Key Takeaways
- An industrial effluent treatment system (IETS) is the plant that treats process wastewater before it leaves a factory. Under the Environmental Quality (Industrial Effluent) Regulations 2009, it must be designed and supervised by a professional engineer, notified to the Department of Environment (DOE) 30 days before work starts, and run with a DOE-certified competent person on duty.
- Treated effluent that goes into a drain, river or the sea must meet Standard A (upstream of a listed drinking water intake) or Standard B (everywhere else). BOD, for example, is capped at 20 mg/L under Standard A and 50 mg/L under Standard B; oil and grease at 1.0 and 10 mg/L.
- A drain counts as "inland waters" under the Environmental Quality Act 1974. Since 7 July 2024, polluting inland waters in breach of the acceptable conditions carries jail of up to five years plus a fine of RM50,000 to RM10 million.
- Connecting to a public sewer needs the prior written permission of the National Water Services Commission (SPAN), and "prohibited effluent" (for example BOD above 250 mg/L, COD above 500 mg/L, oil and grease above 50 mg/L, heavy metals or scheduled waste) may not go into any sewer without SPAN's approval.
- Before you rent or buy a factory with a wet process, ask for the DOE notification, the engineer's declaration, as-built drawings, monthly discharge records, the competent person's certificate, sludge records and, in Selangor, the LUAS licences. Also find out whether the unit drains to a septic tank or an IWK sewer.
This guide covers the federal rules on factory wastewater and what to check in a building. Selangor's own licensing under the Zero Discharge Policy is covered in our guide to the LUAS door to door checks, and the full approval sequence for a new factory is in our factory approvals guide. This is general information, not legal advice.
What is an industrial effluent treatment system (IETS)?
The 2009 Regulations define an industrial effluent treatment system as "any facility including the effluent collection system, designed and constructed for the purpose of reducing the potential of the industrial effluent or mixed effluent to cause pollution." In plain terms, it is everything between the machine that makes dirty water and the point where treated water leaves the site: collection drains and sumps, an equalisation tank, chemical dosing, settling or flotation, biological tanks, sludge handling and the final discharge point.
Industrial effluent, sewage and mixed effluent: what is the difference?
| Term | Definition in the 2009 Regulations | Typical source in a factory |
|---|---|---|
| Industrial effluent | Liquid waste or wastewater from a manufacturing process, including treatment of water for water supply, or any activity at industrial premises | Washing, rinsing, plating, dyeing, food processing, printing, cooling and boiler blowdown |
| Sewage | Liquid waste containing human, animal, domestic or putrescible matter | Toilets, showers, pantry sinks |
| Mixed effluent | Wastewater containing both industrial effluent and sewage | A plant that combines its process and toilet drains |
The difference matters because each goes to a different regulator. Sewage from toilets usually goes to a septic tank or the public sewer run by Indah Water Konsortium (IWK). Industrial effluent is DOE's business, and in Selangor also the Selangor Water Management Authority's (LUAS).
Which laws apply to factory wastewater in Malaysia?
| Where the wastewater goes | Main law | Who enforces it | What it controls |
|---|---|---|---|
| Drain, river, sea or soil | Environmental Quality Act 1974 and the Industrial Effluent Regulations 2009 | DOE | Notification, IETS design and operation, Standard A or B, monitoring, sludge, spills |
| Public sewer or septic tank | Water Services Industry Act 2006 and the Prohibited Effluent Regulations 2021 | SPAN, with IWK as the sewerage operator | Permission to connect, banned substances and limits for what goes into sewers |
| Any discharge in Selangor | LUAS Enactment 1999 and its 2024 licensing regulations | LUAS | Licences for how much water is discharged and what it contains |
| Sludge from the IETS | Scheduled Wastes Regulations 2005 | DOE | Storage, labelling and disposal through licensed contractors |
When does a factory need an effluent treatment system?
The 2009 Regulations apply to any premises that discharges or releases industrial effluent or mixed effluent onto or into soil, inland waters or Malaysian waters, except premises listed in the First Schedule. That schedule lists:
- Crude palm oil mills.
- Natural rubber processing.
- Mining.
- Processing, manufacturing, washing or servicing that produces less than 60 cubic metres of effluent a day.
- Processing, manufacturing, washing or servicing whose effluent contains no oil and grease and none of parameters (v) to (xv) of the Fifth Schedule (mercury, cadmium, chromium, arsenic, cyanide, lead, copper, manganese, nickel and tin).
- Processing, manufacturing, washing or servicing whose BOD or suspended solids load does not exceed 6 kg a day (a concentration of 100 mg/L).
How an exemption applies to your process is a question to settle with the state DOE office in writing before you rely on it, because the penalties fall on the owner or occupier, not on the consultant who advised them.
Which factories usually need one and which usually do not?
- Usually need treatment: food and beverage processing, metal finishing and electroplating, textile dyeing, printing, chemical blending, industrial laundries, vehicle washing and any process that uses water and lets it out with oil, metals, dyes or organic load.
- Usually do not: a dry warehouse, a logistics hub or an assembly plant whose only wastewater is from toilets and a pantry. That is sewage, handled through a septic tank or the IWK sewer.
- Somewhere in between: factories that recycle all process water or send their liquid waste away by tanker. Note that the DOE notification form itself asks whether effluent goes to a watercourse, a sewer, recycling or elsewhere, so DOE expects you to declare the route either way.
Standard A or Standard B: which limits apply?
Standard A applies to inland waters within the catchment areas in the Sixth Schedule, which are areas upstream of public water supply intakes. Standard B applies to all other inland waters and Malaysian waters. In Selangor, the listed intakes include points on Sungai Selangor (including Rasa and Batang Berjuntai), Sungai Langat, Sungai Semenyih, Sungai Labu, Sungai Batang Kali, Sungai Buloh, Sungai Gombak and the Subang dam. A factory upstream of one of them faces the stricter limit, so ask DOE which standard applies to your discharge point before you design anything.
A selection of the Fifth Schedule limits:
| Parameter | Standard A | Standard B |
|---|---|---|
| Temperature | 40°C | 40°C |
| pH | 6.0 to 9.0 | 5.5 to 9.0 |
| BOD at 20°C | 20 mg/L | 50 mg/L |
| Suspended solids | 50 mg/L | 100 mg/L |
| Oil and grease | 1.0 mg/L | 10 mg/L |
| Ammoniacal nitrogen | 10 mg/L | 20 mg/L |
| Copper | 0.20 mg/L | 1.0 mg/L |
| Nickel | 0.20 mg/L | 1.0 mg/L |
| Zinc | 2.0 mg/L | 2.0 mg/L |
| Colour | 100 ADMI | 200 ADMI |
COD limits are set by industry in the Seventh Schedule: 80 mg/L under Standard A and 200 mg/L under Standard B for "other industries", 80 and 250 mg/L for textiles, and 400 mg/L for fermentation and distillery under both standards.
How do you set up an IETS, step by step?
- Characterise the effluent. The DOE notification asks for an Industrial Effluent Characterisation Study (IECS) report, a process flow chart showing where effluent is generated, and the flow rate.
- Appoint a professional engineer. Regulation 5 requires a professional engineer to design the system and supervise its construction, following DOE's Guidance Document on the Design and Operation of Industrial Effluent Treatment System.
- Notify DOE before work starts. Regulation 4 requires written notification in the Second Schedule form 30 days before work that creates a new discharge, a change of machinery that materially changes the discharge, or an upgrade of an existing IETS.
- Mark the discharge point. Regulation 17 requires the final discharge point to be shown on layout plans certified by a professional engineer and submitted 30 days before the premises starts operating.
- Declare and submit as-built drawings. The owner or occupier and the engineer sign the Third Schedule declaration, and as-built drawings go to DOE within 30 days of the premises starting operation.
- Put a competent person on duty. Regulation 10 requires a person certified by DOE to supervise the IETS whenever it runs. The Environment Institute of Malaysia (EiMAS) runs the CePIETSO courses for biological processes and for physical chemical processes; its FAQ lists the biological course fee at RM5,000.
- Monitor and report monthly. Regulation 7 requires flow meters and sampling equipment, monitoring of COD and the Fifth Schedule parameters, and monthly records submitted to DOE within 30 days after the end of each month.
- Keep records and train staff. Regulations 9, 27 and 28 require performance monitoring of each treatment unit, records of operation and maintenance, and training records for every employee who works on the system.
- Manage the sludge as scheduled waste. Metal-bearing sludge is listed as SW 204 under the Scheduled Wastes Regulations 2005, which allow storage on site for up to 180 days and 20 tonnes before it goes to a licensed contractor.
Which rules catch factories out most often?
- By-pass pipes. Regulation 18 bans any diversion of effluent around any part of the IETS.
- Dilution. Regulation 19 bans adding outside water to effluent to make it less concentrated.
- Sludge in the drain. Regulation 21 bans discharging sludges, inflammable solvents, tar or sawdust, and regulation 23 bans dumping IETS sludge on land or in water without DOE's written permission.
- Spills. Regulation 20 requires DOE to be told within six hours of a spill or leak that may reach soil or water.
- Quiet changes. A new production line that changes the volume or quality of effluent needs a fresh notification under regulation 4.
Can a factory discharge wastewater into a drain or the public sewer?
Into a monsoon drain
The Environmental Quality Act defines inland waters as "any reservoir, pond, lake, river, stream, canal, drain, spring or well". Section 25 bars anyone, unless licensed, from discharging pollutants or wastes into inland waters in breach of the acceptable conditions. Since the Environmental Quality (Amendment) Act 2024 took effect on 7 July 2024, a conviction under section 25 means imprisonment of up to five years and a fine of RM50,000 to RM10 million. The drain outside your factory is therefore not a disposal route for untreated process water.
Into the public sewer
Under section 60 of the Water Services Industry Act 2006, no one may connect a private pipe, drain or sewer to a public sewer or public sewage treatment plant without SPAN's prior written permission; the penalty is a fine of up to RM50,000, up to six months' jail, or both. SPAN may refuse a connection if the sewer or treatment plant lacks capacity.
The Water Services Industry (Prohibited Effluent) Regulations 2021, in force since 1 December 2021, list what may not go into a sewer without SPAN's approval:
| Parameter | Limit for discharge into a sewer |
|---|---|
| Temperature | 40°C |
| pH | not lower than 6.0, not higher than 9.0 |
| BOD | 250 mg/L |
| Suspended solids | 300 mg/L |
| COD | 500 mg/L |
| Total nitrogen | 50 mg/L |
| Ammoniacal nitrogen | 30 mg/L |
| Total phosphorus | 10 mg/L |
| Oil and grease | 50 mg/L |
The schedule also bans heavy metals, acids with a pH below 6.0, concentrated plating solutions, scheduled waste, toxic substances, pesticides, strongly coloured dye waste and grease that can block sewers. A food factory with high oil and grease, or a plating line, will usually need pre-treatment or SPAN's approval before anything reaches the sewer. The Water Services Industry (Amendment) Act 2025 extended the ban to all sewers, public or private, added septic tanks, and raised the maximum penalty to RM1 million or ten years' jail.
What IWK charges an industrial premises
According to IWK's industrial charges page, industrial premises pay by headcount: RM2.00 per employee a month with septic tank services and RM2.56 with a connected sewer, with a minimum of ten employees (RM20.00 or RM25.60 a month). IWK's FAQ for commercial and industrial customers says owners must send an updated headcount declaration every six months, that the owner and occupier are jointly liable for the charges, and that a premises is on a connected service if there is a single rectangular inspection chamber cover outside, while a septic tank usually has two to four metal lids.
What should a tenant or buyer check in the building?
| Check | What to ask for or look at | Why it matters |
|---|---|---|
| Where wastewater goes now | Drainage layout, inspection chamber or septic tank lids, the final discharge point | Tells you which regulator and which limits apply |
| Existing IETS paperwork | DOE notification, Third Schedule declaration, as-built drawings, discharge point layout | Shows the system was built as notified |
| Recent performance | The last 12 monthly discharge records and lab results | Exposes a system that already fails Standard A or B |
| Competent person | Name and CePIETSO certificate of whoever supervises the IETS | Required whenever the system runs |
| Sludge | Scheduled waste records and the contractor used | Unpaid or missing sludge disposal becomes your problem |
| DOE licence, if any | Any licence to exceed the acceptable conditions | Under regulation 26, its conditions bind a new occupier for 14 days, or until a transfer applied for in that time is decided; the transfer fee is RM100 |
| Selangor licences | LUAS licences and any LUAS notice | LUAS gives premises it identifies 14 days to respond, The Star reported |
| Red flags | By-pass pipes, stained drains, a DOE prohibition order posted on site | Each is an offence that follows the operator |
Lease and sale clauses to settle before you sign
- Who owns the IETS, who maintains it and who pays for upgrades if your process needs a bigger system.
- Whether the landlord's earlier DOE and LUAS filings cover your process, or you must notify afresh.
- Reinstatement at the end of the lease: tanks, sumps and pipework are expensive to remove.
- For buyers, add these documents to the factory due diligence checklist, and confirm the land and building approvals allow your industry.
How a factory differs from a house
A house only produces sewage, billed by IWK on the domestic tariff. A factory may produce industrial effluent that DOE regulates through the 2009 Regulations, SPAN regulates once it enters a sewer and, in Selangor, LUAS licenses. IWK bills industrial premises by headcount rather than by the property's annual value. Food factories should also read our food processing factory requirements.
What happens if the rules are broken?
| Offence | Maximum penalty |
|---|---|
| Breaching most duties under the 2009 Regulations (regulation 32) | Fine up to RM100,000 or up to five years' jail or both, plus up to RM1,000 a day after a notice to stop |
| Polluting inland waters, including drains (EQA section 25, from 7 July 2024) | Jail up to five years and a fine of RM50,000 to RM10 million |
| Prohibited effluent into any sewer or septic tank (WSIA section 61, as amended in 2025) | Fine up to RM1 million or up to ten years' jail or both |
| Connecting to a public sewer without permission (WSIA section 60) | Fine up to RM50,000 or up to six months' jail or both |
DOE may also issue a prohibition order under regulation 30 that stops a plant or process until the remedial measures it directs are done. Not every factory needs an environmental impact assessment: under section 34A of the Act, an EIA is required only for activities prescribed by order, such as the development of an industrial estate of 20 hectares or more under the EIA Order 2015.
If your process produces wastewater, tell us the flow and what is in it before you shortlist units. Through find me a factory we look for buildings with the space, drainage and paperwork your process needs.
Owners in Klang can read Ms Teh Seok Hoon's notes on effluent rules for Klang factories, and Jason Low explains how the Industrial Effluent Regulations 2009 apply to factories in Rawang.
Frequently Asked Questions
Which industrial parks provide centralised wastewater treatment?
There is no public list of parks with a central industrial wastewater plant, so assume you will need your own treatment system unless the park manager confirms one in writing. Even under Selangor's managed industrial park guideline, a central industrial wastewater treatment plant is only an optional component. Ask what effluent it accepts and what it charges. If there is none, budget for an IETS designed by a professional engineer and notified to DOE, and check whether Standard A or B applies to the lot.
What is IETS in Malaysia?
IETS stands for industrial effluent treatment system, the facility that collects and treats process wastewater so it can be discharged within legal limits. Under the Environmental Quality (Industrial Effluent) Regulations 2009, it must be designed and supervised by a professional engineer, notified to DOE before construction and run with a DOE-certified competent person on duty.
What is the standard for industrial effluent discharge in Malaysia?
The Fifth Schedule of the 2009 Regulations sets two standards. Standard A applies upstream of listed drinking water intakes and Standard B applies elsewhere. BOD is limited to 20 mg/L under Standard A and 50 mg/L under Standard B, suspended solids to 50 and 100 mg/L, and oil and grease to 1.0 and 10 mg/L.
What is an industrial effluent?
The 2009 Regulations define it as any liquid waste or wastewater generated from a manufacturing process, including the treatment of water for water supply, or from any activity at industrial premises. Toilet and pantry water is sewage, and a stream that combines both is called mixed effluent.
Does a warehouse need an effluent treatment system?
A dry warehouse whose only wastewater comes from toilets and a pantry produces sewage, not industrial effluent, so it normally relies on a septic tank or the IWK sewer instead of an IETS. A warehouse that washes vehicles, drums or products, or repacks liquids, may produce industrial effluent and should check with DOE before starting.
Can I discharge factory wastewater into the IWK sewer?
Only with SPAN's prior written permission to connect, and only if the wastewater is not prohibited effluent. Discharges above limits such as BOD 250 mg/L, COD 500 mg/L or oil and grease 50 mg/L, or containing heavy metals or scheduled waste, need SPAN's approval, and breaking this rule carries a fine of up to RM1 million or ten years' jail since the 2025 amendment.
Who is responsible for the IETS, the landlord or the tenant?
The 2009 Regulations place most duties on the "owner or occupier" of the premises, so both can be exposed. In practice the operator that generates the effluent runs the system, but the lease should say who owns, maintains and upgrades the IETS, and who holds the DOE and LUAS filings.
Is EIA mandatory in Malaysia?
Only for activities prescribed under section 34A of the Environmental Quality Act, which are listed in the EIA Order 2015, such as developing an industrial estate of 20 hectares or more. Most single factories in existing industrial parks do not need an EIA but still have to follow the effluent, scheduled waste and notification rules.