Key Takeaways

  • There is no single "DOE approval" that every factory needs. What the Department of Environment (DOE) asks for depends on the process: an EIA for prescribed activities, written notification for air emission sources, a licence for a few prescribed premises, and acceptable noise at all times.
  • An EIA is needed only for activities listed in the EIA Order 2015, such as chemical production of 100 tonnes a day or more, cement grinding of 200 tonnes a day or more, steel production of 200 tonnes a day or more from scrap, recycling plants and industrial estates of 20 hectares or more. Most single factories in an existing estate fall outside the list.
  • Under the Clean Air Regulations 2014 you must give DOE written notification at least 30 days before installing or changing a boiler, furnace, generator set, chimney, spray booth or dust collector, then submit a written declaration within 30 days of starting operations. DOE's client charter promises a decision on fuel burning and air pollution control equipment within 3 weeks.
  • DOE's 2019 noise guideline recommends 75 dBA by day and night in an existing industrial zone, but 65 dBA by day and 60 dBA at night at nearby homes. The nearest house, school or hospital usually sets your real limit.
  • A polluting neighbour can hurt your production through dirty air, contaminated water and shared water supply. In 2020, pollution in the Sungai Gong industrial area in Rawang shut four water treatment plants and cut water to 1,292 areas of the Klang Valley.

A factory in Malaysia needs DOE clearance for what it emits and, for a short list of industries, for what it is. If your process is a prescribed activity, DOE must approve an EIA report before any other authority approves the project. If you burn fuel or vent process air, you notify DOE before installation and declare the finished design after start up. Noise has no permit, but the Environmental Quality Act 1974 makes excess noise an offence. Location runs through all of it: DOE expects heavier industry to sit further from homes.

This guide summarises public rules for planning purposes and is not legal advice. Confirm your own case with the DOE state office or a DOE registered consultant.

Does a factory need DOE approval in Malaysia?

Only for certain activities and equipment. The local council approves the building; DOE looks at what happens inside it. A dry warehouse or an assembly line with no boiler, generator or exhaust stack may have nothing to file with DOE at all, while a plant with a boiler and a paint line has several submissions.

Your situation What DOE requires Law Timing
Process listed in the EIA Order 2015 EIA report approved before other approvals Section 34A, Environmental Quality Act 1974 Decision in 5 weeks (First Schedule) or 12 weeks (Second Schedule) on a complete report
New plant not on the EIA list DOE views on site suitability DOE siting guidelines Preliminary site assessment result in 2 weeks
Boiler, furnace, oven, generator, chimney, scrubber, bag filter, spray booth Written notification, then written declaration Regulations 5 and 7, Clean Air Regulations 2014 At least 30 days before work; declaration within 30 days of operation
New or altered industrial effluent discharge Notification and a treatment system Industrial Effluent Regulations 2009 Before the work
New category of scheduled waste Notification of category and quantity Regulation 3, Scheduled Wastes Regulations 2005 Within 30 days of generation
Palm oil mill, raw rubber plant, off-site scheduled waste facility Prior written permission to build, then a licence Sections 18 and 19 Charter: 3 weeks for permission to build a scheduled waste facility, 2 weeks for a new licence
Noise from the plant No permit; stay within acceptable levels Section 23 All the time

Timings come from DOE's client charter and the regulations themselves. The DOE guide for investors sets out the same order: site suitability or EIA first, then air and water pollution controls.

Owner or tenant? The Clean Air Regulations put each duty on the "owner or occupier of a premises". In practice the company that installs and runs the equipment files the notification, which for a rented factory is usually the tenant. Write into the tenancy who handles DOE work, and get the landlord's consent before cutting a roof for a chimney.

What decides your case: the process and its daily output, the fuel each burner or engine uses per hour, the distance to the nearest homes, and whether you are building new or moving into an approved unit. For the council, Bomba, TNB and MIDA side, see our factory approvals map.

Which factories need an EIA in Malaysia?

Only those whose activity appears in the Environmental Quality (Prescribed Activities) (Environmental Impact Assessment) Order 2015, gazetted on 28 August 2015. First Schedule reports go to the DOE state office without public display. Second Schedule reports go to DOE headquarters and must be displayed for public comment.

Industrial activities on the EIA list

Activity First Schedule (no public display) Second Schedule (public comment)
Chemicals Production of 100 tonnes or more a day
Petrochemicals Below 50 tonnes a day 50 tonnes or more a day
Cement Grinding plant of 200 tonnes or more a day Clinker of 30 tonnes or more an hour
Lime 100 tonnes a day in a rotary kiln, or 50 tonnes a day in a vertical kiln
Iron and steel 100 tonnes a day from iron ore, or 200 tonnes a day from scrap
Non-ferrous metals Primary smelting of aluminium or copper (all sizes); other primary smelting of 50 tonnes or more a day
Pulp, paper and recycled paper 50 tonnes or more a day
Shipyards 5,000 dead weight tonnes or more
Scheduled waste Off-site recovery, wastewater treatment or storage facility Thermal treatment, off-site lead acid battery recovery, secure landfill
Solid waste Composting plant; recovery or recycling plant Thermal treatment, sanitary landfill, transfer station
Power Steam power station on fossil fuel other than coal of 10 MW or more; combined cycle station Coal fired station of 10 MW or more; nuclear power station
Industrial estate Development of 20 hectares or more

Two rules catch people out. Paragraph 3(4) of the Order makes an activity prescribed even if it is split into smaller pieces below the threshold, and also when an expansion pushes an existing activity over it. So a second production line that lifts output past 100 tonnes a day can need an EIA even though the first line did not.

How the EIA works and how long it takes

Under section 34A, the report must reach DOE before the relevant approving authority approves the project, and the activity may not start until DOE approves it. It is prepared by a DOE registered consultant. DOE's EIA Guideline in Malaysia sets 25 working days to review a First Schedule report and 60 working days for a Second Schedule report, counted from a complete submission. Study time before that depends on the project, so ask your consultant for a programme.

The Environmental Quality (Amendment) Act 2024 (Act A1712) raised the penalties. It was gazetted on 6 June 2024 and has been in force since 7 July 2024, the Ministry of Natural Resources and Environmental Sustainability told Parliament, which added that compounds rose from a RM2,000 cap to 50% of the maximum fine. Breaching section 34A now means jail of up to five years, and a fine of RM100,000 to RM1 million may be added.

For a buyer of a lot in a large estate: the estate itself may have needed an EIA when it was developed. Ask the developer or management office whether an EIA was approved and whether its conditions limit the types of industry allowed on each lot.

An environmental consultant and an engineer survey a cleared industrial plot for an EIA study
IllustrationAn environmental consultant and an engineer survey a cleared industrial plot for an EIA study

When do boilers, generators and air pollution control need DOE notification or approval?

Before you install or change anything that creates an air emission source, you must give DOE written notification at least 30 days before the work starts. Regulation 5 of the Clean Air Regulations 2014 applies when you:

  1. change how your premises operate;
  2. carry out work that may create a source of emission;
  3. build a building designed or used for a purpose that may create a new emission source;
  4. change plant, machines or equipment in a way that materially changes the quantity or quality of emissions; or
  5. change or modify an existing air pollution control system.

Which equipment is covered

DOE's download page carries a separate regulation 5 form for fuel burning equipment, generator sets, exhaust and ventilation chimneys, scrubbers, bag filters, cyclones, electrostatic precipitators, spray booths, axial flow vortex tube dust collectors and incinerators. Two thresholds matter:

  • Boilers, heaters and furnaces. Regulation 13(3) requires fuel burning equipment rated to burn 30 kg or more of solid fuel an hour, or 15 kg or more of liquid or gas an hour, to meet the emission limits in the Second Schedule.
  • Generator sets. DOE's guidance document for fuel burning equipment and air pollution control systems says every generator, including a standby set, that consumes more than 15 kg of liquid fuel an hour needs written notification before installation. DOE reviews both the exhaust and the noise at your boundary, wants the exhaust outlet at least 3 metres above ground and diesel storage bunded to 110% of its volume. The notification form also asks you to name every school, clinic or hospital within 150 metres.

Notification or approval?

The 1978 Clean Air Regulations required prior written approval for fuel burning equipment and chimneys. The 2014 Regulations, gazetted on 4 June 2014, replaced that with written notification before the work and a written declaration after it. DOE's client charter still speaks of a decision on "Written Approval to install fuel combustion devices and air pollution control devices" within 3 weeks. Either way, submit to the DOE state office early and do not install until DOE has responded.

After installation

Duty Regulation
A professional engineer designs and supervises the air pollution control system 7(2)
A competent person supervises it whenever it runs 7(4)
Written declaration and as-built drawings within 30 days of starting operations 7(5) and 7(6)
Tell DOE within one hour if the control system fails 8
Where a Schedule requires it, periodic monitoring once a year by a competent person, the first between 3 and 6 months after start up 16
Keep records for at least three years 10
No emission darker than shade No. 1 on the Ringelmann chart, or above 20% opacity 12

Breaching the Regulations carries a fine of up to RM100,000, two years' jail or both. Emitting in breach of the acceptable conditions is also an offence under section 22 of the Act, now punished with a fine of RM10,000 to RM1 million, jail of up to five years or both, plus up to RM1,000 a day if it continues after a DOE notice.

On site: count every chimney, boiler, oven and genset. Ask the owner or previous occupier for the DOE acknowledgement of each notification, the written declaration and the latest monitoring report. A new occupier steps into existing duties: regulation 18(3) makes a new occupier of a First Schedule activity submit the emission declaration for the following year.

What are the DOE noise limits at a factory boundary?

DOE's Guidelines for Environmental Noise Limits and Control, Third Edition 2019 set limits by the land use that receives the noise. For most Klang Valley estates, which are already built up, the Second Schedule applies:

Receiving land use Day (7.00 am to 10.00 pm) Night (10.00 pm to 7.00 am)
Low density housing, schools, hospitals, places of worship 60 dBA 55 dBA
Suburban and urban housing, mixed development 65 dBA 60 dBA
Commercial zones 70 dBA 65 dBA
Industrial zones 75 dBA 75 dBA

For new development the First Schedule is stricter, with 70 dBA by day and 65 dBA at night in an industrial zone. Where the existing noise is already above the Second Schedule, a new source should keep it at the existing level, within 1.5 dBA.

Noise is measured outdoors at the boundary of the receiving property, usually 1.5 to 4 metres above ground. For industrial noise in an industrial zone, DOE may measure at the boundary of your own plant.

The figures are recommendations. The guideline itself says authorities can make them mandatory, for example in EIA approval conditions, and section 23 of the Act makes noise above the acceptable conditions an offence. Under Act A1712 the fine is RM10,000 to RM250,000, jail of up to five years or both, plus up to RM1,000 a day after a DOE notice. Night shifts, loading and DOSH rules for your own workers are covered in our 24 hour factory operation guide.

On site: walk to the nearest house, school or hospital and note its land use. Before your machines arrive, an acoustic consultant can measure day and night levels at your boundary and at that receiver, which gives you a baseline if a complaint comes later.

How far must a factory be from houses?

It depends on the class of industry. DOE's Guidelines for the Siting and Zoning of Industry and Residential Areas (second revised edition, October 2012) give indicative primary buffers from sensitive receptors of at least 50 metres for light industry, 150 metres for medium, 300 metres for heavy and 1 km or more for high risk industry, with modelling where a process is hard to control. MIDA's investor booklet names that guideline and DOE's Environmental Essentials for Siting of Industries in Malaysia (EESIM) 2017 as the guidance for choosing a site, with buffer zones set by PLANMalaysia through the local plan.

Two clauses in the Clean Air Regulations make distance matter after approval too. A "residential area" is a residential zone in the gazetted local plan or, where there is none, a housing estate or any area within 1,000 metres of the nearest dwelling. And regulation 22 lets DOE impose stricter limits, a set fuel or other measures where homes are close or where air pollutants accumulate in an area.

For a new plant outside the EIA list, DOE's charter returns a preliminary site assessment within 2 weeks; ask for it before you commit to the land. How each class appears on the title and in the local plan, with activity examples, is in our light, medium and heavy industry zoning guide.

A planted green buffer strip separates a row of factories from nearby houses
IllustrationA planted green buffer strip separates a row of factories from nearby houses

Will a polluting neighbour affect my production?

It can, in three ways: through your product, through shared water and through tighter rules in a crowded area.

Your product and process

Food factories carry an express duty. Regulation 12 of the Food Hygiene Regulations 2009 says food premises shall be located away from sources of contamination, including aeration ponds, septic tanks and waste disposal sites. A food plant beside a waste recovery yard or an effluent pond has a problem that no fit-out solves. Cleanrooms, coating lines and pharmaceutical plants have no equivalent rule, but dust and solvent from next door raise filter loads and rejects, so check the neighbours as carefully as the building.

Shared water

In September 2020, odour pollution traced to the Sungai Gong industrial area in Rawang forced four Sungai Selangor water treatment plants to stop and cut supply to 1.2 million water account holders in 1,292 areas, including Petaling, Klang and Shah Alam, The Star reported. Factories far from Rawang lost water too. If your process cannot stop, size on-site water storage for it.

Tighter conditions and complaints

Where many plants emit in one area, regulation 22 lets DOE set stricter limits on premises there, and after the incidents listed in the Sixth Schedule, regulation 24 lets DOE order a premises or process to stop. If a neighbour's smoke, odour or noise affects you, complain to DOE on its complaint line 03-8889 1972 or the toll free hotline 1-800-88-2727. The charter promises same day acknowledgement and a status update within 2 weeks. If your effluent goes to a shared treatment plant, read our IETS guide.

On site: visit on a working weekday and at night, look for dust on cars and roofs, smell the air, list the neighbouring operations and their chimneys, and ask the management office about past complaints.

DOE checklist before you rent or buy

  1. Match your process to the EIA Order. Check daily output against the thresholds, including future lines.
  2. List every emission source. Boilers, thermal oil heaters, ovens, gensets, spray booths and dust collectors, with fuel use in kg per hour.
  3. Ask for the DOE file. Notifications, written declarations, monitoring reports, EIA approval and conditions, and any DOE notice or prohibition order on the unit.
  4. Measure the distance to the nearest homes, school, clinic or hospital, and compare it with the buffer for your class.
  5. Book a baseline noise survey if you will run at night or near housing.
  6. Build DOE into the timeline. At least 30 days of notice before installation, plus DOE's response time.
  7. Settle it in the tenancy or SPA. Who files, who pays for controls, landlord consent for chimneys and what happens at the end of the lease.

If you would rather start from units whose layout and neighbours already suit your process, send your brief through Find Me a Factory.

Frequently Asked Questions

Does a warehouse need DOE approval?

Usually not for storage alone, because a dry warehouse has no emission source. It does if you install a standby generator using more than 15 kg of fuel an hour, a boiler or a chimney, and if you generate scheduled waste, which must be notified within 30 days. Chemical and dangerous goods stores also bring Bomba and DOSH rules.

Do I need DOE approval to install a diesel generator in my factory?

Yes if it consumes more than 15 kg of liquid fuel an hour, standby sets included. Submit DOE's generator notification form at least 30 days before installation, with the noise calculation at your boundary, exhaust details and the diesel tank bund. Ask the supplier for the fuel consumption figure at rated load.

How long does DOE approval take for a factory?

DOE's charter promises a decision on fuel burning and air pollution control equipment within 3 weeks, a preliminary site assessment for a new plant within 2 weeks, and a decision on a complete EIA report in 5 weeks (First Schedule) or 12 weeks (Second Schedule). Notification must go in at least 30 days before the work, so plan from that.

Who submits the DOE notification, the landlord or the tenant?

The Clean Air Regulations place the duty on the "owner or occupier", so in practice whoever installs and runs the equipment files it. For a rented factory that is normally the tenant, but the landlord must agree to roof penetrations and chimneys. Put both points in the tenancy agreement.

Do I need an EIA for a factory in an existing industrial park?

Usually not. The EIA Order lists activities by type and size, so most factories in an existing park fall below it. It applies if your process is listed, for example chemicals of 100 tonnes a day or more or a recycling plant, or if an expansion takes you over a threshold.

What is the fine for running a factory without DOE approval?

Since Act A1712 came into force on 7 July 2024, carrying out a prescribed activity without an approved EIA means jail of up to five years, with a possible fine of RM100,000 to RM1 million. Air emissions above the acceptable conditions carry RM10,000 to RM1 million, and excess noise RM10,000 to RM250,000, each with up to five years' jail. Breaching the Clean Air Regulations, such as skipping a notification, carries up to RM100,000 or two years.

Can DOE stop my factory because of a polluting neighbour?

DOE acts against the premises that pollutes, not its neighbours. But regulation 22 lets DOE tighten limits for every emitter in an area where pollutants accumulate, so a crowded estate can mean stricter conditions for you too. Keep your own monitoring records up to date so you can show your share.