |
| Vehicle storage yard | RM100 per 100 square metres |
| Industrial layout as a master or concept plan | RM500 per hectare |
| Material change of use of an industrial building | RM100 per 100 square metres |
At that rate, a factory with 5,000 square metres of gross floor area pays RM5,000 for planning permission. That is only the KM fee. The building plan processing fee under the by-laws, development charges and the ISF contribution are separate, and the manual's start-of-work checklist lists receipts for the development charge and the ISF paid in full, and for the land premium under Form 5A, among its documents. Your PSP prepares the fee calculation and the council confirms it, so ask for the full figure before you commit to a timeline.
What happens after approval, up to the CCC?
The manual splits every project into six processes:
| Process | What happens | Point to note |
|---|---|---|
| 1. Technical information | Your consultant asks agencies for early input | Optional; notes from this stage are not official comments |
| 2. Plan consideration | OSC circulates the plans, agencies comment and the OSC Committee decides | KM approval is issued as Form C1 |
| 3. Start of work | Form B for earthworks and for building works, deposited together | KPKT says the start notice must come within 12 months of the KM approval |
| 4. Site monitoring | Council and agencies inspect during construction | Non-compliance notices can be issued until the CCC |
| 5. Final inspection | Water operator, TNB, council or JKR, Bomba (G8, G9), DOSH (G11) and IWK (G14, G15) | Each agency issues its clearance letter |
| 6. CCC deposit | The PSP issues Form F with Forms G1 to G21 | Deposited with the council within 14 days of issue |
KPKT's briefing on OSC 3.0 Plus adds a warning: if building work stops for three consecutive months, the start-of-work notice and all plan approvals can be treated as cancelled under section 70(9) of Act 133. A paused project should talk to the council early. The CCC is what lets you occupy the building and apply for its licences; our CCC guide explains how buyers check one.
What changes for a factory compared with a house, and what goes wrong?
A single private house on its own lot can skip planning permission under ExPA when it meets the conditions, which allow up to 3 storeys. For a factory the exemption is much narrower: one storey, light industry, a plot of not more than 1 acre. A factory also brings in more agencies at the final inspection: Bomba for fire protection, DOSH for lifts and regulated machinery, TNB for a substation and IWK or a private plant for sewage. A larger power supply can also move the application into a slower category.
Common mistakes that delay OSC approval
- Buying land before the land matters are settled. The fast lanes need the land premium paid and the category right. Read our industrial land conversion guide and the industrial land due diligence checklist before you sign.
- Filing an incomplete set. The clock only starts when the checklist is complete, and KPKT is adding AI to OSC 3.0 Plus Online precisely to flag incomplete documents.
- Assuming a change of use is free. A new process in an old building can need a fresh KM.
- Filing with the wrong council. Confirm it from the assessment bill, not the postcode.
- Leaving the power load until late. The TNB supply level can move the application into a slower category.
- Letting approvals lapse. Start work within the validity period and do not let the site sit idle for three months.
If you would rather buy or rent a building that already has its CCC, compare the JPPH-registered prices on industrial transactions first.
This guide explains the process in general terms and is not legal advice; confirm the current checklist and fees with your council's OSC and your PSP.
Frequently Asked Questions
What is OSC in Malaysia?
OSC usually means the One Stop Centre (Pusat Setempat) at a local council, which receives and coordinates applications for planning permission, building plans and engineering plans. OSCs were introduced at councils across Peninsular Malaysia from 2007, and in Selangor and Negeri Sembilan they all use KPKT's OSC 3.0 Plus Online system. The name was also used by MIDA's OSC for business travellers, which closed on 1 April 2022.
What are one stop shop services?
One stop shop services bring several approvals under one counter with one point of contact. For a factory, the council OSC is that one stop shop for development approvals: planning permission, building plans, earthworks, road and drainage, landscape and temporary permits are filed together and decided together. Licences from other bodies, such as a MIDA manufacturing licence, are applied for separately.
Can I submit an OSC application myself without an architect?
No. Plans go in through a Principal Submitting Person or Submitting Person, which means a professional architect, a professional engineer or, for small buildings, a registered building draughtsman. The owner supplies the land, tax and company documents and signs the forms. Even a minor renovation permit needs plans signed by a registered consultant.
How long does OSC approval take for a factory in Selangor?
Under the Manual OSC 3.0 Plus, a medium-category planning permission filed with its building and engineering plans has a limit of 57 to 99 calendar days. Industrial projects that qualify for SPEED Selangor are capped at 30 days from a complete application. The clock starts only when every item on the checklist is in.
How much does planning permission cost for a factory in Selangor?
Under the Planning Control (General) (Selangor) (Amendment) Rules 2025, the fee for a factory, workshop, store or warehouse is RM100 per 100 square metres of gross floor area, so 5,000 square metres comes to RM5,000. Building plan fees, development charges and the ISF contribution are charged separately. Your PSP prepares the full fee calculation for the council.
Do I need OSC approval to renovate or extend a factory?
Structural changes and extensions need approved plans, and minor works need a renovation permit through the council. A change of use, such as turning a warehouse into a food plant, can need fresh planning permission even with no building work. Ask your architect to compare the work with the approved plans before anything starts.
Is OSC 3.0 Plus used in Selangor?
Yes. All 12 Selangor councils, including MBDK, MBSA, MBPJ, MBSJ, MPKj and MPS, are listed on KPKT's OSC 3.0 Plus Online portal. The SPEED Selangor guideline also requires every Selangor council to use the OSC 3.0 Plus module.