Key Takeaways

  • A power-driven overhead crane in a Malaysian factory is "lifting machinery" under the Occupational Safety and Health (Plant Requiring Certificate of Fitness) Regulations 2024. Before its first lift it needs DOSH design verification, written installation approval and a certificate of fitness (CF), and the CF is valid for 15 months from the date of inspection.
  • The Factories and Machinery Act 1967 was repealed on 1 June 2024. Cranes, lifts, boilers and pressure vessels now sit under Part VIA of the Occupational Safety and Health Act 1994, and a CF issued under the old law on or before 31 May 2024 stays valid until it expires.
  • Whether a factory can take a 5, 10 or 20 ton crane is decided by the building: the columns and crane brackets, the runway beams, the foundations and the clear height under the roof. Only the structural design or a professional engineer's check can confirm it, and new foundations or columns are building works that need council approval first.
  • A goods lift can be added to most factories, but it needs a pit and shaft, DOSH design verification and a CF. If people ride in it with the goods, it is a "lift" in law, with monthly servicing and a comprehensive examination at least every three months.
  • Before you rent or buy, ask for the CF, the registration number marked on the crane, the maintenance records and the approved plans that show the crane structure, and write down in the SPA or tenancy who pays for inspections and repairs.

A factory with an overhead crane is worth more to a fabrication, steel, mould or machinery business only if the crane is legal to use and the building can carry it. This guide explains what the structure needs, what DOSH approves under the law in force since June 2024, how 5, 10 and 20 ton cranes differ, whether a goods lift can be added, and what to check when you rent or buy a factory that already has a crane.

What does a factory building need before it can take an overhead crane?

The building carries the crane. The 2024 Regulations define an overhead travelling crane as "a crane with a girder equipped with a device for raising and lowering loads and move on a fixed runway". The load travels from the crane wheels into the runway beams, from the runway beams into brackets on the columns, and down the columns into the foundations. Regulation 4(1)(h) requires anyone installing a crane to ensure the foundation "is adequately designed and constructed to support and withstand the load imposed on it".

The building items that decide crane capacity

Item What it does What to ask for or check on site
Columns and crane brackets Hold up the runway along the bay Structural drawings that show crane loads; a bracket on every column along the runway
Runway beams and rails The crane travels on them Continuous beams, rails in line, end stops at both ends, no cut or patched sections
Foundations Take the column loads into the ground Design notes; cracks or sinking at column bases
Clear height Sets the highest point the hook can reach Measure to the lowest roof member; ask the crane supplier for a clearance drawing
Span and runway length Decide which crane fits and how far it travels Rail centre to rail centre, and the length of the runway
Power supply Runs the hoist, cross travel and long travel motors Compare the crane motor ratings with the supply using the factory power calculator

Why the hook never reaches the roof

The crane bridge, the hoist and the rails sit between the hook and the roof, so the usable hook height is always lower than the clear height. The crane supplier works the required building height back from your tallest lift with the slings attached. Measure it yourself; listings often quote eave or ridge height. Our factory specs guide explains how to measure clear height, crane span and hook height.

When the floor matters

For an overhead crane the columns, not the floor slab, take the crane load. A gantry crane standing on its own legs on floor rails is different: DOSH lists gantry cranes in its "other crane" group, and their load goes into the slab and the rail foundations, so those must be checked. Heavy machines and racking under the crane still load the slab; work them out with the floor loading calculator.

5, 10 or 20 ton: what changes as the crane gets bigger?

The approval path is the same for all three. What changes is the load on the structure and the DOSH fee band. A bigger safe working load (SWL) means heavier wheel loads on the runway beams, bigger forces on the brackets and columns, and bigger column loads on the foundations.

Crane Who installs it DOSH design verification fee Inspection fee for the CF and each periodical inspection
5 ton (5,000 kg) A DOSH registered competent person or the origin manufacturer RM300 per design unit RM750 (5,000 kg to under 10,000 kg)
10 ton (10,000 kg) Same RM300 per design unit RM950 (10,000 kg to under 20,000 kg)
20 ton (20,000 kg) Same RM300 per design unit RM1,200 (20,000 kg and above)

The fees come from the Sixth Schedule of the 2024 Regulations. The Seventh Schedule requires an overhead travelling crane with an SWL above 4,000 kg to be installed and dismantled by a competent person or the origin manufacturer. These are government fees only. The crane, the runway steel, installation and the engineer's work are quoted by the supplier and vary with span, height and duty, so get written quotes.

Can a 20 ton crane be installed in an existing factory?

Only if the structure was designed for it or is strengthened for it. A runway built for a 5 ton crane cannot simply take a 20 ton crane. The steps:

  1. Get the original structural drawings and calculations from the owner or the original consultant.
  2. Appoint a professional engineer to check the columns, brackets, runway beams and foundations for the new crane loads. DOSH's design verification guide says the design calculation of the lifting machinery support system by a certified professional engineer (PEPC) is to be included as required.
  3. If strengthening adds new foundations or new or increased structure, get council approval of the plans first (see the council section below).
  4. Apply for design verification of the new crane, then installation approval, installation, the load test and the CF.

Raising the SWL of a crane already in the building is an "alteration" that needs DOSH's written approval. DOSH only accepts an alteration application for a crane that already has a CF and where the manufacturer allows that scope of change.

How to find out the crane beam capacity

The SWL marked on the crane and printed on the CF is the rating of the crane, not proof of what the building can carry. The building's capacity is in the structural design. If no drawings exist, a professional engineer can assess the structure on site. Warning signs: brackets added later, welded beam extensions, runway beams that are not continuous, rails out of line, and cracks at column bases.

Which law applies to factory cranes now, and what does DOSH approve?

Since 1 June 2024, cranes and other lifting machinery are governed by sections 27B to 27F of the Occupational Safety and Health Act 1994, inserted by Act A1648, and by the 2024 Regulations (P.U. (A) 99/2024). The Factories and Machinery Act 1967 was repealed by the Factories and Machinery (Repeal) Act 2022.

From order to first lift

  1. Design verification. Applications go through DOSH's MySKUD system with a MyKKP login. For a crane made in Malaysia, only a registered competent person (company) may apply; for an imported crane, the origin manufacturer or its appointed installer, sole distributor or agent. Fee RM300. DOSH's client charter says complete applications are processed within 15 working days.
  2. Installation approval. Section 27C requires DOSH's written approval before installation, and DOSH's guide says only the owner, the occupier or the holder of the design verification may apply for it.
  3. Installation. By a registered competent person or the origin manufacturer for cranes above 4,000 kg.
  4. Inspection. You serve written notice on a DOSH officer or licensed person (section 27D(2)). The inspection includes a load test at the load in the design verification and a functional test of every safety device (regulation 5(2)(d)).
  5. Certificate of fitness. Valid for 15 months from the inspection date (regulation 5(6)). The owner must mark the registration number prominently on the crane (regulation 18).
  6. Periodical inspection. Due before the CF expires. The inspector may set the date, but not earlier than the first day of the twelfth month after the last inspection, and may give 14 days' written notice (regulation 6(2)).

Penalties that matter to an owner

  • Installing without approval: a fine of up to RM100,000, jail of up to one year, or both (section 27C(4)).
  • Operating without a CF: the same maximum (section 27D(5)). An officer can serve a notice prohibiting use or make the crane inoperative, and ignoring that notice carries up to RM500,000, two years' jail, or both (sections 27D(6) and (7)).
  • Altering a crane without approval, or having it dismantled by someone who is not a competent person: up to RM50,000, one year, or both (regulations 10 and 11).
  • A CF ends when the crane is dismantled, repaired or damaged (section 27D(8)).

Certificates issued under the old Act

DOSH's transition FAQ says a CF issued under the 1970 regulations on or before 31 May 2024 stays valid until it expires. Crane operator certificates issued under the old Act also stay valid until expiry, but holders must register again under Act 514 through MyKKP. The same FAQ says owners no longer need to apply for the old first inspection of a factory after 31 May 2024.

Who may operate the crane

Regulation 15 requires every tower crane and mobile crane to be operated only by a registered competent crane operator. That rule does not name overhead travelling cranes, but section 15 of the Act still requires every employer to provide the information, instruction, training and supervision needed for safe work. Train your overhead crane operators and keep a written record of who is authorised.

Overhead crane lifting a steel coil on runway beams carried by column brackets in a factory
IllustrationOverhead crane lifting a steel coil on runway beams carried by column brackets in a factory

Do you need council approval to add crane columns, brackets or a lift shaft?

Usually yes. Section 70(1) of the Street, Drainage and Building Act 1974 says no person shall erect any building without the prior written permission of the local authority. Section 70(16) treats anyone who adds to or alters an existing building in a way that involves new foundations, or new or increased superstructure, as erecting a building. Where new foundations are involved, the plans must be submitted by a principal submitting person or submitting person (section 70(2)), and section 79 separately requires permission for any partition, gallery, loft, roof, ceiling or other structure erected inside a building.

New crane columns with their own footings, a lift pit and a lift shaft cut through the floor slabs all fall within this kind of work. Ask your architect or engineer to confirm the submission with the council (MBSA, MBDK, MBPJ, MPKS or MPSepang, depending on the location) before work starts. Structural work done without approval is an unapproved alteration, which a buyer's lawyer, a bank valuer or an insurer may question later; our guide to the CCC, explains why approved plans matter. Mezzanine floors, floor cracks and slab strengthening, and TNB power upgrades are covered in separate FactoryHub guides.

Can a goods lift be installed in a factory?

Yes, in most two or three storey factories, if there is room for the shaft and pit, the floor slabs can be opened, and the structure can take the lift loads. First decide whether people will ride in it, because that decides how DOSH classes it.

Type How DOSH classes it Design verification fee Ongoing duties
Carries people, or people and goods A "lift" under regulation 2 RM5,000 Service and adjustment at least monthly; comprehensive examination by a competent person at least every three months; a maintenance agreement of at least one year
Goods only, nobody rides (built to EN 81-31) Listed with goods hoists and material hoists in DOSH's 2025 guide RM300 for a hoist Keep it maintained in a safe condition, CF renewed every 15 months

Ask the lift supplier which category DOSH will register your unit under before you sign, because the fees and maintenance duties differ. A lift's CF inspection fee depends on travel distance, starting at RM650 for less than 12 metres; a material hoist's depends on its SWL, from RM350 below 500 kg to RM1,000 at 1,500 kg and above. Lifts and hoists must be installed by a competent person (Seventh Schedule). For lifts, the Thirteenth Schedule also requires the machine room and pit to be used only for the lift, a danger sign at the machine room door, and a notice with the contact for breakdowns.

DOSH's director-general told The Star in September 2026 that a lift receives a CF only after it passes inspection and testing, that the certificate is valid for 15 months, and that an owner operating without one faces a fine of up to RM100,000, jail of up to a year, or both.

Which factory equipment must have a DOSH certificate of fitness?

Regulation 3 lists three groups: steam boilers, pressure vessels and lifting machinery. Production machines such as presses, CNC machines and moulding machines are not on the list, although any boiler, pressure vessel or lifting device that comes with them is, and the employer's general safety duties still apply.

Needs a CF Examples in a factory Excluded by the Second and Third Schedules (examples)
Steam boiler Boilers for process steam
Pressure vessel Any enclosed vessel under pressure, such as a compressed air receiver Design pressure of 15 psig or less; gas cylinders; plate and spiral heat exchangers; vessels inside a building chiller package
Lifting machinery Overhead, gantry and jib cranes, hoists, lifts, goods scissor lifts, powered chain hoists fixed to the structure Forklifts and other material handling equipment, dock levellers, vertical conveyors, automated storage and retrieval systems, pneumatic lifting machinery up to 500 kg, cranes lifting no more than 9 m and 80 kg, manual lifting machinery

The duty to get approval and a CF falls on whoever installs or operates the plant, so a tenant who brings in a compressor receiver or a jib crane needs its own approvals even when the landlord's crane is already certified.

Goods lift carrying a loaded pallet in a two storey factory, with the lift pit and guide rails
IllustrationGoods lift carrying a loaded pallet in a two storey factory, with the lift pit and guide rails

Renting or buying a factory with a crane: what should you check?

Check the paperwork, test the crane, and settle in writing who carries each duty. Start your search with factories with overhead cranes for sale or for rent in Selangor, then verify each crane yourself.

Documents to ask for

  • The current CF, checked against the crane in front of you and its expiry date. DOSH's application form calls the lifting machinery CF number the "PMA number".
  • The registration number marked on the crane (regulation 18).
  • Maintenance records, which the employer must keep (regulation 19), and the design verification, installation, testing, inspection, repair and alteration records that must be kept at the place of work (regulation 20).
  • Approved building plans and structural drawings that show the crane columns, brackets and design crane load.
  • The servicing company's registration. DOSH says the list and scope of registered competent person companies can be checked on MyKKP.

Site checks

Run the crane through its full long travel, cross travel and hoist. Test the brakes, limit switches and emergency stop. Check that the SWL marked on the bridge and the hoist matches the CF, and walk the runway for alignment and end stops.

Rules that change the deal

  • Sale or lease of the crane. The owner must notify the DOSH officer or licensed person within 30 days after selling, leasing, transferring or disposing of the crane (regulation 5(5)(c)). Put the crane, its capacity and its CF in the SPA schedule.
  • Who is the "owner" in a rented factory. The 2024 Regulations define an owner to include a person who receives rent by leasing the plant, so a landlord who lets the factory with its crane carries the owner's duties, such as maintenance (regulation 8). The tenancy should still say who pays for periodical inspections, servicing, wire ropes and repairs.
  • Vacant factories. If a crane has fallen into disuse, the owner must notify DOSH within 30 days (regulation 5(5)(d)). A lapsed CF means a fresh inspection before the first lift.
  • Bringing your own crane. DOSH's guide says an overhead travelling crane is a permanent structure, so moving it to a new factory needs alteration approval even if the SWL does not change, plus installation approval at the new site (regulation 4(3)), competent person dismantling and installation, and a new inspection.
  • Second-hand imports. DOSH does not allow design verification for used imported overhead travelling cranes, goods hoists and passenger hoists, so plan on a new crane or one already certified in Malaysia.
  • End of tenancy. If you install a crane in a rented factory, agree in the tenancy whether it stays or goes, and remember that dismantling must be done by a competent person.

This guide explains the law and DOSH's published requirements; it is not legal or engineering advice. Confirm your project with DOSH, the council and a professional engineer.

Approvals, title and rules: more questions

Does an overhead crane operator need a DOSH licence?

The 2024 Regulations require registered competent operators for tower cranes and mobile cranes, and they do not name overhead travelling cranes in that rule. Employers must still train and supervise overhead crane operators under section 15 of the OSH Act, so keep training records and a list of authorised operators.

Which equipment in a factory must be registered with DOSH?

Steam boilers, pressure vessels and lifting machinery such as cranes, hoists and lifts, unless they fall under the exemptions in the Second and Third Schedules. Each one needs design verification and a certificate of fitness, and the registration number must be marked on the plant.

Before you view a crane unit: Ms Teh Seok Hoon's DOSH and PMA checks for Klang factories and Jason Low's crane beam checks for factories to rent near Rawang and Shah Alam.

Frequently Asked Questions

I need a 30,000 sq ft factory in Klang with 1,000A power and a crane. Where can I find one?

Start in the Port Klang belt and Kapar: on FactoryHub, most advertised factories at 1,000A and above are in Pulau Indah, Westport, Northport, Telok Gong and Klang, followed by Kapar. Search with both the amperage and the overhead crane filters, or send the brief to Peter Tan (016-666 6872) or Jason Low (012-288 1834), as some owners do not advertise. Before you sign, check the crane's DOSH certificate of fitness and safe working load against the crane itself, ask for a recent TNB bill, and make sure the approved plans show the crane structure.

Where can I find a factory with a large overhead crane?

There is no single crane area: factories with overhead cranes are spread across Selangor, and on FactoryHub they appear in places such as Shah Alam, Port Klang, Kapar, Semenyih and Serendah. Use the overhead crane filter on the spec search, or ask Peter Tan or Jason Low, then check each crane yourself: a valid DOSH certificate of fitness, the safe working load marked on the crane, the runway beams and the clear height under the hook. A crane brought from another factory needs DOSH alteration and installation approval.

Do I need DOSH approval to install an overhead crane in my factory?

Yes. A power-driven overhead crane is lifting machinery under the 2024 Regulations, so it needs DOSH design verification, written approval to install under section 27C of the OSH Act, and an inspection with a load test before a certificate of fitness is issued. Installing without approval carries a fine of up to RM100,000, up to a year's jail, or both.

How long is a crane certificate of fitness valid in Malaysia?

Fifteen months from the date of inspection, under regulation 5(6) of the 2024 Regulations. The periodical inspection must be done before it expires, and the inspector will not set the date earlier than the first day of the twelfth month after the last inspection.

Can a 20 ton overhead crane be installed in an existing factory?

Only if the columns, crane brackets, runway beams and foundations were designed for that load or are strengthened for it, which a professional engineer has to confirm from the structural drawings or a site assessment. Strengthening that adds foundations or structure needs council approval, and the new crane still needs design verification, installation approval, a load test and a CF.

Does a forklift need a DOSH certificate of fitness?

No. Forklifts are material handling equipment, which the Third Schedule of the 2024 Regulations excludes, together with dock levellers, vertical conveyors and automated storage and retrieval systems. The employer's general duty to keep equipment safe and train drivers still applies.

Can I move my overhead crane from my old factory to the new one?

Yes, but it is treated as a new installation at the new site. DOSH requires alteration approval for relocating an overhead travelling crane even without a change in SWL, installation approval at the new location, dismantling and reinstallation by a competent person, and a fresh inspection, because the old CF ends when the crane is dismantled.

Who pays for crane inspections in a rented factory?

The 2024 Regulations place the owner's duties, such as maintenance, on the person who leases out the crane, which is usually the landlord. Who bears the cost of inspections, servicing, wire rope replacement and repairs is a commercial point, so agree it in the tenancy before you sign.