Key Takeaways

  • A recycling factory in Malaysia needs approvals on four fronts: the land and its zoning, the Department of Environment (DOE), the local council's industrial premise licence, and, if you import feedstock, a manufacturing licence or ICA10 letter from MIDA plus a SIRIM Certificate of Approval for every shipment.
  • DOE's siting guideline grades plastic sorting, washing and pelletising (materials recovery, MSIC 38383) as heavy industry with an overall buffer of 350 m from homes. Making products from recycled resin is graded medium, with 200 m.
  • The EIA Order 2015 lists "construction of recovery plant or recycling plant" for solid waste as a prescribed activity. In 2019 a Sepang court fined two Selangor plastic recyclers for recycling without DOE approval under section 34A(2).
  • Since 1 July 2025, imported plastic waste (HS 39.15) needs a SIRIM Certificate of Approval: only licensed manufacturers qualify, the material must be at least 99.5% one polymer, and each certificate costs RM350 per shipment. E-waste imports are now absolutely prohibited: announced on 4 February 2026 and gazetted with effect from 1 April 2026.
  • In Selangor, the state said in May 2022 that new business licences for plastic recycling factories will not be approved. A landlord who lets a factory to a recycler without checking the title, the DOE class and this policy risks closure orders, cut utilities and action against the land.

A recycling plant is one of the hardest uses to place in a Malaysian factory. The process sits in a heavier DOE class than most manufacturing, approvals are tied to the exact site, and the rules on imported waste changed twice between 2025 and 2026. This guide answers the questions a buyer, tenant or landlord asks before money changes hands: which factory can take a recycling business, which approvals a plastic recycling plant needs, how the plastic waste import permit works, and what a landlord must check first. It is general information, not legal advice: confirm your own case with DOE, your council, SIRIM, MIDA and a lawyer.

Which factory can legally take a recycling business?

Direct answer: a factory whose land title is in the industry category with a condition that covers your process, in an area the local plan zones for that class of industry, and far enough from homes, schools and hospitals for the DOE class of your activity. For most plastic, metal and mixed recyclers that means a heavy industry lot, normally a detached factory with its own yard.

The title decides first

The National Land Code gives every lot one of three categories (section 52). Industry land may only be used for factories, workshops, warehouses and similar buildings used for manufacture, processing and storage of goods (section 117), and any breach of a condition makes the land liable to forfeiture to the State (section 127), although the Land Administrator may impose a fine instead. Many Selangor industrial titles also name a class: light, medium or heavy. Read the express condition on an official title search before you sign. Our guide to light, medium and heavy industry shows how to read it.

The DOE class of your process

DOE's Guidelines for Siting and Zoning of Industry and Residential Areas (October 2012) grade each activity by its Malaysia Standard Industrial Classification (MSIC) code:

Activity in the guideline MSIC Class Overall buffer Primary buffer
Sorting and pelleting of plastics; cleaning, melting or grinding plastic or rubber waste into granulates; sorting mixed paper, plastics, cans and metals; dismantling cars, computers and TVs for materials; crushing and sorting glass 38383 Heavy (2) 350 m 300 m
Making plastic products from new or recycled resin (moulding, extrusion, blow moulding) 22222 Medium (3) 200 m 150 m
Treatment and disposal of hazardous waste 383823822 High risk (1) 1,000 m 800 m

The overall buffer is the distance to the nearest sensitive receptor such as housing. At least the primary part must lie outside your own boundary; the rest can be made up inside your lot. The 22222 row also asks for a 20 m buffer around boilers, blowers, gensets, pumps and fuel storage. A plant that washes and pelletises waste plastic therefore carries the same buffer as a steel rolling mill, not the buffer of a moulding shop.

What to check on site

  • Distance from the building to the nearest house, school, hospital or place of worship, measured on a map, not estimated.
  • Yard space for bales and jumbo bags, kept separate from drains and boundaries.
  • Where washing water would go: an effluent treatment system, and in Selangor a licence under the state's zero discharge rules.
  • Fire separation from neighbours and access for Bomba. See our Bomba requirements guide.

What decides the right unit is the process: sorting and baling only, washing plus extrusion, or handling waste that is scheduled waste. The heavier the process, the fewer lots qualify.

What DOE approvals does a plastic recycling plant need?

Direct answer: usually an approved EIA before construction, written notifications for air emissions and industrial effluent, and compliance with the scheduled waste rules for the waste your process creates. Which ones apply depends on your process and scale, so ask the DOE state office at the planning stage.

Environmental Impact Assessment (section 34A)

The EIA Order 2015 puts these in the First Schedule: for solid waste, "construction of recovery plant or recycling plant", and for scheduled waste, an off-site recovery plant, off-site wastewater treatment plant or off-site storage facility. The Second Schedule, which needs public display and comment, covers an off-site recovery plant for lead acid battery waste and recycled paper mills of 50 tonnes a day or more. Splitting a project into smaller parts to stay under a threshold still counts. According to MIDA's environmental services booklet, First Schedule EIAs are approved by the DOE state office and Second Schedule EIAs by DOE headquarters.

This is enforced. In May 2019 the Sepang Sessions Court fined two plastic recyclers in Jenjarom and Kuala Langat for recycling used plastics without DOE approval under section 34A(2), and for failing to notify DOE of air polluting work, failing to fit air pollution control on the machine that melts plastic, and failing to notify DOE of effluent from a washing line (Malay Mail). Penalties are heavier now: amendments in force from 7 July 2024 set a minimum fine of RM5,000, a maximum of RM10 million, and mandatory jail of up to five years for offences that include not complying with EIA requirements (Bernama via Malay Mail).

Air and effluent notifications

Under the Clean Air Regulations 2014, the owner must notify DOE at least 30 days before work that creates a new emission source or installs fuel burning equipment of 30 kg an hour or more of solid fuel (15 kg for liquid or gas), then submit a written declaration within 30 days of starting. Washing lines produce industrial effluent, which needs written notification under the Industrial Effluent Regulations 2009. In Selangor, LUAS also licenses discharges: in May 2026 a recycling factory in Mahkota Beranang that held a LUAS licence but broke its conditions was investigated after a coloured discharge was traced to it and odour reached Sungai Semenyih (Kosmo). For the building side, see this partner guide to factory wastewater and LUAS licences.

Officer checking the extruder chimney and wastewater tank at a plastic recycling plant
IllustrationOfficer checking the extruder chimney and wastewater tank at a plastic recycling plant

Do you need a scheduled waste licence?

Direct answer: every recycler must manage the scheduled waste it generates; only a recycler whose input is scheduled waste needs a DOE licence as an off-site recovery facility.

Waste your process creates

The Scheduled Wastes Regulations 2005 require you to notify DOE within 30 days of generating a new category, to send it only to licensed (prescribed) premises, and to store it for 180 days or less and no more than 20 tonnes unless DOE agrees. Codes that can arise in a recycling plant include SW409 (containers or bags contaminated with chemicals or oil) and SW410 (rags, plastics or filters contaminated with scheduled waste). DOE's own green industry guide for plastic recyclers recorded SW409 at one audited plant. A separate FactoryHub guide on scheduled waste management in factories covers storage and contractors in detail.

When the input is scheduled waste

E-waste (SW110), contaminated containers and spent solvents are scheduled wastes. Recovering material from scheduled waste produced elsewhere makes the site an "off-site recovery facility", a prescribed premises. MIDA's booklet sets out the chain: EIA approval, written permission to construct under section 19, then a section 18 licence to occupy and use the premises, at RM100, valid for one year unless stated otherwise and renewed at least three months before expiry. DOE publishes a searchable list of licensed facilities by state, licence type and waste code, including partial and full e-waste recovery.

How do you get the import permit for plastic waste?

Direct answer: since 1 July 2025 you need a SIRIM Certificate of Approval (COA) for every shipment of HS 39.15 plastic waste, replacing the old JPSPN approved permit, and only a licensed manufacturer that can process the material in-house may apply (SIRIM, MITI).

Who qualifies

The SIRIM Guidelines for Importation and Inspection of Waste Plastic (May 2025) allow only manufacturers holding a MITI manufacturing licence or a MIDA ICA10 exemption letter whose scope covers the material. The waste may come only from Basel Convention parties or countries with a qualifying agreement. Only the manufacturer that will process the material qualifies, and SIRIM expects any trading arm acting as applicant and any outsourced crushing or re-melting to be listed and inspected. If you are unsure whether you need the licence or the letter, read our manufacturing licence guide.

What SIRIM checks

Requirement What it means
MISW licence SIRIM inspects the factory under its Management of Imported Scrap and Waste guideline: processing capability, storage, calibrated weighing, records kept five years. Valid three years, quota renewed yearly
Quota Existing plant running over a year: 110% of its highest annual production in the last five years. New plant or new capacity: 50% of maximum production capacity
Purity Clean, recyclable, not from landfill, at least 99.5% one polymer; other materials 2% max; zero oil, mould, food waste, e-waste, scheduled waste
Bank guarantee Enough to cover the highest cost of shipping non-conforming material back
Compliance Premises compliant with the Clean Air, Industrial Effluent and Scheduled Wastes Regulations, with adequate storage

Fees and timing

Item SIRIM fee or charter
COA, per shipment RM350, non-refundable; valid 60 days
Pre-shipment inspection abroad (Type 1) RM1,000 half day, RM1,500 full day, RM125 per extra hour, plus travel
Factory yard inspection (Type 2) RM300 for the first 3 containers, RM100 each after, RM500 report per shipment
Timing Pre-shipment route 6 to 12 working days; yard inspection 3 to 6; COA evaluation 3 working days

Non-conforming loads go back at the importer's cost, the bank guarantee can be forfeited, and more than two non-conformances can bar future applications.

The policy is still moving

On 4 February 2026 a government task force announced that e-waste would move to absolute prohibition and discussed a three-month moratorium on plastic waste imports, pending data for the Prime Minister (The Star). The e-waste ban was gazetted under the Customs (Prohibition of Imports) Order 2023 with effect from 1 April 2026 (NST). In April 2026 the government said it was still reviewing whether Malaysia should keep importing plastic waste (NST). Do not build a business plan that depends on imported feedstock without asking SIRIM for the current position.

Which council licence applies, and what is Selangor's policy?

Direct answer: you need the council's industrial premise licence, which in Selangor is only issued after technical agencies comment, and for plastic recyclers Selangor's 2022 policy says new licences will not be approved.

The council licence

At MBSJ, for example, factory licences are Category B, which need technical comments from other departments; a normal application goes to the licensing technical meeting within 14 working days, a full licence runs one year, and a six-month temporary licence may be given while other approvals are pending (MBSJ guideline). The council, DOE and the building's own approvals connect in a fixed order, mapped in our factory approvals guide.

Selangor's plastic recycling policy

In May 2022 the Selangor government said new business licences for plastic recycling factories would not be considered or approved by state or local authorities, that factories in the state may not import plastic waste for recovery or final disposal, and that the policy would be reviewed every five years. Existing licensed factories may continue, subject to EIA technical committee and council conditions (Sinar Harian, Utusan). In January 2025 the state's environment exco said Selangor "has banned the import of foreign plastic waste" (The Star). Before you commit to a Selangor site for plastic recycling, ask the council's licensing department in writing whether it can licence your activity at that address.

Kuala Lumpur and Negeri Sembilan: Act 672

Act 672 applies in Johor, Melaka, Negeri Sembilan, Pahang, Perlis, Kedah, Kuala Lumpur and Putrajaya, but not in Selangor (KPKT). Where it applies, a "material recovery facility", one that processes controlled solid waste by mechanical methods to separate useful materials, is a prescribed solid waste management facility: plans to build or alter it need the Director General's approval through SWCorp, and operating it needs a licence (P.U.(A) 302/2011).

Metal recyclers: check MIDA first

MIDA announced that from 15 August 2023 MITI froze manufacturing licence and ICA10 applications for iron and steel, including recycling and recovery in the non-ferrous segment, and its 8 November 2024 update kept non-ferrous recycling under the moratorium. A manufacturing licence is needed at RM2.5 million of shareholders' funds or 75 full-time employees (MIDA). Ask MIDA's Machinery and Metal Technology Division for the current position before you sign for premises.

Landlord and tenant measuring the distance from a detached factory to nearby houses
IllustrationLandlord and tenant measuring the distance from a detached factory to nearby houses

What must a landlord check before letting a factory to a recycler?

Direct answer: check that the process fits the title, the zoning and the DOE buffer, that the tenant can actually get each approval at your address, and that the lease leaves the tenant, not you, holding the clean-up.

Enforcement lands on the building as well as the operator. In June 2026 MPKS closed two plastic recycling premises in Jeram that were running without a valid licence: it compounded them, seized machinery, served notices under section 70(1) of the Street, Drainage and Building Act 1974, Air Selangor cut and removed the water meters, and TNB issued electricity disconnection notices (Kosmo). In April 2026 Selangor DOE served notices on owners of private land used for illegal scrap processing to carry out remedial measures, and compounded several (The Star).

Check How
Title and class Official title search; compare the express condition with the DOE class of the tenant's process
Buffer Measure to the nearest house, school, hospital or place of worship
State policy For plastic recycling in Selangor, a written answer from the council licensing department
Approvals as conditions Lease starts only after the council licence, DOE notifications or EIA approval, and SIRIM MISW if importing
Scheduled waste Search the tenant on DOE's eSWIS list if it handles scheduled waste
Use clause Name the exact process, materials and maximum stock on site; ban open burning and e-waste
Exit Tenant removes all stock and waste and reinstates before the deposit is returned
Insurance Declare the real use to your fire insurer and require the tenant's own cover
Company SSM, CTOS, directors and past premises, as in our tenant screening guide

The deposit and guarantee that make sense depend on the stock the tenant will hold and the cost of removing it, which only a quote can tell you. Do not set them by habit.

Common mistakes

  • Signing a lease because the title says "industry", without checking whether a heavy process is allowed.
  • Assuming the previous recycler's licence passes to you. Council licences, DOE notifications and the MISW certificate are tied to the operator and site.
  • Planning on imported bales before confirming eligibility for a SIRIM COA and the current import policy.
  • Accepting e-waste or contaminated material without an off-site recovery facility licence.
  • Running a washing line before the effluent notification and, in Selangor, the LUAS licence.

Frequently Asked Questions

Where can I find a factory suitable for a recycling business?

Look for a detached factory with its own yard on heavy industry land, because DOE grades sorting and pelletising of waste plastics, paper, cans and metals as Category 2 with a 350 m buffer from homes. In FactoryHub's experience, heavy industry lots are found in Pulau Indah, Westport, Kapar, Banting (Olak Lempit) and Jenjarom. Note that Selangor said in 2022 it would not approve new licences for plastic recycling factories, so ask the council in writing first, and check the effluent route and Bomba access.

What licence do I need to open a recycling factory in Malaysia?

You need a factory on industry land that allows your class of process, the council's industrial premise licence, and DOE clearance, which for a recycling plant often means an approved EIA plus air and effluent notifications. If you import waste plastic you also need a MITI manufacturing licence or MIDA ICA10 letter and a SIRIM Certificate of Approval for each shipment. Recovering scheduled waste such as e-waste needs a DOE section 18 licence as well.

How do I start a plastic recycling company in Malaysia?

Fix the process first (sorting, washing, pelletising, or making products), because it sets the DOE class: pelletising waste plastic is heavy industry with a 350 m buffer. Then find a heavy industry lot, confirm with the council and DOE that the activity can be approved there, and apply for the EIA, notifications and council licence before you install machines. In Selangor, check the 2022 policy on new plastic recycling licences before anything else.

How do I apply for an e-waste licence in Malaysia?

E-waste is scheduled waste (SW110), so a plant that recovers it is an off-site recovery facility. You need EIA approval, DOE's written permission to construct under section 19, and then a section 18 licence to occupy and use the premises, applied for at the DOE state office. E-waste imports have been absolutely prohibited since the order took effect on 1 April 2026, so feedstock must come from within Malaysia.

Can I import plastic scrap without a manufacturing licence?

No. SIRIM issues a Certificate of Approval only to manufacturers holding a MITI manufacturing licence or a MIDA ICA10 exemption letter whose scope includes the material and who can process it in-house. A company without a licence that covers the material, or without the machines to process it, is not eligible.

Is a recycling factory light, medium or heavy industry?

Under DOE's 2012 siting guideline, materials recovery, including sorting and pelleting plastics and grinding plastic or rubber waste into granulates, is heavy industry with an overall buffer of 350 m. Making new products from recycled resin is medium industry with 200 m. Hazardous waste treatment is high risk with 1,000 m.

Can I run a plastic recycling factory in Selangor?

Selangor said in May 2022 that new business licences for plastic recycling factories would not be approved and that factories may not import plastic waste, while existing licensed factories may continue under conditions. The policy was due for review every five years, so ask the council's licensing department in writing before you buy or rent.

Can a landlord get into trouble for a tenant's illegal recycling plant?

Yes. In 2026 Selangor DOE served remedial notices on owners of land used for illegal scrap processing and compounded several, and in a June 2026 case in Jeram, Air Selangor removed the water meters and TNB issued disconnection notices at unlicensed recycling premises. Using industry land against its conditions also makes the land liable to forfeiture under section 127 of the National Land Code.