Key Takeaways

  • On 13 November 2026, Menteri Besar Amirudin Shari tabled a RM3.3 billion Selangor Budget 2027: RM1.9 billion for operating spending and RM1.4 billion for development.
  • RM36.45 million goes to 47 flood mitigation projects under the Drainage and Irrigation Department (JPS), including RM9.15 million for the Sungai Klang basin. The Sungai Kapar Besar basin is also on the list.
  • Klang gets two named flood projects: a RM26 million flood retention pond at Sungai Jati, now at design stage, and RM25 million to continue river capacity works under the Selangor Maritime Gateway (SMG) programme, which is at 71.43% physical progress.
  • On water, the state lists the RM479 million Labohan Dagang Phase 2 treatment plant (200 million litres a day, built 2027 to 2029) and RM209.2 million for water grid links, with Klang among the districts on the routes.
  • Speed Selangor will cover more industrial and commercial projects, including solar farms and centralised labour quarters (CLQ), with a target of 9 days at the council One Stop Centre once a complete application is in.

What Selangor announced on 13 November

Amirudin tabled the budget at the State Legislative Assembly in Shah Alam. Of the RM3.3 billion, 57.6% is operating spending and 42.4% is development, and the state expects to collect RM2.85 billion in revenue next year, with land premiums making up over RM1.1 billion of it, according to FMT.

Flood control was the first pillar of the speech. The New Straits Times reported that the RM36.45 million funds 30 ongoing projects and 17 new ones under the Second Selangor Plan (RS-2). Of the 30 ongoing projects, 13 are complete and in final accounts, nine are being built, two are at pre-tender stage and six are at design stage. Media Selangor carried the full list of flood and drainage items:

Item Amount stated Notes
Flood mitigation projects under JPS (47) RM36.45 million 30 ongoing, 17 new under RS-2
Of which: Sungai Klang basin RM9.15 million Rest covers Sungai Buloh, Selangor, Bernam and Kapar Besar basins, plus design, survey and land work
Of which: Sungai Langat basin RM7.35 million
Drainage system projects (25) RM19.38 million
River basin development and management (16) RM17.9 million
Environmentally friendly drainage (9) RM6.63 million
Flood works under the Selangor Maritime Gateway (SMG) RM25 million 71.43% physical progress
Sungai Jati flood retention pond, Klang RM26 million Design stage

The water items came in a separate part of the speech, reported by Media Selangor: RM479 million for the Labohan Dagang Phase 2 water treatment plant, RM209.2 million for water grid connectivity, RM120.8 million to cut non-revenue water and RM559 million to replace 300 km of old pipes in 2027.

Why this matters for factories in Klang

Amirudin tied the flood money directly to business losses. Quoting the Department of Statistics' special flood impact report, he said the floods of late 2021 and early 2022 cost Selangor about RM3.1 billion, and that Klang district recorded the highest loss at RM1.2 billion, ahead of Petaling (RM1.1 billion) and Hulu Langat (RM400 million). The manufacturing sector lost RM884.5 million and the business sector RM396.4 million. Floods still cost Selangor RM52.9 million in 2025, he said, according to Media Selangor's Malay report.

The timing is not abstract. As of 9.30am on 13 November, 1,301 flood victims were sheltering at nine relief centres in Kuala Selangor and Hulu Selangor, Media Selangor reported.

The Sungai Jati retention pond

The RM26 million pond is meant to hold part of the water flow temporarily during heavy rain and take pressure off the drains downstream. It is still at design stage, so it will not help in this monsoon. The speech did not give the exact site, the size of the pond or a construction date. Jalan Sungai Jati runs through Taman Sentosa (postcode 41200) in south Klang, so owners and tenants of factories in south Klang should follow the design when Royal Klang City Council (MBDK) and JPS release it. Speaking about the pond and a drainage master plan for Hulu Langat, Amirudin said both "demonstrate why space for water must be planned before surrounding development is finalised."

SMG river works at 71.43%

The RM25 million under SMG, the state's Sungai Klang river programme, continues the work to raise river capacity and improve water flow. Amirudin said residents in affected areas must be told what work remains and when the flood protection is expected to start working. For a factory near the river, that date matters more than the allocation: until the works are finished, your own drainage, floor level and insurance are what protect your stock.

Sungai Kapar Besar basin

The Sungai Kapar Besar basin is one of the river basins covered by the RM36.45 million, although the budget did not break out its share. Kapar, north of Klang, is home to estates such as KIIP Kapar and Sungai Kapar Indah; see our Kapar industrial area page for what is there.

Developers who neglect retention ponds

After the tabling, Amirudin said the state has identified development projects whose developers did not maintain their retention ponds, and he has told the councils to order those developers to maintain and upgrade them or face a stop-work order, Media Selangor reported. JPS will rank 56 flood hotspots through a task force he will attend, and flood-risk areas will be announced every month, especially before the monsoon. The state also plans a public dashboard showing each flood project, the agency in charge and its stage.

Factory workers lift cartons onto raised racks as sandbags guard the shutter during heavy rain
IllustrationFactory workers lift cartons onto raised racks as sandbags guard the shutter during heavy rain

Water supply and approvals

Labohan Dagang Phase 2 will treat 200 million litres a day, with construction scheduled for 2027 to 2029. The water grid project (RM209.2 million) covers routes in Petaling, Gombak, Kuala Lumpur, Hulu Selangor, Klang, Hulu Langat, Sepang and Kuala Selangor, and aims to connect all 36 reservoir terminals by the end of 2028. A water-heavy plant, such as food processing, dyeing or industrial washing, should not count on new treatment capacity before then and should keep its own storage tanks.

On approvals, Media Selangor reported that Speed Selangor will be expanded to industrial and commercial developments, including solar farms, centralised labour quarters and circular economy projects. The target is a maximum of 9 days from the day a formal, complete development plan application reaches the local council's One Stop Centre (OSC), with KUSEL, utility providers and technical departments coordinating. A new Speed Rakyat policy extends business licences from one year to two for 122 types of business, such as restaurants, retail shops, mini marts, vehicle repair shops and education institutions, if applicants meet the council's criteria. The announcement did not say whether factory licences are among the 122.

What factory owners, tenants and buyers should do now

  1. Check your location against the hotspot list. When JPS publishes its priority list and the dashboard goes live, see whether your factory, or the one you plan to buy or rent, sits in or downstream of a hotspot.
  2. Ask for flood history before you sign. Ask the owner and neighbours whether the unit flooded in 2021 or since, and look at the floor platform level against the road. For registered sale prices and rents in the area, compare with the Klang and Port Klang transaction data.
  3. Read the lease. Tenants should check who repairs flood damage, whether rent stops while the unit cannot be used, and who insures the building and the stock.
  4. Plan extensions with complete papers. If you are planning a solar farm, a CLQ for your workers or an extension that needs development plan approval, the 9-day target only starts once the OSC has a complete application.
  5. Compare estates. If flooding keeps stopping your line, compare units on higher ground or in newer estates; our factories for rent in Klang cover Bukit Raja, Meru, Klang Jaya and other inland estates.

Frequently Asked Questions

How much did Selangor Budget 2027 set aside for flood mitigation?

The budget gives RM36.45 million to 47 flood mitigation projects under JPS, of which RM9.15 million is for the Sungai Klang basin and RM7.35 million for the Sungai Langat basin. A further RM25 million continues river works under the Selangor Maritime Gateway, and the Sungai Jati retention pond in Klang is a RM26 million project. Drainage projects add RM19.38 million.

Where is the Sungai Jati flood retention pond and when will it be ready?

The state says the RM26 million pond is in Klang and still at design stage. The budget speech did not give the exact site, its size or a construction date. Jalan Sungai Jati is in Taman Sentosa, 41200 Klang, so factory users in south Klang should watch for the design details from MBDK and JPS.

Does the 9-day Speed Selangor approval apply to factories and workers' quarters?

Speed Selangor will be expanded to industrial and commercial developments, and the state named solar farms and centralised labour quarters among them. The 9-day target counts from the day a complete, formal development plan application is submitted to the council's One Stop Centre. Incomplete papers, land title issues or zoning problems still slow a project down.

Will factory licences in Selangor now last two years?

Not necessarily. Speed Rakyat extends business licences to two years for 122 types of business, with examples such as restaurants, retail shops and vehicle repair shops, but the announcement did not say whether factory licences are included. Ask your council, such as MBDK in Klang, before your next renewal.

FactoryHub is dedicated to helping every client find the right factory or warehouse. For factories and warehouses in Klang and Port Klang, contact Peter Tan (REN 12771) at 016-666 6872 or Jason Low (PEA 1478) at 012-288 1834.