Key Takeaways

  • If your company needs a manufacturing licence, it cannot start production the day the tenancy is signed. Section 3 of the Industrial Co-ordination Act 1975 bars manufacturing without a licence, and MIDA issues the certificate only after its approval letter, a no objection letter (from the state government in Selangor) and the documents behind it.
  • In Selangor the licence depends on the building. Invest Selangor's NOL page asks for the land title or conversion approval, the Certificate of Fitness, your sale and purchase or tenancy agreement and the council business licence before MIDA can grant the licence.
  • Moving factory is an amendment; adding a second factory is a new licence. A change of factory location is a post licensing application (RM750, processed within 30 days of complete information), while section 4(2) of the Act requires a separate licence for each place of manufacturing.
  • A licence never passes with the building. Moving it to another company needs MIDA's prior approval under section 7. A share sale keeps the licence with the company, but MIDA lists transfer of shares, change of directors and equity conditions as post licensing applications.
  • More capacity or a new product needs approval first. Expansion and diversification applications cost RM1,500 each on MIDA's fee list, and section 7A bars making products that are not on your licence without prior approval.

Our main manufacturing licence guide explains who needs a licence (shareholders' funds of RM2.5 million or more, or 75 or more full-time paid employees), the ICA10 exemption and how to apply online. This guide picks up where that one stops: what the licence means for the factory you rent or buy, and what to file when you move, expand, add products or change owner. It is written for companies taking a detached or semi-detached factory, a large warehouse or industrial land in Selangor. It is general information, not legal advice; confirm your own case with MIDA or your lawyer.

Can you start production right after renting a factory?

Not if your company needs a manufacturing licence and has not been issued one yet. Section 3 of the Act says no person shall engage in any manufacturing activity unless issued a licence. The penalty is a fine of up to RM2,000 or up to six months' jail, plus up to RM1,000 for every day the default continues. Signing the tenancy is one step toward the licence, not the end of the process.

What comes between the tenancy and the licence?

Step What happens Who
1. Apply online Submit the application on InvestMalaysia. MIDA's client charter commits to 7 working days on the fast track or 60 on the normal track, from complete information MIDA
2. Approval letter MIDA issues an Interim Approval Letter with its conditions in "Lampiran A" MIDA
3. State letter In Selangor, apply for the No Objection Letter (NOL) with the title, Certificate of Fitness, tenancy or SPA and council licence Invest Selangor for the state
4. Issuance Send MIDA a covering letter, the interim letter with Lampiran A and the no objection letter Your company
5. Certificate MIDA issues the manufacturing licence certificate MIDA

MIDA's post licensing checklist (2017 version) names the documents for issuance of a licence, whether new, an expansion at a new location, additional products or diversification: a covering letter, a copy of the interim letter and Lampiran A, and a no objection letter from the local authorities. In Selangor, Invest Selangor says MITI or MIDA requires a No Objection Letter from the Selangor State Government before the licence can be granted. The law firm Azmi & Associates puts the whole process at about 3 to 5 months, and notes that MIDA may visit the premises during its review.

What can you do while you wait?

The interim letter already counts for some purposes. MIDA's expatriate FAQ of 1 June 2026 accepts a manufacturing licence, an Interim Approval Letter or an ICA10 letter from manufacturing companies applying for expatriate posts. Fit-out, TNB works and council applications can run at the same time. Whether you may run trial production before the certificate is a question to put to MIDA in writing: we found no MIDA page that allows it, and the Act speaks of being "issued a licence".

For the tenancy itself, this means three things:

  1. Set the rent-free or fit-out period around the licence timeline, not only the renovation. Our factory relocation timeline shows how the other approvals overlap.
  2. Ask the landlord for copies of the title, the CF or CCC and any previous council licence before you sign, because the NOL file needs them.
  3. Make sure the tenancy is in your company's name and allows your process, since the agreement itself goes into the NOL file.

If your company is below both thresholds, it needs no licence. Even so, MIDA's FAQ lists a business licence from the local authority among the documents for its exemption confirmation letter, so the premises still have to be licensable. Our business premise licence guide covers that council step.

How do you confirm a licence is possible before you sign?

Run four checks on paper before you commit: the company test, the product, the ratios and the building. Most can be answered quickly if the landlord or seller hands over documents early.

  1. The company test, now and later. You need a licence at shareholders' funds of RM2.5 million or 75 full-time paid employees, under MIDA's guideline of 6 June 2024. If you will cross either line during the tenancy, plan for the licence from the start, because the building must then pass the NOL checks too.
  2. The product. Some products face extra limits, such as the deferred applications for upstream iron and steel. Our main licence guide lists them; call MIDA on 03-2267 3633 if yours is close.
  3. The ratios. The guideline asks for capital investment per employee (CIPE) of at least RM140,000, at least 80% Malaysian full-time staff, and either 25% managerial, technical and supervisory staff or 40% value added. CIPE counts fixed assets including 10 years of rent for land and building. Each RM10,000 of monthly rent therefore adds RM1.2 million to the sum, while a company with 100 full-time employees needs RM14 million in total. Run it with the rent you are about to sign.
  4. The building. Ask for what the NOL asks for: the land title or land conversion approval (check that the category and express condition allow industry), the Certificate of Fitness or CCC, and the council's view on whether your trade can get a business licence there. Our guides on light, medium and heavy industrial zoning and renting a factory without a CCC or CF explain what to look for.

Then ask the authorities directly. MIDA's charter commits to answering website enquiries within 3 working days, and the guideline gives investment@mida.gov.my for clarification. Describe the product, headcount, shareholders' funds and the address you are considering, and keep the reply. Invest Selangor takes enquiries through the "Talk To Us" form on its site. If you are buying, the wider approvals such as planning permission, DOE and Bomba are in our factory approvals guide.

Tenant and landlord checking the title, fitness certificate and tenancy papers before signing
IllustrationTenant and landlord checking the title, fitness certificate and tenancy papers before signing

Do you need a new manufacturing licence if you move factory?

No. A straight move is a post licensing application to change the factory location on your existing licence. MIDA's FAQ lists change of factory location among the amendments filed through InvestMalaysia, and says post licensing applications are processed within 30 days of complete information. The evaluation fee is RM750 on the fee list.

Three situations are often mixed up:

Your situation What MIDA calls it Fee
Moving all production to a new factory Change of factory location RM750
Same factory, address renamed or corrected Amendment of factory address RM750
Keeping the old factory and opening a second one Expansion, with a separate licence for the new place RM1,500

The second site needs its own licence because section 4(2) says one application may cover several places, but a separate licence shall be issued for each place of manufacturing activity. MIDA's checklist handles "expansion at new location" like a new licence at the issuance stage, with a no objection letter.

What else carries the old address?

  • Tax incentives. MIDA's licensing and incentive compliance page lists amendment of the Pioneer certificate for a change of location or factory address as a separate post incentive application.
  • Expatriate approvals. MIDA's FAQ says expatriate approvals issued before 15 June 2023 are amended, for example for a new factory address, through the Xpats Gateway under a new category.
  • Customs. A Licensed Manufacturing Warehouse is a separate Customs licence; see our LMW guide before you plan a move.
  • Council and state. A council business licence is issued for premises, so the new factory needs its own. The NOL documents are specific to the site (title, CF, tenancy), so ask Invest Selangor whether your move needs a fresh letter.

Apply as soon as the new address is fixed, and ask MIDA whether you may produce at the new site while the amendment is processed.

Can a manufacturing licence be transferred to a new owner?

It depends on what is sold: the building, the company or the business. The licence belongs to the manufacturer that holds it, and section 7(1) says no licence is transferable from a manufacturer to any person without the licensing officer's prior approval.

What changes hands What happens to the licence What to file with MIDA
The factory building only Stays with the seller's company; the buyer or new tenant needs its own Buyer: new licence or expansion at a new location. Seller: change of factory location or surrender
The company's shares Stays with the same company Check the conditions. Transfer of shares, change of board of directors and amendment or waiver of equity conditions are post licensing applications (RM750 each)
The business moves to another company Needs a transfer Transfer of manufacturing licence (RM750), with prior approval under section 7
Change of company name only Same licence Change of company name (RM750)

Buying the company that holds the licence

A share sale keeps the licence with the company, but read the licence and its Lampiran A first. MIDA's expansion and diversification page says equity and export conditions imposed before 17 June 2003 are maintained, and that companies may ask for them to be removed, with approval given on the merit of each case. If the target's licence carries an equity condition, build MIDA's approval or a waiver into the deal timetable. A certified true copy of the licence and Lampiran A costs RM500 under MIDA's fee FAQ. Our guide on selling company shares or the factory asset covers stamp duty and tax.

Moving the licence to another company

The checklist lists the documents for a transfer: a letter from the company with justification, the original licence (or the interim letter) with Lampiran A, a board resolution, and the SSM profiles of both the transferor and the transferee. Section 7(2) lets the licensing officer authorise a transfer on the holder's death, incapacity, bankruptcy or liquidation, when a receiver or manager is appointed, or where refusing would be unjust. A refusal can be appealed to the Minister within 45 days of the decision under section 13, and under section 14 the licence stays in force while that appeal is pending.

Do you need approval to add production lines or new products?

Yes, for both, and before you start. MIDA says a licensed company that wants to expand its production capacity or diversify its product range must apply.

  • More lines for the same product: an expansion application, for an existing licensed manufacturer increasing the capacity of its approved products (InvestMalaysia FAQ). RM1,500.
  • A new product: a diversification application. Section 7A(1) says a manufacturer shall not manufacture any product other than those specified in the licence without prior approval. RM1,500.
  • Same product, described differently: redefinition of product, a post licensing application at RM750.
  • A capacity or export condition in the way: amendment or deletion of conditions, RM750.
  • Dropping a product: you may suspend or stop it after notifying MIDA in writing (section 7A(2)).

If InvestMalaysia does not let you pick expansion or diversification, MIDA's FAQ says to update the Industrial Profile section first so MIDA can verify your approved record. The building side is separate: an extension or mezzanine needs council approval (see our illegal factory extension guide), and more machines usually mean more power, which our TNB power upgrade guide covers.

Technicians installing a new production line beside a running line inside a factory
IllustrationTechnicians installing a new production line beside a running line inside a factory

How long does each change take and what does it cost?

Application MIDA fee Published time
New manufacturing licence RM1,500 7 working days (fast track) or 60 (normal track), from complete information
Expansion, diversification or regularisation RM1,500 Ask MIDA which track applies
Change of location, address or company name; transfer of licence; transfer of shares; change of directors; conditions; consolidation; redefinition of product RM750 Within 30 days of complete information
Appeal against a licence decision RM750 Lodge within 45 days of the decision (section 13)
Certified true copy of licence and Lampiran A RM500 Not stated
Duplicate licence RM2,000 first request, RM3,000 second, RM5,000 third Not stated
Selangor NOL Not stated on Invest Selangor's page Not stated; ask Invest Selangor

Fees are from MIDA's March 2025 list and its fee FAQ; timelines are from the client charter and the FAQ. MIDA says there are no waivers and no refunds, including when an application is rejected or withdrawn, so check eligibility before you pay.

What happens if you change without approval?

  • Manufacturing without a licence, including at a new place that has none, is an offence under section 3.
  • Section 6 lets the licensing officer revoke a licence for breaching a condition, for no longer carrying on the licensed activity, or for a false statement in the application. If you close a factory for good, surrender of the licence is one of the post licensing applications MIDA lists.
  • Under section 10 the licensing officer may require returns, and failing to provide them on time is an offence.
  • Under section 19, directors and managers can be held liable for an offence committed by the company.

Common mistakes to avoid in a deal timetable:

  1. Planning the start of production around the renovation and forgetting the NOL and the certificate.
  2. Signing a tenancy before checking that the title, CF and council licence will pass.
  3. Buying a factory from a manufacturer and assuming its licence comes with it.
  4. Buying a company without reading the equity and export conditions in Lampiran A.
  5. Adding a product line and applying afterwards.

Frequently Asked Questions

Can I start production while waiting for my manufacturing licence?

If your company is above the threshold, the Act says you must be issued a licence before you engage in manufacturing. MIDA issues the certificate only after its approval letter, the state no objection letter and the other documents are in. The interim letter is enough to apply for expatriate posts, but ask MIDA in writing before any trial run.

Do I need a new MIDA licence if I move to another factory?

Not a new one if you move all production: apply for a change of factory location on InvestMalaysia, at RM750, processed within 30 days of complete information. If you keep the old factory and add a new one, the new place needs its own licence, because the Act requires a separate licence for each place of manufacturing.

Can a manufacturing licence be transferred to the buyer of my factory?

Not with the building. A licence can only move to another person with MIDA's prior approval under section 7, through a transfer application backed by a board resolution and the SSM profiles of both companies. A buyer of the building normally applies for its own licence instead.

If I buy a company that already has a manufacturing licence, is the licence still valid?

Yes, the licence stays with the company, because the company is the licensee. Check the licence conditions first: equity and export conditions imposed before 17 June 2003 remain unless MIDA removes them, and MIDA lists transfer of shares and change of directors as post licensing applications.

Do I need MIDA approval to add a production line?

Yes. More capacity for products already on your licence is an expansion application, and a new product is a diversification application; each costs RM1,500. Section 7A bars making products that are not on your licence without prior approval.

What is the difference between MIDA and MITI?

MITI, the Ministry of Investment, Trade and Industry, approves manufacturing licences under the Act, according to MIDA's approvals page. MIDA is the agency under MITI that receives the applications on the InvestMalaysia portal, so in practice you deal with MIDA.

How do I know a factory can get a manufacturing licence before I sign?

Check the company test and the ratios with the rent you are about to sign. Then ask the landlord or seller for the title or conversion approval, the CF or CCC and the council's view on your trade at that address. Put your case to MIDA in writing; its charter promises a reply to website enquiries within 3 working days.

What is the No Objection Letter from Invest Selangor?

It is the Selangor State Government's letter that MITI or MIDA requires before a manufacturing licence can be granted for a project in Selangor. You apply on Invest Selangor's NOL portal with the MIDA approval letter, the title or conversion approval, the CF, the tenancy or SPA and the council business licence, each certified by a company secretary or a commissioner for oaths.