Key Takeaways
- You can sublet a factory or warehouse in Malaysia only as far as your tenancy agreement allows. Where a registered lease says nothing, the National Land Code implies a promise not to sublet or part with possession without the landlord's prior written consent, and that consent may not be unreasonably withheld.
- Subletting without consent is a breach that can end your tenancy, and your sub-tenant's tenancy ends with it. An owner whose factory is charged to a bank also needs the bank's written consent before letting any part of it.
- Every partition needs the council's prior written permission under section 79 of the Street, Drainage and Building Act 1974. MBSJ, for example, charges RM10 per 9 m² of partitioned floor (minimum RM100) plus RM100 a year, and its permit lasts one year.
- A split unit must still give each part at least two exits within the permitted travel distance, each occupier needs its own business licence, and the fire insurer must endorse the change of occupation before a loss, or cover on the affected property can cease.
- Give each occupier its own TNB meter and account. Supplying electricity to another person without an Energy Commission licence carries a fine of up to RM100,000, and a company in Johor Bahru was fined RM10,000 in 2023 for supplying its tenants.
This guide is for two readers: a tenant who wants to let part of a rented factory or warehouse to another business, and an owner who wants to divide one unit into spaces for two occupiers. It walks through the land law, the landlord's and the bank's consent, council and Bomba rules for partitions, insurance, electricity meters, stamp duty and service tax. It is general information, not legal or tax advice; ask a lawyer to read your own agreement and title before you sign anything.
What does sublet mean for a factory or warehouse?
To sublet is to let all or part of a property you rent to someone else while you stay the tenant. You become the sub-landlord, the other business becomes your sub-tenant, and your own landlord remains the head landlord. Another word for sublet is sublease or underlet. In Selangor's land registry a registered sublease is a pajakan kecil, and Malay templates call the agreement a perjanjian subsewaan.
The National Land Code (Act 828) sorts every letting by its length:
| Arrangement | Term | How it is made | NLC section |
|---|---|---|---|
| Tenancy or subtenancy | Up to 3 years | By word of mouth or a written document in any form; not registered on the title | s.223 |
| Lease granted by the owner | More than 3 years; up to 99 years for the whole land, 30 years for a part | Form 15A, registered at the land office | s.221 |
| Sublease granted by a lessee | More than 3 years; up to 30 years for a part | Form 15B, registered at the land office | s.222 |
Section 228A adds that a "part" of land includes a part of a building, so one bay of a factory can be let on its own. A registered lease or sublease of part of the land needs a plan and description that identify the part. The PTG Selangor checklist for Pajakan and Pajakan Kecil also asks for the original title, this year's quit rent and assessment receipts, the original stamp certificate, the consent letters described below, and charges a late penalty if the form reaches the office more than three months after it was witnessed.
Is subletting a factory allowed in Malaysia?
Yes, but only within the limits of your own agreement and with the consents the law requires.
Your tenancy agreement decides first
Under section 225(1)(c) of the National Land Code, a tenant's or lessee's power to sublet is subject to the express and implied terms of its own lease or tenancy. So the subletting clause is the starting point. Read it for three things: whether subletting is banned outright, whether it is allowed with the landlord's prior written consent, and whether it treats letting to a related company differently.
If a registered lease is silent
Section 231(1)(d) implies into every registered lease, unless it says otherwise, a promise by the lessee "not to transfer or charge the lease, or sublet or otherwise part with the possession of the demised property, without the prior consent in writing of the lessor (which consent shall not be unreasonably withheld)". Section 231(2) puts the same promise into every registered sublease. For a tenancy of three years or less, rely on what the agreement says and get written consent anyway: it is your proof if the landlord later objects.
If the owner has a bank loan on the factory
Section 226 is the rule many owners miss. Where land is charged, the owner cannot grant any lease, sublease or tenancy without the chargee's consent, and for a tenancy that consent must be in writing, signed by the bank or its authorised agent. An owner who splits a mortgaged factory and lets one half should get the bank's letter first.
If the title carries a restriction in interest
Some titles carry a restriction in interest that needs the State Authority's consent for dealings in the land. PTG Selangor's checklist asks for the state's consent letter for a registered lease or sublease when the title has such a restriction, and for the consent of any caveator, chargee or head lessee. Our state consent guide explains how that application works.
What the landlord's consent letter should say
A one-line "no objection" invites disputes later. Ask for a letter that names the sub-tenant, marks the area on a plan, states the permitted use, confirms that the sub-tenancy ends before your own tenancy, and says who applies for partition permits, licences and meters. Give your sub-tenant a copy: it is the only proof they have that the arrangement is lawful.
What happens if you sublet without permission?
The National Land Code spells out the consequences, and they fall on both you and your sub-tenant:
- Forfeiture. Under section 234(1), every lease, sublease or tenancy becomes liable to forfeiture if the tenant breaches any of its express or implied terms, unless the agreement provides otherwise.
- Notice first. Section 235 says the landlord cannot enforce forfeiture until it serves a written notice that names the breach, asks you to remedy it if it can be remedied, and (except for unpaid rent) asks for compensation, and you then fail to do so within a reasonable time.
- Your sub-tenant goes too. Section 236 says forfeiture also extinguishes every derivative sublease or tenancy. The sub-tenant who fitted out its half of your factory loses its right to stay.
- Relief from the court. Under section 237 you can apply to court for relief against forfeiture, and the court may grant it on terms.
- Waiver. Under section 234(3), a landlord who knowingly accepts rent falling due after the breach, or otherwise acts as if the tenancy continues, waives the right to forfeit for that breach, unless a forfeiture action has already started.
A surrender is different from forfeiture. If you give up your tenancy by agreement, section 239(5) keeps the sub-tenancy alive as if the head landlord had granted it. And while the sub-tenancy runs, you stay liable to your landlord: section 230(3) makes a sublessor pay the rent under its own lease, and lets a sublessee who pays that rent set it off against the rent it owes the sublessor.
Can an owner split one factory into two units?
To rent the parts out
Yes. Sections 221, 223 and 228A let an owner lease or let part of the land, including part of a building. A registered lease of part is capped at 30 years and needs a plan of the part. The physical split, however, still needs council approval (next section), and the land's conditions and planning approval must allow what each occupier will do there.
To sell one part
Selling half of a factory needs separate titles. Under section 135 the land must be subdivided with the approval of the State Director (Registry title) or the Land Administrator (Land Office title). Section 136 refuses approval unless the subdivision does not contravene any restriction in interest, complies with written law and has the necessary planning approval.
Do you need council approval to partition a factory?
Yes. Section 79 of the Street, Drainage and Building Act 1974 says no person shall erect, or cause or permit to be erected, in any building "any partition, compartment, gallery, loft, roof, ceiling or other structure" without the council's prior written permission. The owner is presumed to have done the work unless proved otherwise. The council may enter and remove an unapproved partition and recover the cost of demolition, removal and storage from the owner, and the offence carries a fine of up to RM500 plus up to RM100 for each day it continues after conviction.
How Selangor councils handle partitions
The MBSA licence checklist (amended 29 August 2025) requires a Permit Binaan Sementara for partition walls, awnings, openings in a party wall or cabins in shop offices and in terrace, semi-detached and detached factories, using MBSA's standard plan book or a consultant's plan. For those factories it also sends added partitions, sheds and extra space at the front, side or back to the One Stop Centre as amendment plans. The approval letter is then one of the documents for the business licence.
MBSJ publishes its fees and conditions in its partition permit form (amended June 2017, when the council was still MPSJ):
| Item | MBSJ rule |
|---|---|
| Premises covered | Shop offices, terrace factories, shophouses and retail lots |
| Size limit for the standard plan route | Up to 300 m² (3,000 sq ft); larger works need a normal building plan from an architect |
| Tenant applicants | Tenancy agreement plus the owner's signed consent form |
| Partition fee | RM10 per 9 m² of floor area, minimum RM100 |
| Opening in a party wall | RM200 per 3 m of opening, minimum RM200 |
| Annual permit | RM100 per lot, paid again at each renewal |
| Standard plan | RM100 per plan |
| Validity | Temporary, one year |
| Materials | Non-combustible, such as gypsum board, aluminium and glass |
| Smallest room | 6.5 m² (70 sq ft) |
| Built before approval | Penalty of one extra plan processing fee |
| Works over 1,000 sq ft | A civil engineer certifies party wall openings and the existing structure |
Work may start only after approval, and the permit requires the partition to meet Bomba's conditions. Each business that occupies a part then applies for its own licence: MBSA's checklist asks for a stamped tenancy agreement, the CF or CCC, a floor plan in square metres and the partition permit letter. See our business premise licence guide for the full list.
What do Bomba rules mean for a partitioned factory?
A new wall changes how people escape. By-law 166 of the Uniform Building By-Laws 1984 requires at least two separate exits from each storey, sited within the travel distances of the Seventh Schedule and "readily accessible at all times". By-law 138A requires every partition to meet Part IX of the Ninth Schedule, and by-law 139 requires fire resisting separation around high risk areas such as a boiler room, hazardous storage, LPG storage or a transformer room. If your sub-tenant's process brings one of these, the split has to provide it.
The Fire Services Act 1988 treats a bad split as a fire hazard. Its definition includes an unlawful alteration that makes escape materially more difficult, inadequate means of exit, and the removal of required fire fighting equipment. Under section 8, Bomba can serve a fire hazard abatement notice on the occupier who caused it, or on the owner.
If the building is a designated premises that needs a fire certificate, section 32(2) requires the occupier to notify the Director General before starting a material change, and section 33, as amended by Act A1568, makes the owner liable to a fine of up to RM50,000, five years' jail or both when no fire certificate is in force. Our Bomba requirements guide explains which buildings need one.
How should insurance work when you sublet part of a factory?
Fire policies are written for the occupation declared at the start. A typical Malaysian wording, the RHB fire insurance policy, says under its "Change in Risk" condition that the insurance ceases to attach to the property affected if the trade or manufacture carried on is altered, or the nature of the occupation changes in a way that increases the risk of fire, unless the insurer agrees by endorsement before any loss.
In practice:
- The owner tells the insurer of the building policy who the new occupier is and what it does, and keeps the endorsement.
- The head tenant does the same for its own contents and liability policies.
- The sub-tenant insures its own stock, machinery and public liability, and names the parties the sub-tenancy requires.
Our guide to factory insurance for landlords and tenants covers who insures what in a lease.
Can two occupiers share one TNB meter?
This is the part of a split that can become a criminal offence.
- The account holder pays everything. TNB's contract terms make the consumer fully responsible for all bills registered in its name, and say that in multi tenanted premises the landlord's supply and each tenant's supply will be separately metered and billed by TNB, with the owner providing the rising and lateral mains.
- Bulk supply needs a licence. TNB's Electricity Supply Application Handbook gives the owner of multi tenanted premises two options: individual supply to the landlord and each tenant under TNB's connection schemes, or bulk supply, which needs a public distribution licence from the Energy Commission.
- Selling power without a licence is an offence. Section 9(1)(b) of the Electricity Supply Act 1990 forbids anyone other than a supply authority to supply electricity to another person without a licence, and section 37(5) sets a fine of up to RM100,000 plus up to RM1,000 a day. The Energy Commission's prosecution report records that Pioneer Heritage Sdn Bhd pleaded guilty in the Johor Bahru Sessions Court on 28 August 2023 to supplying electricity to tenants without a licence and was fined RM10,000.
| Option | What it involves | Risk |
|---|---|---|
| Separate TNB supply for each part | The owner arranges wiring and meter positions to TNB's connection scheme for multi tenanted premises; each occupier holds its own account | Cleanest; each occupier pays its own deposit and bill |
| Sub-tenant takes over an existing separate meter | TNB Change of Tenancy: form, ID, company registration, proof of occupancy, a deposit of two months' electricity, RM10 stamp duty and a processing fee of RM3 (low voltage) or RM80 (medium and high voltage) (myTNB) | Low |
| One TNB account shared through private check meters | Head tenant stays liable for the whole bill and recharges the sub-tenant | Supplying another person can breach section 9; ask the Energy Commission before relying on it |
Stamp duty and service tax on a sub-tenancy
Stamp duty. The Stamp Act 1949 defines a lease to include "any undertaking in writing to cultivate, occupy, or pay or deliver rent for, immovable property", so a written sub-tenancy is stamped like any tenancy. The council and TNB will ask for the stamped copy. Our tenancy stamp duty guide has the rates, and the tenancy stamp duty calculator works out the figure.
Service tax. When you sublet, you are the one providing a rental service. Rental and leasing services are taxed at 8% in law, effectively 6% from 1 January 2026, and registration is compulsory once taxable rental exceeds RM1 million in 12 months (MOF Fiscal Outlook 2026). The 6% comes from Customs Service Tax Policy 2/2025 (Amendment No. 3), which grants a 2% exemption on the rate from 1 January 2026. The same policy exempts tenants with annual sales up to RM1.5 million who register on MyPMK, and exempts rental between companies in the same group. A group here means a company holding more than 50% of the other's paid-up capital, or 20% to 50% with the power to appoint or remove most of its directors. That makes letting part of your factory to a sister company simpler than letting it to an outsider.
Checklist before you sublet or split a factory
- Read the subletting, alterations and use clauses of your tenancy agreement.
- Get the landlord's written consent naming the sub-tenant, the area, the use and the term.
- Owners with a loan: get the bank's written consent. Registered leases on a restricted title: check whether the state's consent is needed.
- End the sub-tenancy before your own tenancy ends, and give the sub-tenant a copy of the consent.
- Have a registered draughtsman or architect draw the partition, and get the council permit before building.
- Check that each part keeps two exits within travel distance; notify Bomba first if the building holds a fire certificate.
- Have the insurer endorse the policy for the new occupier.
- Arrange a separate TNB supply or change of tenancy for each occupier.
- Stamp the sub-tenancy agreement; the sub-tenant then applies for its own business licence.
- Check whether you must register for service tax, or whether an exemption applies.
Frequently Asked Questions
Is sublet allowed in Malaysia?
Yes, if your tenancy agreement allows it and you have the consents the law requires. Section 225 of the National Land Code makes a tenant's power to sublet subject to its own agreement, and a registered lease that is silent implies that you need the landlord's prior written consent, which cannot be unreasonably withheld. An owner whose land is charged also needs the bank's written consent.
What happens if you sublet without permission?
It is a breach that makes your tenancy liable to forfeiture under section 234 of the National Land Code, after the landlord serves a written notice under section 235 and you fail to remedy it. Forfeiture also extinguishes your sub-tenant's tenancy under section 236. You can apply to court for relief against forfeiture.
What is the difference between a lease and a sublease?
A lease is granted by the owner of the land; a sublease is granted by a lessee out of its own lease. In Malaysia both are registered only when they run for more than three years (Form 15A for a lease, Form 15B for a sublease). Lettings of three years or less are tenancies or subtenancies, which need no registration.
What are the disadvantages of a sublease?
The sub-tenant has no contract with the owner, so its right to stay depends on the head tenancy: if that is forfeited, the sub-tenancy ends too. The head tenant stays liable for the full rent and every covenant to its landlord. Both sides also carry the work of partition permits, separate licences, insurance endorsements and meters.
What is the meaning of sublet in Malay?
People in Malaysia often just say "sublet". Selangor's land registry calls a registered sublease pajakan kecil (Form 15B), and Malay agreement templates use perjanjian subsewaan.
Can I divide my factory into two units and rent them out separately?
Yes, the National Land Code lets an owner let part of a building. You still need written council permission for the partition under section 79 of the Street, Drainage and Building Act 1974, two exits for each part, the bank's consent if the factory is charged, and a separate TNB supply for each occupier. Selling one half needs a subdivision of the title.
Do I need a separate TNB meter for a sub-tenant?
It is the safe route. TNB meters and bills each tenant separately in multi tenanted premises, and supplying electricity to another person without an Energy Commission licence is an offence with a fine of up to RM100,000. If you plan to share one account, take advice from the Energy Commission first.
Does a sub-tenancy agreement need to be stamped?
Yes. The Stamp Act 1949 treats any written undertaking to occupy or pay rent for immovable property as a lease, so the sub-tenancy is stamped like a tenancy. The council's licence checklist and TNB both ask for the stamped agreement.
FactoryHub is dedicated to helping every client find the right factory or warehouse. If you are planning to sublet part of a factory or warehouse, or divide one, call or WhatsApp Peter Tan (REN 12771) at 016-666 6872 or Jason Low (PEA 1478) at 012-288 1834 before you sign.